You are on page 1of 6

www.revay.com VOL. 7 No.

1, May 1988

By Steve Revay
2. Why was there an increase in the cost However, it is only now that it has gained
of the contractor? the required maturity. RAL, under the
leadership of Mrs. Tardif, made major
Additionally, the answer to the second advances in computerizing the analysis,
question, more often than not, depends thereby rendering it both cost-effective
on the answer to the first. (depending on the records available) and
capable of being used even on the most
Simply stated, seldom can one escape the complex projects.
necessity of undertaking a delay analysis
when trying to find an answer to a The last page of this issue is devoted to
construction dispute. On the other hand, another important development in our
A large majority of construction disputes the techniques available for such analysis corporate life. This again is not a new
today centre around two questions: did not keep up with the ever-increasing step: we offered this service in the past;
complexities of the projects built today. but with Michael Tucker joining us, we
1. Who caused how much delay? and, The method described by Mrs. Lorna now have a solid base on which we can
Tardif in the lead article is not new; in fact, build a strong team, with a view to
it has been around for about ten years. servicing the surety industry.

DELAY ANALYSIS USING THE "SNAPSHOT" TECHNIQUE


by Lorna M. Tardif, Eng., MBA,

In delay claims the conventional analysis a few. There may be more than one amount of delay may undermine the
method requires the prior identification of cause of delay occurring at the same entire analysis.
delay causes. The "snapshot" technique time. It quickly becomes an almost
provides an alternative method whereby a insurmountable task to assess the cause Secondly, this technique does not
comparison is made at selected keystone or causes of delay on a global basis. A address concurrent delays. The amount
dates between the schedule in effect at systematic approach is required. of delay to the project is assessed
the start of each period experiencing independently for each delay-causing
delay and the extended duration schedule Conventional Method event.
at the end of the period. This technique
greatly helps in the determination of the The conventional method of delay The third - and most serious - drawback
length of delays and of the corresponding analysis requires at the outset that the of the conventional method of delay
causes and responsibilities. Its execution events that caused delay be identified. analysis is that it disregards the impact of
is "computer friendly''. Each delay causing event is analyzed a delay to one activity on other indirectly
individually. The schedule in effect affected activities. This can often result in
An owner hires a contractor to build a immediately prior to the event is modified a serious under-estimation of the total
building for a fixed price and within a one by incorporating revised durations into all impact a delay-causing event has on a
year period. A contract is signed. The those remaining activities directly affected project schedule.
contractor submits his schedule for the by the event in question. The schedule is
project. Work proceeds. Eighteen recalculated and the projected completion The Snapshot Technique
months later the building is completed. date is compared with the projected
The contractor claims cost overruns due completion date prior to the incorporation Snapshot Analysis is a delay analysis
to owner-caused delay. The owner of the delay. The difference between technique used to determine the amount
claims costs from the contractor due to these two dates is the delay to the project of delay that has occurred on a project,
late occupancy. The problem: how to caused by the event under consideration. when the delay occurred, and the cause
determine the cause or causes of the six or causes of the delay.
months' delay. The above method is simple to apply and
widely used; however, it does have a This method approaches the problem
There are many parties involved: the number of shortcomings. from the opposite perspective to that of
owner, the contractor, the architect, the the conventional method of delay
engineer, other contractors, the Firstly, you have to know before you start, analysis: instead of asking the question,
municipality - even God himself (i.e. delay not only what the causes of delay on the "This event occurred; what delay did it
caused by an "Act of God''). There are project were, but also how much delay cause to the project?" Snapshot Analysis
even more potential causes of delay: resulted from each cause. Neither of asks, "This delay occurred; what event or
strikes, material shortages, equipment these is self-evident. The subjectivity events caused it?"
failure, design changes, rework, poor inherent in determining the causes and
organization, and weather - to name just

