1. The following is a sample data set.


10 8 8 6 5
What is the variance of this data set?
a. 3.0
b. 3.8
c. 7.3
d. 7.4

Ref: CCT Study Guide Q7

2. An auditor should use a histogram in a quality audit to do which of the following?

a) Provide objective evidence that the auditee uses statistical process control (SPC)
b) Expose patterns that are normally difficult to detect
c) Interpret data for a trend chart
d) Create a stratified tally diagram

Ref: CBA Study Guide Q2

3. Comparing how a process is actually performed against the documented work


instruction for that process is an example of which of the following techniques?

a. Quantitative
b. Qualitative
c. Statistical
d. Random sampling

Ref: CBA Study Guide Q4

4. Attribute sampling should be used when

a. the data are measurements in metric units.


b. a yes-or-no decision is to be made.
c. the population has variability.
d. a multi-stage sampling plan is needed.

Ref: CHA Study Guide Q10.

5. Scatter diagrams are best described as


a. histograms.
b. correlation analysis.
c. Pareto analysis.
d. Ishikawa diagrams.

Ref: CMQOE Study Guide Q9

Page 1 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

6. In which of the following diagrams does the input variable X have the highest positive
correlation with the output variable Y?

Ref: CMQOE Study Guide Q13

8. If data are plotted over time, the resulting chart will be a


(A) run chart
(B) histogram
(C) Pareto chart
(D) Poisson distribution

Ref: Detailed CMQOE Study Guide Q5

9. To determine who are or might be customers for a specific


process, it would be most useful to create a
(A) Pareto chart
(B) flow diagram
(C) cause and effect diagram
(D) scatter diagram

Ref: Detailed CMQOE Study Guide Q13

10. A production line uses signs at specific points on the line to


indicate when components or raw materials need to be
replenished. This practice is an example of
(A) kanban
(B) poka-yoke
(C) checkpoints
(D) hoshin

Ref: Detailed CMQOE Study Guide Q16

Page 2 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

11. Which of the following is a good tool for planning cycletime


reduction and concurrent operations?
(A) A timeline
(B) A Pareto diagram
(C) An X and R chart
(D) A PERT chart

Ref: Detailed CMQOE Study Guide Q23

12. Attribute and variable data are best described as which of


the following?
Attribute Variable
(A) Counted values Measured values
(B) Counted values Visual features
(C) Measured values Counted values
(D) Visual features Counted values

Ref: Detailed CMQOE Study Guide Q28

13. All of the following are common ways for people to react
to conflict EXCEPT
(A) competing
(B) collaborating
(C) avoiding
(D) sabotaging

Ref: Detailed CMQOE Study Guide Q29

14. A quality manager has chosen to survey customer


satisfaction by taking samples based on the categories of
frequency of use, categories of use, and demographics.
This technique is known as
(A) random sampling
(B) data collection
(C) stratification
(D) customer classification

Ref: Detailed CMQOE Study Guide Q50

15. Which of the following actions is NOT used to reduce


process cycle time?
(A) Analyzing current processes
(B) Reducing queue times
(C) Setting priorities
(D) Implementing activity-based costing

Ref: Detailed CMQOE Study Guide Q59

16. A company’ s accounts payable department is trying to


reduce the time between receipt and payment of invoices
and has recently completed a flowchart. Which of the
following tools would be the best for them to use next?
(A) Fishbone diagram
(B) Scatter diagram
(C) Box and whisker plot

Page 3 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

(D) Histogram

Ref: Detailed CMQOE Study Guide Q60

17. In a manufacturing company, the machine shop is what


kind of customer in relation to the human resource
department?
(A) Intermediate
(B) Hidden
(C) External
(D) Internal

Ref: Detailed CMQOE Study Guide Q66

18. The primary purpose of a project charter is to


(A) subdivide the project into smaller, more manageable
components
(B) provide management with a tool for selecting a project
that addresses business needs
(C) provide management with a tool to ensure that project
deadlines are met
(D) provide the project manager with authority to apply
organizational resources to project activities

Ref: Detailed CMQOE Study Guide Q71

19. Sample selection of parts for inspection must be selected at random to ensure

a) a minimum sample size.


b) the probability of not rejecting the lot.
c) the probability of accepting the lot.
d) finding typical characteristics of the lot.

