De Guzman, Alexandrea Mari

Sotto, Maria Conchita C.


1A29 S<D
Plant Outlet X Outlet Y Outlet Z Supply

2000 4000 1500


A 45
45 ? ?
3000 3500 4500
B 5 55 ? 60

4000 1000 2500


C 20 60
? 40
0 0 0
Dummy Plant ? ? 10
“D” 10

Demand 50 75 50 175

Improvement Index Initial Shipment Cost


A to Y Formula= (Initial Route) Quantity X Cost (1st step)
= 4000 – 2000 + 3000 – 3500 Add all the amounts from the acquired costs
= 1500 from the routes

A to Z Route Quantity Cost Amount


A to X 45 2000 90,000
= 1500 – 2000 + 3000 – 3500 + 1000 – 2500 B to X 5 3000 15,000
B to Y 55 3500 192,500
= -2500
C to Y 20 1000 20,000
B to Z C to Z 40 2500 100,000
D to Z 10 0 0
= 4500 – 2500 + 1000 – 3500
Initial Shipment Cost
= -500
= 90,000 + 15,000 + 192,500 + 20,000 + 100,000
C to X
= 417,500
= 4000 – 3000 + 3500 – 1000
40
= 3500 -45 + 5

D to X 45
5
v + 3500 – 1000 + 2500 – 0 -55 15
= 0 – 3000
= 2000 20 -40 60 -
D to Y
= 0 – 1000 + 2500 – 0

= 1500
Plant Outlet X Outlet Y Outlet Z Supply

2000 4000 1500


A 45
5 ? 40
3000 3500 4500
B 45 15 ? 60

4000 1000 2500


C 60 60
? ?
0 0 0
Dummy Plant 10
“D” ? ? 10

Demand 50 75 50 175

Improvement Index
A to Y
= 4000 – 2000 + 3000 – 3500
45
-5 40 -
= 1500
B to Z 45 50
v -15 10
= 4500 – 1500 + 2000 – 3000
+ -10 5 5
= 2000
C to X
= 4000 – 3000 + 3500 – 1000
= 3500
C to Z
= 2500 – 1500 + 2000 – 3000 + 3500 – 1000
= 2500
D to X
= 0 – 2000 + 1500 – 0
= -500
D to Y
= 0 – 0 + 1500 – 2000 + 3000 – 3500

= -1000
Plant Outlet X Outlet Y Outlet Z Supply

2000 4000 1500


A ? ? 45
45
3000 3500 4500
B 50 10 ? 60
c
4000 1000 2500
C ? 60 ? 60

0 0 0
Dummy Plant ? 10
“D” 5 5

Demand 50 75 50 175

Improvement Index Final Shipment Cost


A to X Formula= (Final Route) Quantity X Cost (1st step)
= 2000 – 3000 + 3500 – 0 + 0 – 1500 Add all the amounts from the acquired costs
= 1000 v from the routes

A to Y Route Quantity Cost Amount


A to Z 45 1500 67,500
= 4000 – 0 + 0 – 1500 B to X 50 3000 150,000
B to Y 10 3500 35,000
= 2500
C to Y 60 1000 60,000
B to Z D to Y 5 0 0
= 4500 – 3500 + 0 – 0 D to Z 5 0 0

= 1000
Final Shipment Cost
C to X
= 67,500 + 150,000 + 35,000 + 60,000
= 4000 – 3000 + 3500 – 1000
= 312,500
= 3500
Therefore, the least cost for the shipment of the
C to Z
plants to the three outlets is 312,500
= 2500 – 0 + 0 – 1000
= 1500
D to X
= 417,500
= 0 – 3000 + 3500 – 0
= 500