-1-
The analysis is based upon the original or information shown prior to this date is three week delay to the completion date
"As-Planned" schedule; the actual or "As- historic information and forms part of the of the project. Because the cause of each
Built" schedule; and any revised As-Built schedule. The information delay is known, the relevant importance
schedules that may have been shown subsequent to this date is future can be assessed and responsibility for the
implemented during the execution of the planning and comes from the contractor's net delay apportioned accordingly.
project. As-Planned schedule. When we calculate
the critical path for this new Snapshot The determination of the cause or causes
In our earlier building example, six schedule, we generate a new completion of delay becomes significantly easier
months' delay occurred. What caused it? date and the completion date shown on when the time period under consideration
On a large complex job, it is next to the contractor's original As-Planned is shorter and the amount of delay is
impossible to come up with a meaningful schedule is the delay that has occurred known.
answer to the question without breaking it during the time period from the beginning
down further. of the job to the first Snapshot date. In The first Snapshot is now complete. Both
the present example, a three-week delay the amount of delay and the causes of
The total project duration is therefore has occurred during the first two months delay have been determined for the first
divided into a number of time periods. of the job. two-month period of the job. We are now
For each time period, the amount of delay ready to go on to the analysis of the
that occurred within that time period is Where the Extended Duration schedule second time period.
determined, and the causes of the delay pushes the project completion date
are assessed. beyond the previously projected Changes in the Plan
completion date and into either a period
The breakdown of the project duration of inclement weather or a vacation period, The first step - and a critical step - is the
into time periods is achieved by the an adjustment is required. In the first verification of the Extended Duration
selection of a series of dates. Each date case, the durations of those activities schedule. If this schedule is no longer
represents the end of one period and the occurring during inclement weather valid because of a change in planning, the
beginning of the subsequent period. The periods are increased to reflect the schedule is revised to reflect the planning
dates are selected to coincide with major anticipated loss of productivity due to in effect on the project at the point in time
project milestones, including the weather. In the second case, the project under consideration. The difference
implementation of significant changes in calendar is prolonged and non-working between the projected completion date
planning, and to isolate known major days are identified as such. It is possible shown on the Extended Duration schedule
delays or groups of delays. that, as the result of either of the above on a Snapshot date and the Revised
situations, the total delay to the project Schedule on the same Snapshot date is
The first time period under consideration completion incurred during a particular an indication of the amount of
is the time period from the beginning of period can exceed the duration of the acceleration (or relaxation) achieved
the job to the first date selected as period itself, i.e. the events that occur through the change in planning.
described above. during a four-week period can actually
cause a five-week delay to the project In the case of owner-caused delays, the
The project completion status at the end completion. contractor has an obligation to mitigate
of this time period is determined from the the ultimate damages, i.e. delays. If this
As-Built schedule, taking, so to speak, a Causes of the Delays can be done through resequencing with
snapshot of the project. The schedule for no additional cost to the contractor, then
the uncompleted portion of the work is We have now determined objectively how he must revise his schedule accordingly.
projected to completion according to the much delay occurred during the first time
schedule in effect at the beginning of the period. The next step is to determine the In our example, we know the project was
time period, which for this first period is cause or causes of this delay. A detailed running three weeks late on the Snapshot
the As-Planned schedule. This projected analysis of the events that occurred date. Was there a change in planning to
schedule at the Snapshot date is referred during the time period should reveal the regain this time? Let's assume that our
to as the Extended Duration schedule. causes of delay. A comparison of the As- contractor adopted an accelerated
The project completion date in the As- Planned schedule with the As-Built schedule to bring the job back on
Planned schedule is compared with the schedule for the time period under study schedule. We revise our Extended
project completion date in the Extended can be very revealing. Duration schedule accordingly. This
Duration schedule. In other words, the "Revised Schedule'' forms the basis of
projected completion date at the For example, the contractor may have comparison for the second Snapshot.
beginning of the period is compared with mobilized according to schedule;
the projected completion date at the end however, excavation took one week The delay analysis is continued
of the period. The difference between longer than originally planned due to progressively through each of the periods
these two dates is the delay to the project heavy rains in the fourth and fifth weeks. defined by the selection of the Snapshot
that occurred during the period. Once the No work was accomplished on the dates. The total delay to the project is
amount of delay that occurred during the concrete footings because a design calculated by adding up the individual
period is known, the causes of this delay change delayed the release of the delays associated with the various
are assessed. construction drawings. The contractor periods, disregarding any time that might
was behind schedule but could have have been gained through acceleration.
For example, let us say that at the end of regained the time by mobilizing additional The so accumulated total delay time
the first two months the contractor had equipment. The Extended Duration represents the total extended duration
only executed the work he had originally schedule shows a project completion date which is then analyzed for responsibility
planned to execute in the first five weeks. three weeks later than the original apportionment between owner and
The last day of the second month is planned completion date. We have two contractor, or designated as excusable,
therefore the Snapshot date. The parallel delays, the net effect of which is a depending on the terms of the contract.
-2-
The so-determined total delay is, The As-Planned schedule and revisions to analysis. The delay measured is actual
however, not necessarily the basis of this schedule, and the As-Built schedule, delay, not estimated delay. As such it
damage quantification. For calculating form part of the job record. These can be encompasses all delay - both direct and
extended duration or acceleration costs, agreed upon as fact by both parties indirect - experienced on the project.
the extent of acceleration should also be involved in a delay dispute. The Subjective and usually inaccurate
considered. argument can therefore be limited to estimates of the impact of a delay-
assessing the cause of the known delay in causing event on unaffected work are not
This technique is intended to be used in each of the periods developed during the required and form no part of this method
after-the-fact delay analysis in that the Snapshot analysis. of delay analysis.
analysis is based on the actual job
progress immediately after the delay in This structuring of the issues is perhaps
question. the greatest service afforded by Snapshot