Ref: CQI Study Guide Q12

20. Which of the following are bases for establishing calibration intervals?

I. Stability
II. Purpose
III. Degree of usage
a. I and II only
b. I and III only
c. II and III only
d. I, II, and III

Ref: CQI Study Guide Q13

21. In a normal curve, approximately what percentage of the area is included within 3
standard deviations of the mean?

a. 50.0%
b. 66.6%
c. 95.0%

Page 4 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

d. 99.7%

Ref: CQI Study Guide Q17

22. Specification limits are derived from which of the following?

a. Process capability studies


b. Process control charts
c. Customer requirements
d. Historical data

Ref: CQI Study Guide Q17

23. The primary purpose of a control chart is to

a. set specifications and tolerances.


b. compare operations.
c. determine the stability of a process.
d. accept or reject a lot of material.

Ref: CQI Study Guide Q19

24. When a control chart is used on a new process, capability


can be assessed at which of the following times?
(A) Before the chart is first started
(B) After the first ten points are plotted
(C) When the plotted points hug the centerline
(D) After the process is shown to be in control

Ref: CQI Pdf Study Guide Q02

25. Precision is best described as


(A) a comparison to a known standard
(B) the achievement of expected outgoing quality
(C) the repeated consistency of results
(D) the difference between an average measurement and
the actual value

Ref: CQI Pdf Study Guide Q14

26. The overall ability of two or more operators to obtain


Consistent results repeatedly when measuring the same set
of parts and using the same measuring equipment is the
definition of
(A) repeatability
(B) precision
(C) reproducibility
(D) accuracy

Ref: CQI Pdf Study Guide Q39

27. Which of the following conditions must be met for a


Process to be in a state of statistical control?

Page 5 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

(A) Most of the product output by the process is in


specification.
(B) All subgroup averages and ranges are within control
limits.
(C) All variation has been completely removed.
(D) Previously optimal process settings are used.

Ref: CQI Pdf Study Guide Q43

28. Which of the following measures of dispersion is equal to


the sum of deviations from the mean squared divided by
the sample size?
(A) Range
(B) Standard deviation
(C) Variance
(D) Mode
Ref: CQI Pdf Study Guide Q44

29. An X and R chart is used to


(A) indicate process variation
(B) specify design limits
(C) interpret costs
(D) identify customer expectations

Ref: CQI Pdf Study Guide Q48

30. Which of the following is the most useful graphical tool for promoting an
understanding of process capability?

a. A flowchart
b. A histogram
c. An affinity diagram
d. An Ishikawa diagram

Ref: CQA Study Guide Q5

31. The type of chart that presents the value of items in descending order is a

a. histogram
b. Pareto chart
c. u chart
d. cusum chart

Ref: CQA Study Guide Q18

32. Measures of which of the following provide attributes data?

a. Temperature in degrees
b. Attendance at meetings
c. Weight in pounds
d. Length in metric units

Ref: CQA Study Guide Q20

Page 6 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

33. A cause and effect diagram is a useful tool for doing which of the following?

a. Determining the flow of a process


b. Detecting shifts in a process
c. Developing theories based on symptoms
d. Arranging theories by defect count

Ref: CQA Study Guide Q23

34. The fraction of nonconforming products is plotted on


which of the following types of control charts?
(A) p chart
(B) u chart
(C) np chart
(D) c chart

Ref: CQA pdf Study Guide Q07

35. Which of the following statistics would best describe the


central tendency of a sample of data?
(A) Mode
(B) Mean
(C) Standard deviation
(D) Range

Ref: CQA pdf Study Guide Q13

36. Which of the following types of tools or techniques is


considered qualitative?
(A) Histograms
(B) Frequency distributions
(C) Pareto charts
(D) Process observations

Ref: CQA pdf Study Guide Q26

37. The process information shown in the graph above is


indicative of a
(A) cycle
(B) run
(C) trend

Page 7 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

(D) shift

Ref: CQA pdf Study Guide Q55

38. Which of the following techniques is most useful in


narrowing issues and limiting discussion?
(A) Brainstorming
(B) Quality function deployment
(C) Cause and effect analysis
(D) Multivoting

Ref: CSQE pdf Study Guide Q03

39. Quality function deployment (QFD) is a methodology for


(A) removing bugs from code
(B) identifying and defining key customer demands
(C) measuring the reliability of a software product
(D) training employees in quality issues

