IAACOBS V Page 1 of 2
‘SPECIFICATION NO: 22-11051-02/H.02/00004
SPECIFICATION TITLE: THERMAL INSULATION
PROJECT REFERENCE: — AMOXYCILLIN 4™ TRAIN
- Project No: 11051 |
- Project Location: ‘Singapore 2,
- Project Title: AMOXYCILLIN PLANT 4™ TRAIN
EXPANSION (AB103)
- Client: "GlaxoSmithKline
- Project Manager Authorisati
- Client Authorisation:
‘APPROVALS.
issue] Date | Pages Issue Description By | Gheck | Approwe
| Ne
1 9 Sop 02 12 _| Valve, Expansion joint insulation dete included | Rithard | JOhemage
9 | 16Apr2002 | 13° | Issued for Construction (ncorp comment from | Reny | Franc’
GSK -transmittal 47) Lewis | “Ong
A | 28Jan2002 | 13 | Issued tor Approval (Based on Augmentin SR] Reny | France
specifications Lewis | Ong
Entire Specification SPECIFICATION ISSUED FOR:
Issued this Revision | C) _Inshouse Review DO Purchase
1D Revised Pages Only | 1 client Approval Construction
‘sued this Revision | 1) Inquiry Roissued for ConstructionJACOBS:
AMOXYCILLIN PLANT 4™ TRAIN EXPANSION (AB 103) SPECIFICATION NO:22-11051-02/H.02/00004
GLAXOSMITHKLINE,
10
20
3.0
40
5.0
7.0
8.0
9.0
PAGE 20F 12
WsUE 4
DATE —: 9 September 2002
‘TABLE OF CONTENTS
INTRODUCTION
SCOPE
MATERIALS
APPLICATION
ACCESSORY MATERIALS
SITE PRACTICE
IDENTIFICATION
INSPECTION
INSULATION THICKNESS
ATTACHMENT : 4
INSULATION FOR VALVES AND EXPANSION JOINTSJACOBS:
AMOXYCILLIN PLANT 4™ TRAIN EXPANSION (AB 103) SPECIFICATION NO:22-11051-02/H.02/00004
GLAXOSMITHKLINE PAGE 30F 12
ISSUE 1
DATE 9 September 2002
10
14
1.2
2.0
24
22
23
3.0
34
344
INTRODUCTION
This specification covers the Supply and Installation of thermal insulation materials to ductwork and
pipework systems serving the GlaxoSmithkline Amoxycilin Plant 4" Train in Singapore.
Insulation shall be provided for the following requirements:-
i Heat retention
ii) Personnel protection control
iii) Prevention of heat absorption and surface condensation
SCOPE
Ductwork Insulation shall be applied to the following:-
i) All supply ductwork.
ii) All fresh air ductwork and plenums between inlet louvres and air handling units.
ili) All return air ductwork.
Pipework insulation shall be applied to the following:-
) Steam and condensate
ii) Chilled Water Flow and Return
iii) HWS Flow and Return
iv) Boosted Water Service(Process Cold Water)
v) Purified Water
vi) Condense Recovery
Technical Information in Tender
‘The contractor shall submit drawings or sketches for approval by the Engineer, showing his proposed
method of insulation and cladding for:
i) Top and bottom of vessels
ji) _ Branches and manholes
i) Machinery
iv) Valves boxes and flanges, expansion joints, tees and bends
Alternative or more economic recommendations shall, if necessary, be submitted for comment by the
Engineer.
The Vendor shall submit a list for the Engineers approval of the Proprietary Materials such as
adhesive, vapour seals, masties, etc., that he proposes to use,
The chloride content of the insulation shall be stated in the Tender.
MATERIALS
General
The Contractor shail be responsible for the supply of all material required, including insulation, fixing
and finishing materials.
Materials shall be new and of the quality specified
All materials used shall be asbestos free.
Solvent based formulations shall not be used in poorly ventilated areas,