Professional Documents
Culture Documents
5.2.2 – Pressure differential across doors shall not cause the force required to open
the doors to exceed 133 N.
5.4 – Elevators shall be considered a separate smoke zone when smoke control is
required.
5.3.5.1 – Vestibules shall not be required, but shall be permitted as part of a building
smoke management system.
Code & Standard Design Requirements
Qatar Civil Defense
Fire Safety Standards
FSS 2.2.13 – Smoke Stop or Fire Fighting Lobby required when:
(i) Stairway has no natural light or ventilation, or
(ii) Stairway traverses more than 4 stories (incl. basements), or
(iii) Has a habitable height more than 28 meters above Ground.
All Fire Fighting Lifts shall be provided with a Fire Fighting Lobby.
FSS 6.6.3 – Fire Lift required when building habitable height exceeds 23 meters
above ground level or 9 meters below ground level.
FSS 1.5 – A high-rise building exceeding 30 storeys shall be provided with refuge
floors at an interval not exceeding 20 storeys.
A minimum of 50% of the gross floor area of the Refuge Floor must be a protected
Holding Area.
Code & Standard Design Requirements
Qatar Civil Defense
Fire Safety Standards
FSS 1.5 – The Holding Area is to be ventilated:
(ii) Naturally ventilation requires the total area of the ventilation openings to not
be less than 25% of the gross floor area of the Holding Area.
(iii) Mechanical ventilation is also acceptable as long as the equipment is powered
via 2-hour fire rated cables and 100% stand-by power is available.
Low-Rise
Building
• < 23 meters
above ground
• < 9 meters
below ground
• No smoke
mgmt system
required
Low-Rise Bldg
w/ Deep
Basement
• < 23 meters
above ground
• > 9 meters
below ground
• Fire Lift
Required
• Bsmt Stair
Pressurization
Required
Mid-Rise
Building
• > 23 meters
above ground
• > 9 meters
below ground
• Fire Lift
Required
• Bsmt & Tower
Stairs Require
Pressurization
High-Rise Bldg
w/ Refuge Floor
• > 30 storeys
above ground
• > 9 meters
below ground
• Fire Lift
Required
• Evacuation Lift
may be required
• Bsmt Stairs,
Tower Stairs,
and Refuge
Require
Pressurization
High-Rise Bldg
w/ Fire Floor
Isolation
• Same physical
features as
High-Rise
• In addition to
standard High-
Rise smoke
mgmt, two
floors above
and below the
fire floor are
pressurized.
Typical Floor Plan (No Fire Floor Isolation)
Pressurized Floor (Fire Floor Isolation)
Typical Floor Plan (Fire Floor Isolation)
Code & Standard System Sizing Method
Recommendation and Test Requirements
Document NFPA 92 - 2012 Qatar Civil Defense - FSS
System Sizing SFPE TR 82-4 Designing Stair None Provided
Method Pressurization Systems
Recommendation (Similar to British Standard
Method)
• Single point
injection OK for
stairways of
approx. 15 to 20
storeys, but will
not satisfy Bsmt
Stairways
Recommended
Air Injection
Points System Layout
• Inject air to Lift
Shafts at top,
bottom, and
approximately
every 40 storeys
• Inject air to
stairways at top
and approximately
every 15-20 storeys
Contact Information:
PO Box 27594
Abu Dhabi, UAE