Ref: CSQE pdf Study Guide Q24

40. Which of the following is the critical path in the activity


network above?
(A) A, B, C, F, G, I, J
(B) A, B, D, E, F, G, I, J
(C) A, B, D, E, F, H, I, J
(D) A, K, L, M, J

Ref: CSQE pdf Study Guide Q25

Page 8 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

41. On the basis of the control chart above, which of the


following statements is true?
(A) Components 1, 2, 3, and 5 should be reinspected
because they are below the mean.
(B) Only component 4 should be investigated because it
is closest to the upper control limit.
(C) Components 4, 6, 7, 8 and 9 should be investigated
because they are above the mean.
(D) No action is required; all data points are within
acceptable statistical variance.

Ref: CSQE pdf Study Guide Q31

42. A customer satisfaction survey used the following rating


scale:
1 = very satisfied
2 = satisfied
3 = neutral
4 = dissatisfied
5 = very dissatisfied
This is an example of which of the following
measurement scales?
(A) Nominal
(B) Ordinal
(C) Ratio
(D) Interval

Ref: CSQE pdf Study Guide Q38

43. Which of the following techniques is used in identifying


underlying problems?
(A) Cause and effect analysis
(B) Prioritization matrix
(C) Force field analysis
(D) Pareto analysis

Page 9 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

Ref: CSQE pdf Study Guide Q54

44. For a normal distribution, two standard deviations on each side of the mean would
include what percentage of the total population?

a. 47%
b. 68%
c. 95%
d. 99%

Ref: CSSBB Study Guide Q01

45. In measurement system analysis, which of the following pairs of data measures is
used to determine total variance?

a. Process variance and reproducibility


b. Noise system and repeatability
c. Measurement variance and process variance
d. System variance and bias

Ref: CSSBB Study Guide Q04

46. Process data being used in the initial set-up of a process are assumed to have a
normal distribution. If the nominal (target) is set at the center of the distribution, and the
specification limits are set at ± 3 from the center, the Cpk is equal to

a. -0.25
b. 1.00
c. 1.33
d. 1.67

Ref: CSSBB Study Guide Q06

47. A green belt is going to monitor the number of defects on different size samples.
Which of the following control charts would be most appropriate?

a. u
b. np
c. c
d. p

Ref: CSSBB Study Guide Q07

48. Correction, over-production, inventory, and motion are all examples of

a. waste
b. 5S target areas
c. noise
d. value-added activities

Ref: CSSBB Study Guide Q11

Page 10 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

49. The primary factor in the successful implementation of six sigma is to have

a. the necessary resources


b. the support/leadership of top management
c. explicit customer requirements
d. a comprehensive training program

Ref: CSSBB Study Guide Q12

50. Which of the following types of variation is LEAST likely to occur in sequential
repetitions of a process over a short period of time?

a. Cyclical
b. Positional
c. Temporal
d. Seasonal

Ref: CSSBB Study Guide Q15

51. The primary reason that most companies implement six sigma is to

a. reduce defects
b. improve processes
c. improve profit
d. increase customer satisfaction

Ref: CSSBB Study Guide Q16

52. The term used to describe the risk of a Type I error in a test of hypotheses is

a. power
b. confidence level
c. level of significance
d. beta risk

Ref: CSSBB Study Guide Q19

53. One characteristic of attributes data is that it is always

a. continuous
b. discrete
c. expensive to collect
d. read from a scale of measurement

Ref: CSSBB Study Guide Q24

Page 11 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

54. Which of the following tests may be used to determine whether a sample comes from a
population with an exponential distribution?

a. t
b. F
c. Chi-square
d. ANOVA

Ref: CQE Study Guide Q02

55. Which of the following tools are appropriate for a quality engineer to use in qualifying a
process that has variable data?

I. An and R control chart


II. A histogram
III. A c chart
IV. A p chart

a. I and II only
b. II and III only
c. III and IV only
d. I, II, and IV only

Ref: CQE Study Guide Q03

56. The correlation coefficient for the length and weight of units made by a process is
determined to be 0.27. If the process were adjusted to reduce the weight of each unit by
0.5 ounce, the correlation coefficient of the length and weight of the units made by the new
process would be equal to

a. 0.50
b. 0.27
c. 0.23
d. -0.23

Ref: CQE Study Guide Q05

57. A form, in either diagram or table format, that is prepared in advance for recording data
is known as a

a. cause-and-effect diagram
b. Pareto chart
c. flowchart
d. check sheet

Ref: CQE Study Guide Q06

58. A major drawback of using histograms in process control is that they

a. do not readily account for the factor of time

Page 12 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

b. are relatively difficult to construct and interpret


c. require too many data points
d. require too many intervals

Ref: CQE Study Guide Q07

59. Which of the following tools would be of the greatest use for finding the most efficient
path and realistic schedule for the completion of a project?