Snapshot Technique Computer team can be mobilized to complete the The As-Planned schedule, if not already
Friendly. document review in the available time. in CPM format, is converted into CPM
format.
The Snapshot method of delay analysis The data is then sorted and summarized
takes full advantage of the computer in the computer to yield a list of actual The above two schedules must be co-
programs currently available for data start and finish dates for the activities on related. The means of co-relation is
base management and project planning. the As-Built schedule. This information is determined by the particular program
transferred by batch process to the selected. The simplest method of co-
The As-Built schedule is developed from project management software that is used relation from the computer's point of view
the job records including diaries, to develop the project schedules. is via a common list of activities for the
correspondence and minutes of meetings. two schedules. Given the divergence of
Relevant information is extracted from A chronological listing of the data the two schedules, particularly on jobs
these documents, coded and entered into extracted for the job records forms the requiring delay analysis, there is often not
a computer file. Each record includes the basis of a statement of facts for the a good co-relation possible between sets
date, the source document, one or more project. The coding system enables this of activities. The option to co-relate
subject or area codes, and a code to statement of facts to be regenerated by activities by activity codes is most
relate the information to the appro-priate subject. It therefore becomes a valuable desirable; however, it is not often
activity of the As-Built sche-dule. The tool to all parties involved in the project. available.
data is entered in the same order as it is
reviewed by the analyst or technician. A ''pattern'' for the schedule at the first
Once the coding system is established, a Snapshot date is made by duplicating the

-3-
As-Planned schedule. A computerized The graphic capabilities of project impact on the total cost of the project, as
sort is performed on the As-Built schedule management software greatly facilitate well as the impact on the schedule.
to identify all activities having an actual the comparison of the schedule in effect Certainly, the tools required to perform
start date prior to the Snapshot date. For at the beginning of a period with the this enhanced analysis are currently
those activities whose actual finish date is Extended Duration schedule at the end of available. The maintenance of per-tinent
also prior to the Snapshot date, the actual a period. This visualization of the job records will greatly facilitate the
dates are fed into the above "pattern", to difference between the planned dates and application of the snapshot technique.
create an updated schedule in effect on the actual dates for each activity is Yet another reason for maintaining
the Snapshot date. Those activities extremely helpful in assessing the causes adequate records!
started but not completed as of the of delay within a period.
Snapshot date require special attention. Conclusion
Someone familiar with the job must Project Simulation
evaluate the remaining duration of these Snapshot Analysis offers a systematic
activities, based on the schedule in effect The schedule analysis is only a means to and objective method of quantifying the
at the beginning of the period. Once this an end. The ultimate objective is to amount of delay incurred on a project on
information has been input, the updated determine the cost implications of a progressive basis. It greatly facilitates
schedule is recalculated to yield the unforeseen events. The Snapshot the task of assessing the causes of delay
extended duration schedule. method measures only the impact on time and the corresponding responsibility for
of unforeseen events. The analyst must the delay. The measurement of the
The Extended Duration schedule is then go on and quantify the cost amount of delay is inclusive of both the
revised (if required) to reflect any change implications of the delay. The inclusion of direct and indirect consequences of a
in planning, and is then duplicated to form resource and cost data for each activity in delay-causing event. The method lends
the pattern for the Extended Duration the As-Planned schedule would further itself well to a compu-terized analysis,
schedule at the next Snapshot date. enhance the application of this technique taking full advantage of the features
by generating a financial model for the currently available in project management
The process is repeated. project. The calculation of the Extended software.
Duration schedule would then yield the

