You are on page 1of 4

McCarthy P L 2001.

Mining Dilution and Losses in Proceedings Underground


Mining, in Mineral Resource and Ore Reserve Estimation – The AusIMM Guide to
Good Practice (Ed: A C Edwards), pp333-336 (The Australasian Institute of
Mining and Metallurgy: Melbourne). Reprinted with permission of The
Australasian Institute of Mining and Metallurgy.

Mining Dilution and Losses in


Underground Mining
By P L McCarthy 1

Abstract
Resource modelling and Ore Reserve estimation procedures are different for open pit and
underground mines. A statistical approach to the spatial location of orebody limits is unhelpful in
underground Ore Reserve estimation, while experience with practical mining outcomes and
economics is fundamental.

Resource modelling for underground ruining relies heavily on geological interpretation and
experience. When converting Mineral Resources to Ore Reserves, the chosen grade interpolation
technique, while important, has less significance than the raining, geotechnical and economic
considerations which determine mining dilution and recovery.

Mining dilution and recovery are difficult to measure and more difficult to predict. There is no
alternative to careful measurement coupled with experience-based adjustment. It is possible that a
`Competent Person' for the purpose of preparing a Mineral Resource estimate may not be `competent'
to estimate Ore Reserves for the same deposit.

Introduction Definitions
Conversion of a Mineral Resource estimate to an Ore Reserve Dilution may be defined in several ways. To the metallurgist
estimate is a team effort involving, at minimum, a geologist, receiving the ore for treatment, it is the percentage of the
metallurgist and mining engineer. The factors to be considered delivered material which is waste.
relate to practical mining outcomes and economics, so the
Competent Person preparing the Ore Reserve estimate must be Thus;
very familiar with the proposed mining methods. The main Dilution (%) = (mass of waste) x 100 / (mass of ore + mass of waste) (1)
considerations are the amount of lower-grade or waste material
that will become mixed with the ore (mining dilution), and the The mining engineer often expresses dilution as a tonnage
proportion of the resource that can be economically recovered increase.
(mining recovery).
Thus;
Face-to-face involvement of the geologist who prepared the Dilution (%) = (mass of waste) x 100 / (mass of ore) (2)
resource estimate is essential. The assumptions and limitations
inherent in the resource model must be drawn out. The Formulae (1) and (2) ignore the fact that `waste' may contain
background of the resource geologist and his or her experience payable values, so that the economic impact of dilution is less
with underground mining estimates (as distinct from open-pit) severe. Dilution may also be expressed as a grade reduction.
should be understood.
Thus;
For reasons set out in this paper, conversion of a Mineral Dilution (%) = (resource grade - diluted grade) x 100 / (resource grade) (3)
Resource estimate to an Ore Reserve estimate is a challenging
task. The use of `text book' factors for dilution and recovery is All of the above measures of dilution are acceptable so long as
likely to lead to errors. they are defined before use. An example of the
misunderstandings that may otherwise arise is given by the
following example. Consider 100 t of ore of ten per cent grade
diluted with 10 t of material of four per cent grade, to give 110 t
at 9.127 per cent grade.

Equation (1) gives: 10 x 100 / 110 = 9.1% dilution.


1. Managing Director, AMC Consultants Pty Ltd,
19/114 William Street, Melbourne Vic 3000.
Equation (2) gives: 10 x 100 / 100 = 10% dilution.
E-mail: pmccarthy@amcconsultants.com.au Equation (3) gives: (10 - 9.127) x 100 / 10 = 8.7% dilution.
Mining Dilution and Losses in Underground Mining

Mining recovery may also be expressed in a variety of ways as the model become insignificant. For other cases, the geologist
follows: must form a view about the spatial limits of ore at the chosen
cut-off grade, and must be prepared to model the ore
• What percentage of the total resource tonnage will boundaries realistically. To do this, the geologist needs to
ultimately be mined'? understand the style of mineralisation and to be able to infer
• How does the diluted tonnage delivered to the mill irregularities, including structural dislocations such as faults, at
compare with the estimated resource tonnage? a scale smaller than the drill spacing.

• What percentage of the total metal contained in the The mining engineer will design slopes which have geometric
resource will be delivered to the mill? limitations dictated by geotechnical factors, the economic
• What percentage of the resource (tonnage or spacing and length of production blastholes, or the need to
contained metal) calculated at the resource cut-off combine blocks of `ore' and `waste' into mineable units. When
grade will be mined (or delivered for treatment) at the these shapes are overlaid on the resource model, the resource
chosen mining cut-off grade? grade is diluted and some of the resource is lost. The resource
model will contain internal dilution according to the model
• After elimination of those parts of the resource
block size (based on the assumed Selective Mining Unit) which
deemed inaccessible or otherwise uneconomic (for
may or may not accord with the engineer's proposed method.
reasons of width, dip, deleterious elements, rock
conditions, etc), what proportion of the remainder
In an underground mine, levels are planned on the basis of
will be recovered after leaving supporting pillars.
relatively coarse-spaced drilling. Stopes are designed and then
mined with limited flexibility for change. Pods of ore not
There may be other ways of defining mining recovery; it is
identified by drilling will be lost, even if they are expected
sufficient to state accurately what is meant by the term.
statistically to be present.