a. Interrelationship digraph
b. Activity network diagram
c. Tree diagram
d. Affinity diagram

Ref: CQE Study Guide Q09

60. A control plan is designed to do which of the following?

a. Supplement information contained in operator instructions


b. Support the production scheduling system
c. Provide a documented system for controlling processes
d. Provide a method for tracking the design review process

Ref: CQE Study Guide Q10

61. To determine the average number of nonconforming parts over time, which of the
following attribute control charts would be most appropriate?

a. c chart
b. np chart
c. p chart
d. u chart

Ref: CQE Study Guide Q21

62. Which of the following techniques is most appropriate for


generating continuous improvement ideas?
(A) Tree diagram
(B) Brainstorming
(C) Prioritization matrix
(D) Interrelationship digraph

Ref: CQE pdf Study Guide Q01

63. Which of the following tools is used extensively in


quality function deployment (QFD)?
(A) Affinity diagram
(B) Matrix diagram
(C) Cause and effect diagram
(D) Activity network diagram

Ref: CQE pdf Study Guide Q03

Page 13 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

64. Which of the following tools is most likely to be used to


organize a list of ideas generated during a brainstorming
session?
(A) Activity network diagram
(B) Affinity diagram
(C) Histogram
(D) Process control chart

Ref: CQE pdf Study Guide Q10

65. Which of the following tools would be most appropriate


for collecting data to study the symptoms of a problem?
(A) A check sheet
(B) A flow diagram
(C) A force field analysis
(D) An activity network diagram

Ref: CQE pdf Study Guide Q11

66. Kaizen is defined as


(A) re-engineering
(B) lean manufacturing
(C) continuous improvement
(D) error-proofing

Ref: CQE pdf Study Guide Q15

67. Legal requirements specify that a bottled product must


contain no less than the volume printed on the label. A
bottling company wants to reduce the amount of
overfilled bottles.

On the basis of the data above, what is the most effective


strategy to accomplish this task?
(A) Decrease the target fill volume only
(B) Decrease the target fill variation only
(C) First decrease the target fill volume, then decrease the
target fill variation
(D) First decrease the target fill variation, then decrease
the target fill volume

Ref: CQE pdf Study Guide Q18

Page 14 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

69. The LEAST informative of the four measurement scales


is the
(A) ratio
(B) nominal
(C) ordinal
(D) interval

Ref: CQE pdf Study Guide Q20

70. Which of the following can be used to determine the


goodness-of-fit of a distribution to a data set?
(A) t test
(B) ANOVA
(C) F test
(D) Chi square test

Ref: CQE pdf Study Guide Q21

71. When σ = 10, what sample size is needed to specify a


95% confidence interval of ±3 units for the mean?
(A) 7
(B) 11
(C) 32
(D) 43

Ref: CQE pdf Study Guide Q22

73. A process capability analysis is NOT used to


(A) determine the ability of a process to meet
specifications
(B) maintain a process in a state of statistical control
(C) establish new specifications
(D) prioritize competing processes

Ref: CQE pdf Study Guide e Q31

74. A type of line graph used to assess the stability of a


process is called a
(A) control chart
(B) Pareto chart
(C) check sheet
(D) cause and effect diagram

Ref: CQE pdf Study Guide Q37

75. A process produces nonconformities according to a


Poisson distribution. If the mean of the nonconformities
is 25, what is the standard deviation?
(A) 2.5
(B) 5.0
(C) 12.5
(D) 25.0

Ref: CQE pdf Study Guide Q38

Page 15 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

76. Five six-sided dice are rolled together 100 times. Two
histograms are constructed: one for the 500 individual
results and one for the 100 averages of five results. In this
situation, the individual results follow a uniform
distribution, while the averages follow which of the
following distributions?
(A) Normal
(B) Student’ s t
(C) Binomial
(D) Uniform

