海军学院内结构物监测日报
CCCC Multi-lane Road Tunnel Project under the River Karnaphuli
Monitoring Daily Report of Naval Academy (Swimming Pool and Guardhouse)
Initial time: 2018-4-21 Last time: 2018-5-30 8:30 AM Date: 2018-5-31 8:30 AM
初始高程 变化速率
本次高程 上次高程 本次变化量 累计变化量
点号 Initial Rate of 备注
This time Last time change Total change
No. elevation change Note
elevation(m) elevation(m) (m) (m)
(m) (m/d)
HW1 0.662 1.115 0.318 0.797 0.453 0.797
HW2 0.541 0.911 0.185 0.725 0.370 0.725 HH1为湖面
HW3 0.503 0.796 0.228 0.568 0.293 0.568 观测点,
HW4 0.684 0.802 0.197 0.604 0.118 0.604 "+"为水位
HW5 0.284 0.669 0.186 0.483 0.385 0.483 上升,"-"
HW6 0.929 1.333 0.961 0.371 0.404 0.371 为水位下降
HH1 -0.160 1.442 1.197 0.245 1.602 0.245
监测时施工工况:工作井正在开挖第二层。
Working conditions: The working well is excavating the second floor.
监测简要总结分析及判断性结论:
1.本次总计观测水位监测点6个,累计变化最大点为HW1,累计变化量为0.453m,变化速率最大点为
HW1,变化速率为0.797m/d。
2.湖面累计变化量为1.602m,变化速率为0.245m/d。
Monitoring conclusion of groundwater level
1. The maximum total change point was HW1, the cumulative change amount was 0.453m, the
maximum change rate was HW1, and the change rate was 0.797m/d.
2. The total change in lake level was 1.602m with a rate of change of 0.245m/d.
Figure 1:
14.35
14.76 Legend:
Monitoring points of
sedimentation
Monitoring points of
14.35 groundwater level
Reference points
Inclination point
Notes:
1.All the dimensions in this drawing are
in the unit of m.