Suitability of the Resource Model Proponents of geostatistics sometimes claim that a resource
model inherently contains an appropriate allowance for internal
Resource models and the Ore Reserve estimation procedure are and edge dilution. This is an obvious fallacy; the dilution
different for open-pit and underground mints. To a scale of tens estimate must derive from mining and geotechnical
of metres, the location and spatial distribution of values may be considerations. A resource model which purports to include
unimportant in an open pit resource model. Provided the pins dilution provides an undefined starting point for the Ore
located to access the mineralised zone, any valuable material Reserve estimator, who must somehow `remove' the diluent
can be identified by grade control sampling and then marked material from the model before adding back mining dilution.
out for mining. Thus, the emphasis in open-pit resource This is an impractical task, so the only satisfactory approach is
modelling is on the global accuracy of estimates of tonnes and to refuse to accept such a model as a basis for an underground
grade and internal variability at a scale that might affect pit mine ore reserve.
optimisation, so a statistical approach is often appropriate.
The resource estimate for underground mining must include a
For underground mining the thickness, dip, continuity and statement of:
spatial relationship of ore zones, the regularity of wall contacts,
strength of ore and wall rocks are all critical inputs to the Ore • cut-off grade,
Reserve estimate. These are drawn from the resource model, or
from the geologist's knowledge of the deposit gained during the • minimum mining width,
data-gathering and modelling phase. Some parts of the resource • vertical limits (top and bottom RL), and
may be impossible to mine; others may be located too far from • lateral extent (plan limits).
development to be economic; others may suffer severe dilution.
The estimate should include a grade-tonnage curve. This
A sectional interpretation by an experienced geologist at one or enables the mining engineer to consider strategic sloping
more possible cut-off grades is usually the first step in options (high tonnage bulk mining vs low tonnage selective
preparing the resource model. This sectional interpretation will mining). The estimate should also quote resources at varying
include features inferred from the drill logs that would not be cut-off grades and minimum widths to enable economic
generated by any grade interpolation software. The geologist's optimisation.
experience tells him or her how variable the ore boundaries are
in this type of deposit and what shapes the variations might
take. When the sections are linked and wireframed, then Measurement of Dilution and Recovery
checked and corrected in plan and back to section, the resulting
three-dimensional outlines can be used to validate the grade- In many mines, ore from a number of sources is stockpiled and
interpolation process. blended before treatment, making reconciliations difficult or
impossible. Assuming reconciliation is possible, the resulting
The above procedure is usually necessary regardless of whether calculations of dilution and recovery may reflect on the
or not the limits of the mineralisation envelope have been accuracy of the Mineral Resource and Ore Reserve estimates
interpreted (at a subeconomic cut-off) and wireframed as limits rather than on actual mining performance. As in open pit
to the grade block model. This is because the shape of the mining there are several levels of reconciliation that may be of
mineralisation envelope may be quite different from the shape interest as performance measures:
of the economic material.
• How does the material treated compare with the
It may be acceptable to let the grade interpolation process Mineral Resource estimate'?
determine limits of economic mineralisation in large deposits to • How does the material treated compare with the Ore
be mined by caving methods, where the edge inaccuracies of Reserve estimate'?

AMC Reference Library – www.amcconsultants.com.au 2


Mining Dilution and Losses in Underground Mining

• How does the material treated compare with the slope In practice, slope overbreak usually takes an arcuate shape,
design estimate, which was based on infill drilling, deepest at the mid-point of the slope and minimal al the pillar
and perhaps a `call factor' grade adjustment`? sides. In large open stopes (∼20m spans), the `normal' arch may
• What was actually drilled out, charged and fired (as be 3m deep at mid-span. If drill assays outside the stope (or
distinct from design)? ore) limits are statistically analysed to calculate diluent grade,
then this shape must be allowed for. The shape of overbreak
• What was delivered for treatment as measured by may be predicted using techniques such as the Radius Factor
truck factors, load cells, weightometers and grab (Dunne and Pakalnis, 1996).
samples?
• What was really extracted from a stope as calculated Where there is a sharp geological cut-off between ore and
from slope surveys and back-calculation using all waste, simple geometric analysis, assuming dilution at zero
available data? grade, is often satisfactory. Where the boundary is gradational
(a fiat grade-tonnage curve at the chosen cut-off) then some
When overbreak occurs beyond the slope design line, it may credit should be given for values in the diluent.
introduce unexpected high-grade ore, low-grade, waste or a
process contaminant such as graphite in a contact shear zone. Dilution is greatest in narrow ore zones with sharp contacts,
Thus there is usually no direct correlation between and least in massive ore with gradational boundaries. Dilution
measurements of slope overbreak and the variation of recovered from backfill may be significant. If pillars are to be extracted
metal from the treatment plant. Expressed globally in relation to against freestanding cemented fill in open slopes, then the
the resource estimate, 'dilution' is an experience-based stability and likely frequency of fill failure must be considered,
adjustment that takes account of a number of subjectively even if rigorous control procedures are in place. In cut-and-fill
assessed variables. mining, more dilution may be experienced if the slope miners
are paid on a piecework (tonnage) contract because they may
Among the less obvious variables are: dig deeper into the fill floor.