Ref: CQE pdf Study Guide Q40

77. A calibrated micrometer was used to take 10 replicated


measures of a reference standard. If X m = 0.073, and the
true value of the reference standard is 0.075, what is the
bias of the micrometer?
(A) 0.001
(B) 0.002
(C) 0.073
(D) 0.075

Ref: CQE pdf Study Guide Q42

78. The power of a test for the difference between means is


measured by
(A) α
(B) 1 - α
(C) β
(D) 1 - β

Ref: CQE pdf Study Guide Q44

79. A process is stable and its output is normally distributed.


The process has a specification of 16.73 ± 0.01. What is
the maximum process standard deviation if the Cp must
be ≥1.5 ?
(A) 0.0011
(B) 0.0022
(C) 0.0041
(D) 0.0133

Ref: CQE pdf Study Guide Q47

Page 16 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

81. Which of the following figures is labeled correctly?

Ref: CQE pdf Study Guide Q27

82. A quality improvement team that was assigned to


decrease the number of pinholes in milk jugs presented
the following Pareto diagrams during a management
briefing.

Page 17 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

The best interpretation of these data is that the project


was
(A) not successful in reducing pinholes, since causes B, C,
and D now occur more frequently than cause A
(B) successful in removing the primary cause of pinholes,
and no further improvements are necessary
(C) successful, and tracking pinholes by cause A is no
longer necessary
(D) successful in decreasing pinholes, and the team should
work on cause B to further improve the process

Ref: CQE pdf Study Guide Q51


84. The main advantage of a matrix diagram is that it
(A) displays all the possible causes related to a problem
(B) displays the strength of relationships between each
paired combination of variables
(C) identifies, analyzes, and classifies the cause and effect
relationships that exist among all critical issues
(D) identifies a sequence of actions and materials entering
a process
Ref: CQE pdf Study Guide Q55

85. Poka-yoke is best defined as


(A) improving machine efficiency

Page 18 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

(B) reducing field failures to virtually zero


(C) capturing the voice of the customer
(D) preventing controllable defects

Ref: CQE pdf Study Guide Q56

86. Which of the following describes the 95% confidence


interval of a 20% absentee rate in a department with
30 people?
(A) 6% to 34%
(B) 8% to 32%
(C) 13% to 27%
(D) 17% to 23%

Ref: CSSBB pdf Study guide Q20.

87. Which of the following are needed to calculate the


process capability index, Cp?
(A) The specification limits and the mean
(B) The specification limits and σ^ (Sigma Cap)
(C) The process mean and σ^ (Sigma Cap)
(D) The upper and lower specification limits

Ref: CQE pdf Study Guide Q63

88. Repeatability and reproducibility are terms that


operationally define
(A) bias
(B) accuracy
(C) discrimination
(D) precision

Ref: CQE pdf Study Guide Q65

89. A method that classifies data without significantly reducing


accuracy or precision is known as
(A) bias adjustment
(B) statistical efficiency
(C) blocking
(D) coding

Ref: CQE pdf Study Guide Q66

90. If a process has a variance of 4 units and a specification


of 96 ± 4, what is the process performance index (Pp)?
(A) 0.33
(B) 0.66
(C) 1.00
(D) 1.50
Ref: CQE pdf Study Guide Q72

92. If a histogram has a distribution that is bimodal


this indicates that the

Page 19 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

a. process is in control
b. distribution is abnormal
c. data collected is accurate
d. data has two points

Ref: CQIA Study Guide Q03

93. Which of the following best describes how an affinity diagram is used?

a. Grasping organizational performance relative to contrasting data


b. Prioritizing data from most significant to least significant
c. Grouping ideas that are created during brainstorming
d. Identifying when a process is in control

Ref: CQIA Study Guide Q08

94. Warranty claims are classified in which of the following cost of quality groups?

a. Internal failure
b. External failure
c. Appraisal
d. Prevention

Ref: CQIA Study Guide Q09

95. At what stage of the problem-solving process would a team most likely use a cause-
effect diagram?

e. Description of the process associated with the problem


f. Definition of the problem and its scope
g. Organization of possible problem causes
h. Collection of data to identify actual causes

Ref: CQT Study Guide Q01

96. Steel bars are cut to cylindrical shafts by means of a lathe. The diameter and allowable
tolerance of the shaft is 2.000 ± .001 inch. A control chart is used to monitor the quality
level of the process. Which of the following plots on the control chart might indicate a
problem of wear on the lathe?

