Professional Documents
Culture Documents
ABSTRACT line, depending on mining height. The cable tendon passes through
the heavy-wall stiffener tube, and extends from the barrel-and-
Over the past three decades, the U.S. coal mining industry has wedge assembly at the roof line to the maximum length of the
widely used cable supports to supplement traditional primary cable support. The expansion shell allows tensioning of the cable,
bolting systems, especially in difficult ground conditions. However, up to approximately 10,000lbf. Tensioning is completed as the
increased mining activity in adverse conditions has underscored bolt is installed and does not require additional equipment or time
the limited effectiveness of the non-tensioned, partially grouted after initial installation. Traditional post-tensioned cables require
cable supports used to supplement primary bolts. Roof failures in individual cables be tensioned with a hydraulic tensioner after
conditions such as corrosive environments, highly laminated strata, the resin grout has cured. This additional installation step limits
low overburden depth and water intrusion have demonstrated that the installation rate and overall deployment of tensionable cables.
the need for cable technology has reached beyond the traditional Operators often have difficulty maintaining a cable bolt installation
non-tensioned, partially-grouted cable tendon. Furthermore, rate that is consistent with the mining rate. This situation often
declining market conditions and increased competition for coal results is un-tensioned cables or cuts that sit unsupported for an
customers has demanded that new cable bolt technology be cost- extended length of time.
effective and readily adaptable to the mining cycle.
130
32nd International Conference on Ground Control in Mining
B-Rigid truss configuration as a stiff, high capacity truss alternative
(Figure 3). A three- or four-hole roof channel is used to apply
structural surface control. The cross-section of the roof channel is
designed primarily to resist bending moments. Two cable bolts are
angled over the mine ribs to anchor into undisturbed strata, similar
to a traditional roof truss. One or two cable bolts are installed
vertically toward the center of the channel, and these vertical
cables provide additional stiffness to the center of the channel and
may or may not anchor into competent strata. The B-Rigid truss
utilizes off-the-shelf roof control products, and many mines already
have the assorted components in stock in the mine supply yard.
Additionally, no special tools are required to install the B-Rigid
truss. It can be used in conjunction with all cable bolt systems
including INSTáL CC cables, fully grouted cables, post-tensioned
cables and non-tensioned cables.
Case study 1 is a longwall headgate in the Eagle seam, in Case study 2 is a long-term belt corridor in the Eagle seam,
southern West Virginia. Supplemental support in the headgate was central West Virginia. Constraints on the mining reserve required
installed approximately 9 months after the headgate was developed. that the corridor be developed underneath a valley where
The roof in this area consisted of highly laminated sandstone the original overburden depth was less than 50ft (Figure 8).
with mica streaks (Figure 4). During installation of supplemental Compounding the difficulty was the fact that the valley had been
support, mining-induced roof fractures were discovered up to 11 ft filled in the 1950s and the fill depths reached approximately 150ft
above the roof line, using test drilling with a roof bolter. Fracture in the belt corridor area.
131
32nd International Conference on Ground Control in Mining
132
32nd International Conference on Ground Control in Mining
133
32nd International Conference on Ground Control in Mining
CASE STUDY 3
Figure 13. Initial support plan for case study 3. Figure 15. Fractured roof observed in initial support plan area.
As the setup face was developed, vertical fractures, cutters and Because stability of the longwall setup face was critical, post-
other signs of roof movement developed outby the active face tensioned cables were not eliminated from the roof support
(Figure 14). Based on interviews with face personnel, most of the plan. Instead, the (4) 0.7 in x 144 in grade 270 non-tensioned
roof movement developed between installation of the first and cables with T5 x 192 in roof channel were replaced with (4) 0.6
second stages of roof support. After the second stage of support in x 144 in grade 270 INSTáL CC cables. These cables allowed
was installed, further indications of roof movement ceased. application of tension to the supplemental support during the first
stage of roof support. In addition, installation time was reduced by
approximately 20 seconds per cable.
134
32nd International Conference on Ground Control in Mining
and mining-induced fractures. Where polyurethane injection
After adoption of the new support system, signs of roof is necessary, the Fully-Grouted Cable Bolt can be used as both
movement were greatly reduced (Figure 16). Scope data indicated a supplemental support and an injection point. In addition, the
similar geology, with a reduction in fracture density of about 63%. Fully-Grouted Cable Bolt is approximately 75% of the cost of
Additionally, the maximum fracture height was reduced from an inflatable packer injection system. All of these technologies
approximately 10 ft to approximately 3 ft (Figure 17). have been designed to dovetail into the mining cycle, and present
minimal interruptions in mining activity.
REFERENCES
CONCLUSION
135