• mixing of waste and spillage into ore in passes and Dilution can be reduced over time as experience is gained and
onto stockpiles; the mining method is optimised. Decisions about the level of
slope-wall support using cable dowels are based on cost-benefit
• blasthole damage to slope walls;
analysis, and will affect dilution. As a general guide the
• turn-around time from grade control sampling to following suggestions are made for dilution expressed using
mark-up; Equation 3 above:
• selective mining by resuing or in-slope sorting; and
• dilution is not less than five per cent unless an error
• loss of free gold in mining and transportation.
was made in the resource estimate;
Recently surveying instruments have become available which • for selective methods (eg cut and fill), dilution is
enable very accurate three-dimensional profiles of a slope void typically ten per cent;
to be determined. These are invaluable for mine planning, • for open sloping dilution is typically 15 to 20 per cent
reconciliation and management, and their use can provide an but can be more;
improved understanding and control of dilution. There is a
growing database of these measurements. • for caving methods dilution is 20 to 30 per cent; and
• for narrow vein mining, dilution of 50 to 100 per cent
Predicting Dilution is not uncommon.

For ore reserve purposes dilution must be estimated from data Exceptions can be found to the above guidelines, and will be
obtained from drilling and development, and from experience. dependent on ore width, dip and stratigraphy. Improvements are
possible with good mining practice. Contract mining on
Key variables are: tonnage-based and metres-based schedules of rates may require
more rigorous management to ensure control of dilution.
• the mining method and size of equipment;
It may be useful to use dilution reconciliations for a similar
• grade variability at the resource boundary; orebody and mining method as a check. This should be done
• ore width, dip, geometry and continuity; carefully with regard to the definition of dilution, the use of
hidden `call factors', and the methods of grade control and
• grade control method and proposed mining rate, and
ground support employed.
• slope design criteria, including hydraulic radius, RQD
and pillar dimensions The proportion of a resource that can be recovered is typically
70 to 90 per cent after removing `inaccessible' or uneconomic
The availability of digital resource models has led some blocks. The higher recoveries can be justified using more
practitioners to calculate diluted grades based on an assumed selective mining methods in ore of higher unit value. With all
average thickness of overbreak. For example, 0.5m on each methods, some resource that would otherwise be classified as
wall of a 3m wide stope represents a 33 per cent tonnage ore will be left in pillars or abandoned due to premature ground
increase. Grades from assays or composites within this failure.
envelope are used to interpolate a diluent grade. Caution is
needed, as the search ellipsoid used for `ore' may have already Pillar recovery may be justified as part of the on-going mining
considered this material, or conversely the grade of this process or as a retreating salvage operation at the end of mine
material may be related to the sample grades lying outside the life. For example, pillars were reduced on retreat in the
diluent boundaries in `ore' or `waste'. Cadjebut room and pillar operation, giving an improved

AMC Reference Library – www.amcconsultants.com.au 3


Mining Dilution and Losses in Underground Mining

recovery compared with the initial Ore Reserve assumptions. In


general, resources remain 'open' along strike or at depth for
most Ore Reserve estimates (i.e. there are Inferred Resources),
so that any error in the recovery estimate is rendered
inconsequential in time after further exploration and conversion
to Ore Reserves.

In preparing a feasibility study it is critical to estimate mining


recovery accurately so that the tonnes of ore delivered to the
mill in the life-of-mine schedule relate to the expenditure on
development and the amortisation of capital. As the mining
recovery is increased, less capital and operating costs are
incurred in accessing each tonne of ore. Whether the increased
recovery is desirable depends on how quickly the
corresponding sloping costs increase in achieving the higher
recovery.

Conclusions
The Ore Reserve estimate derives from a Mineral Resource
estimate. For an underground mine, particular limitations are
placed on the resource modelling technique. In particular,
geostatistical models which purport to include dilution are
likely to lead to errors in estimation.
The conversion of a Mineral Resource estimate to an Ore
Reserve estimate for an underground mine requires
consideration of mining dilution and mining recovery. These
two variables are the result of a multitude of factors that are
difficult to assess. Thus careful measurement, management,
judgment, experience and a thorough understanding of the
proposed mining method are required. The use of `textbook
factors' by inexperienced practitioners should he avoided. It is
possible that a `Competent Person' for the purpose of preparing
a Mineral Resource estimate may not he 'competent' to prepare
an ore reserve estimate for the same deposit.

There are several ways of expressing mining dilution and


recovery, all of which are valid. It is essential that these terms
be defined wherever they are used.

References
Dunne, K and Pakalnis, R C, 1996. Dilution aspects of sublevel
retreat .stope at Detour Lake Mine Rack Mechanics, (Eds:
Aubertin, Hassani and Mitri) (Balkema).

AMC Reference Library – www.amcconsultants.com.au 4

You might also like