a. The diameter of a single shaft above 2.001 inch


b. The diameter of a single shaft below 1.999 inch
c. An apparent increasing trend in the shaft diameters
d. Erratic in-tolerance or out-of-tolerance diameter measurements

Ref: CQT Study Guide Q03

97. A sample consists of one or more units of product drawn from a lot or batch on the
basis of

a. defect of the product

Page 20 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

b. random selection
c. size of the product
d. when the inspection process was completed

Ref: CQT Study Guide Q08

98. What is the percent yield for a normally distributed


process in which the item length specification is
5.750 ±0.004, X is 5.752, and the standard deviation is
0.002 ?
(A) 15.73%
(B) 19.15%
(C) 47.72%
(D) 83.99%

Ref: CQT pdf Study Guide Q09

99. In preparation for construction of a cause and effect


diagram, it is important to
(A) plot separate charts for each source
(B) focus only on what makes things go wrong
(C) record everything people suggest
(D) validate possible root causes

Ref: CQT pdf Study Guide Q10

100. A quality technician uses a c chart to monitor the number


of defects in a square foot of material. After the initial
startup period, the mean number of defects is calculated
at 13.5. What should the control limits be for the c chart?
LCL UCL
(A) 0.00 54.00
(B) 0.00 27.00
(C) 2.48 24.52
(D) 9.83 17.17

Ref: CQT pdf Study Guide Q11

101. The shape of the distribution above is best described as


(A) normal
(B) multi-modal
(C) positively skewed
(D) negatively skewed

Ref: CQT pdf Study Guide Q12

102. If a distribution is normal, with µ= 50 and σ= 15, what

Page 21 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

percentage of data will be less than 30 ?


(A) 59.18%
(B) 40.82%
(C) 9.18%
(D) 1.33%

Ref: CQT pdf Study Guide Q18

103. A company is receiving an unusually high number of


returns from various customers. The first step in
investigating the problem would be to
(A) check the inspection records
(B) establish the correlation of the returns to shipments
(C) brainstorm the potential causes
(D) classify the returns by type and degree of seriousn

Ref: CQT pdf Study Guide Q21

104. Which of the following activities would NOT contribute to


the effective functioning of a team?
(A) Eliminating unnecessary activities
(B) Developing team performance measures
(C) Defining processes in detail
(D) Monitoring each member’s performance

Ref: CQT pdf Study Guide Q27

105. Which of the following is the best definition of a


flow chart?
(A) A diagram used to structure ideas into useful categories
(B) An illustration used to analyze variation in a process
(C) A picture used to separate steps of a process in
sequential order
(D) An analytical tool used to clarify opposing aspects of a
desired change

Ref: CQT pdf Study Guide Q28

106. What is the standard deviation of the population below?


10, 4, 16, 12, 8
(A) 4.00
(B) 4.47
(C) 16.00
(D) 20.00

Ref: CQT pdf Study Guide Q29

107. The extent to which an instrument replicates its result


when measurements are taken repeatedly on the same
unit is called
(A) real bias
(B) precision
(C) accuracy
(D) true value

Page 22 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

Ref: CQT pdf Study Guide Q34

109. On the basis of the control chart sample above, what is the
upper control limit (UCL) for the average?
(A) 1.23
(B) 3.21
(C) 3.43
(D) 7.25

Ref: CQT pdf Study Guide Q40

110. Which of the following measures is a sufficient statistic


for the parameter µ?
(A) Median
(B) Mid-range
(C) Mean
(D) Mode

Ref: CQT pdf Study Guide Q41

111. What is the recommended minimum number of subgroups


necessary to calculate the limits for a control chart?
(A) 10
(B) 15
(C) 25
(D) 35

Ref: CQT pdf Study Guide Q44

112. The distribution above most likely implies that the

Page 23 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

elements measured represent


(A) the extremes of a single process
(B) a collection of two processes with normal distributions
(C) random variations
(D) the modes of a single process
Ref: CQT pdf Study Guide Q45

113. Which of the following describes the Deming method for


continuous improvement?
(A) Cost of quality analysis
(B) Process map
(C) Tree diagram
(D) Plan-do-check-act cycle

Ref: CQT pdf Study Guide Q46

114. Which of the following is the formula for calculating the


number of permutations of x units taken y at a time?