network analyses and is actively involved


in claims preparation work. As a Among her current assignments is that
professional background to such of Program Co-ordinator for the 5th
activities, she has a decade of Canadian Building and Construction
experience in heavy engineering Congress, to be held in Montreal,
construction on major projects with November 27-29, 1988. This congress
major companies in Trois Rivieres, Long is sponsored by the Canadian
Spruce, Baie James, Revelstoke and Construction Research Board of the
Montreal. National Research Council, in
collaboration with 11 national and
Her last on-site job was as project provincial associations whose members
manager for a $32 million tunnel project are involved in the construction process
for the Montreal Urban Community - an as designers, contractors, owners or
experience she described as a guest technological information providers.
LORNA M. TARDIF, eng., MBA speaker at the 1986 convention of the Over 60 speakers will be involved.
Canadian Construction Association.
Lorna Tardif has lived a fairly full life Looking ahead, Lorna is the chairman-
since she graduated from McGill She took a couple of years off to attend elect of the Construction Division of the
University with her civil engineering the University of Western Ontario, where Canadian Society for Civil Engineering.
degree in 1975. A Senior Consultant she obtained her MBA in 1980. And, oh
with RAL, Montreal, she is responsible yes, she is married and has three
for the Estimating Department and children.

Emeric Leonard joined RAL in 1987 and preparation or evaluation. His previous
was appointed a Vice-President in April position was Vice-President,
of this year. He brings to the position 35 International Development, for the Sintra
years experience in construction in Group in Montreal. In this capacity he
Canada and abroad. Most of this was was also Chairman of the Canadian
obtained in construction companies but International Construction Corporation, a
he has also had stints with a consulting joint venture of six Canadian
firm and with a federal construction construction firms interested in export
agency. work.

At RAL Emeric is engaged in planning, Overseas projects included those in


scheduling, estimating, progress Grenada and Malagasy. These and
EMERIC G. LEONARD, eng. monitoring, cost control and claim project investigation trips enabled him to
-4-
accumulate an impressive total of expressways, bridges, roads, dams and courses from Montreal universities over
''frequent flyer'' points! His main work hydro projects. the years. He is a founder and past-
experience, however, has been in president of the Quebec Road and
engineering construction projects at Emeric served as a navigator in the Transportation Association and a
home in Canada in Quebec, Royal Canadian Air Force. He obtained member of the Executive Committee of
Newfoundland and New Brunswick. his B.A.Sc. degree from Ecole the Advisory Council to Ecole
These include a wide variety of six-lane Polytechnique de Montreal in 1952 and Polytechnique.
has taken many continuing education

The head of RAL's new unit servicing excolleagues formed Environmek


bonding companies entered the Contractors Inc.
construction industry in 1953, following
his graduation from McGill University All of his career has been related to
with a degree in civil engineering. construction with the exception of a year-
and-a-half in the mid-fifties, when he
For nearly twenty years he was was the envy of thirsty friends in his
associated with the Francis Hankin capacity as a production engineer with a
organization, including a decade in which famous Canadian brewer.
he served as President and C.E.O. of its
operating and holding companies in He is a keen advocate of rural living,
Canada and the United States. These alpine and cross-country skiing,
included Francis Hankin & Co. Ltd., gardening and woodlot management.
Hankin Environmental Systems Inc. and
Hankin Management Services Ltd.
MICHAEL L. TUCKER, P. Eng. More recently, he and some

WE SHALL MISS
A good friend, Baker Daigle, died on April 29 after a brief illness. Baker joined RAL in 1980 as Vice-President, the position he
held until his death. In 1986, he also assumed the position of Chairman of the Board of WDR.

Baker will always be remembered for his sense of humour and willingness to listen to and assist others with their professional and
personal problems.