Ref: CQT pdf Study Guide Q48

115. In an analysis of variance, which of the following distributions is the basis for
determining whether the variance estimates are all from the same population?

a. Chi square
b. Student's t
c. Normal
d. F

Ref: CRE Study Guide Q05

116. Which of the following statements best describes the set


of all values of a random variable?
(A) It is finite.
(B) It is an interval.
(C) It can be discrete or continuous.

Page 24 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

(D) It can be tracked by using control charts or


scatter plots.

Ref: CRE pdf Study Guide Q14

117. Which of the following is the best description of


randomization?
(A) A technique used to increase the precision of an
experiment
(B) A means of assuring representative sampling
(C) The repetition of an observation or measurement
(D) The relationship between two or more variables

Ref: CRE pdf Study Guide Q15

118. When the order of items is not important, which of the


following is the method to use to determine the number of
sets and subsets of items?
(A) Combination
(B) Permutation
(C) Factorization
(D) Simulation

Ref: CRE pdf Study Guide Q22

119. A fair coin is tossed 10 times. What are the expected mean
and variance of the number of heads?
Mean Variance
(A) 0.5 0.025
(B) 5.0 2.500
(C) 5.0 5.000
(D) 10.0 5.000

Ref: CRE pdf Study Guide Q25

120. In statistics, an estimation error that is persistent or


systematic is called
(A) bias
(B) sensitivity
(C) random
(D) shift

Ref: CRE pdf Study Guide Q43

121. Which of the following is the most effective technique


for prioritizing critical factors for problem-solving?
(A) Venn diagram
(B) Scatter diagram
(C) Pareto diagram
(D) Cause and effect diagram

Ref: CRE pdf Study Guide Q52

Page 25 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

122. Which of the following tools should be used when a team


is generating and prioritizing a list of options that include
highly controversial issues?
(A) Brainstorming
(B) Affinity diagrams
(C) Nominal group technique
(D) 5 whys

Ref: CSSBB pdf Study guide Q01

124. Which of the following tools would be most appropriate


for collecting data to study the symptoms of a problem?
(A) Check sheet
(B) Flow diagram
(C) Force-field analysis
(D) Activity network diagram

Ref: CSSBB pdf Study guide Q03

125. Positional, cyclical, and temporal variations are most


commonly analyzed in
(A) SPC charts
(B) multi-vari charts
(C) cause and effect diagrams
(D) run charts

Ref: CSSBB pdf Study guide Q04

127. Which of the following is most important in evaluating


and understanding design intent?
(A) Identifying the functional requirement
(B) Brainstorming failure modes
(C) Conducting computer simulations
(D) Developing FMEA

Ref: CSSBB pdf Study guide Q07

128. Which of the following activities is value-added?


(A) Setup
(B) Process
(C) Storage
(D) Inspection

Ref: CSSBB pdf Study guide Q09

129. A Green belt plans to test the performance of workers


before and after training. Which of the following
hypothesis tests should be used to determine whether the
training actually improved the workers’ performance?
(A) 2-sample z test
(B) 2-sample t test
(C) Paired t test
(D) F test

Page 26 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

Ref: CSSBB pdf Study guide Q10- minor change

130. The purpose of using control charts is to determine


(A) if the process is performing within specifications
(B) the process capability
(C) how to re-create the process
(D) the cause of nonconformities

Ref: CSSBB pdf Study guide Q11

132. Which of the following is defined as continuous,


incremental improvement?
(A) Kanban
(B) Kaizen
(C) JIT
(D) Kaikaku

Ref: CSSBB pdf Study guide Q13

133. Which of the following is the best way to enhance the


long-term availability of a machine?
(A) Machine repair
(B) Total productive maintenance
(C) Computerized SPC systems
(D) Increased operator training

Ref: CSSBB pdf Study guide Q16

134. Typically, which of the following activities is done


earliest in the formation of a project team?
(A) Select the team
(B) Identify the objective
(C) Identify the sponsor
(D) Allocate the resources

Ref: CSSBB pdf Study guide Q17

135. A Green belt is developing a failure mode and effects


analysis (FMEA) for the hamburger preparation station in
a fast-food restaurant. The following ratings were
developed for the low-heat temperature failure mode.
Severity = 9
Occurrence = 2
Detection = 1
What is the risk priority number (RPN) for this FMEA?
(A) 4
(B) 6
(C) 12
(D) 18

Ref: CSSBB pdf Study guide Q18- minor change

136. Which of the following statements is true about the


theory of constraints?