NEW UNIT TO SERVE SURETIES

Revay and Associates Limited is These potential liabilities can be c) Assemble and put a project
pleased to announce the establishment substantial and will depend on the team to work.
of a new unit to formalize its services to following:
bonding companies who must complete In order to contain and minimize
work in progress when a 1. The number of bonded contracts liabilities, a bonding company must have
contractor/client becomes insolvent or that must be completed; instant access to project management
cannot continue with the work. It is at personnel experienced in sizing up the
this point that a bonding company is 2. The degree of completion of extent of the work still to be done and
most vulnerable because it may not have contracts; then to manage it to completion at
the resources to establish the extent of minimum cost.
these liabilities and to staff the project 3. The time taken to:
management team required to contain If a bonding company does not have this
the losses. a) Make an assessment of the capability in-house, RAL can provide an
work to be done; experienced construction manager to
b) Prepare a plan to manage the make an immediate assessment of the
completion of the work. scope of the work still to be done. RAL

-5-
will then make written recommendations will be lost to those responsible for company can step in quickly and
to the bonding company as to the best completing the work. assume command, then there is a good
way to proceed to complete the work in chance of retaining the confidence of
progress at the least possible cost. RAL It is important that the project team have suppliers and subcontractors. If this
has the personnel who have the access to key employees of the confidence is lost, many problems are
experience to maximize recoveries from defaulting contractor. Some of these created for those who must complete
unpaid progress invoices and employees can be hired to be part of the the work.
outstanding balance of contract team who are completing the work and
amounts, to process change orders and others can be retained as consultants for RAL has set up a project management
to collect holdbacks. RAL also has special assignments. The job-specific group with these skills to assist bonding
personnel who have the skills to explore knowledge that these employees have is companies faced with the insolvency of
fully the potential in claims or actions to often the key to maximizing recoveries. contractors or owners during
recover damages. construction projects. It will be led by a
The capacity to prepare claims is construction industry veteran of thirty
SPEED ESSENTIAL essential because a claim to recover years, Michael L. Tucker, P. Eng., who is
damages is not only a potential revenue currently completing a major assignment
The key to keeping losses to a minimum source but is also often a key for the Guarantee Company of North
is speed. It is essential that a project component in defending attempts by America. This involved setting up and
management team be put in place in a owners or contractors to make staffing a company which then acted as
matter of days so that construction work unjustified or exaggerated back charges. GCNA's agent to complete twenty-one
does not miss a beat. If work in the field The research work required to prepare a projects which a contractor client had on
slows down and stops, the inevitable good claim is usually the same as that its books when it became insolvent. Mr.
result is that key personnel such as required to defend against such back Tucker's background in the construction
project managers, supervisors and charges. business and experience gained while
tradesmen will leave to seek other work. completing contracts for the GCNA,
If this happens the background Speed is also important in terms of the backed up by the resources of the RAL
knowledge that these employees have trade and how they react to the organization, are now available to
contractor's default. If the bonding bonding companies when needed.

The Revay Report is published by Revay and Associates Ltd., a national firm of Construction Managers and Claims Consultants.
The above article has been electronically modified from its original publication. Contents may be reproduced; with a credit as to
source appreciated. Your comments and suggestions for future articles are most welcome. If you have any questions or would
like to obtain other Revay Reports, please feel free to contact any one of the following Revay offices:

MONTREAL:
CONTACT INFORMATION CALGARY:
4333 Rue Ste. Catherine 0uest Suite D262, 1600 - 90th Avenue S.W.
Montreal,
Please visitQuebec H3Z 1P9 for current office locations.
www.revay.com Calgary, Alberta T2V 5A8
IfTel:
you(514)
would932-2188
like to subscribe for The Revay Report, click here. Tel: (403) 777-4900
Fax: (514) 939-0776 Fax: (403) 777-4903
E-mail: revay@dsuper.net E-mail: revays@telusplanet.com

OTTAWA: VANCOUVER:
Suite 301, 39 Robertson Road 201, 1985 West Broadway
Nepean, Ontario K2H 8R2 Vancouver, BC V6J 4Y3
Tel: (613) 721-6801 Tel: (604) 737-2005
Fax: (613) 596-8172 Fax: (604) 737-2008
E-mail: ralott@istar.ca E-mail: revayvan@smartt.com

TORONTO:
Suite 306, 505 Consumers Road
Toronto, Ontario M2J 4V8
Tel: (416) 498-1303
Fax: (416) 491-0578
E-mail: revay@ican.net

-6-

You might also like