Page 27 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

(A) It views a system in terms of discrete processes


(B) Most constraints are physical
(C) Most constraints are the result of policies
(D) It focuses on continuous improvement

Ref: CSSBB pdf Study guide Q19.

139. A measurement system analysis is designed to assess the


statistical properties of
(A) gage variation
(B) process performance
(C) process stability
(D) engineering tolerances

Ref: CSSBB pdf Study guide Q23.

140. For a process, X double bar = 35.0 and σ = 5.00. If the subgroup
size is n = 5, what is the value for the upper control limit
for the process?
(A) 37.24
(B) 37.89
(C) 41.71
(D) 52.50

Ref: CSSBB pdf Study guide Q25.

142. A six sigma project to reduce billing statement expenses


has shown the need to hire two additional mailroom
clerks. Based on this information, which of the following
metrics should be used to measure the financial benefits
of the project?
(A) Cost of poor quality
(B) Return on investment
(C) Net present value
(D) Internal rate of return

Ref: CSSBB pdf Study guide Q27.

144. Which of the following is a component of a visual


factory?
(A) Product specifications
(B) Zero defect policies
(C) Just-in-time policies
(D) Equipment service manuals

Ref: CSSBB pdf Study guide Q30.

146. Which of the following is the best technique for


improving the precision of a designed experiment when
the experimental material is not homogeneous?
(A) Blocking
(B) Confounding
(C) Randomization
(D) Fractionalizing

Page 28 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

Ref: CSSBB pdf Study guide Q32.

147. A six sigma team has been formed to improve an existing


process. Which of the following tools should the team use
first to gain a clear understanding of the current process?
(A) Flowchart
(B) Pareto chart
(C) Process FMEA
(D) Latin square DOE

Ref: CSSBB pdf Study guide Q34.

151. A company’s accounts payable department is trying to


reduce the time between receipt and payment of invoices.
If the team has just completed a flowchart of the process
and identified the critical steps, which of the following
tools should be used next?
(A) Fishbone diagram
(B) Scatter diagram
(C) Box and whisker plot
(D) Histogram

Ref: CSSBB pdf Study guide Q39.

152. When a team consists of five black belts and eight quality
engineers, how many unique meetings could be held
consisting of one black belt and two quality engineers?
(A) 40
(B) 80
(C) 140
(D) 280

Ref: CSSBB pdf Study guide Q40.

155. A six sigma team has been chartered to improve the way
in which a company takes orders for its products. Which
of the following tools should the team use to determine
all of the potential pitfalls and the actual defects that
occur?
(A) Process failure mode and effects analysis
(B) Process map
(C) Design for six sigma
(D) Supplier input process output control

Ref: CSSBB pdf Study guide Q46.

156. According to Juran, anyone is a customer of a product or


service if that person
(A) purchases it
(B) uses it
(C) is affected by it
(D) produces it

Page 29 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

Ref: CSSBB pdf Study guide Q47.

157. For an F-test to be inferentially valid, all of the following


assumptions must be true EXCEPT the
(A) populations must be discrete distributions
(B) populations must be normally distributed
(C) samples must be independent
(D) samples must be randomly selected from the
population

Ref: CSSBB pdf Study guide Q49.

158. “Forming, Storming, Norming, and Performing” are


terms that describe
(A) process variation reduction and improvement phases
(B) root cause identification and corrective action
(C) stages of team growth
(D) steps of the brainstorming process

Ref: CSSBB pdf Study guide Q51.

159. The process of having a six sigma team develop a


problem statement helps the team
(A) agree on key dates associated with completing major
project phases
(B) achieve consensus and ownership of the process
(C) determine solutions
(D) determine how often it should meet

Ref: CSSBB pdf Study guide Q54.

160. Which of the following is an element of standard work?


(A) Takt time
(B) Product cost
(C) Product value
(D) Maximum inventory

Ref: CSSBB pdf Study guide Q55.

161. An important aspect of data collection is that the data


collector should
(A) determine the dispersion of the data
(B) know how the data are to be used
(C) use a control chart to analyze the data
(D) use a stratified sampling plan

Ref: CSSBB pdf Study guide Q56.

163. Which of the following charts plots the mean of a set of


values and recalculates the mean with each new value?
(A) Moving range
(B) Moving average
(C) X and s
(D) c

Page 30 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

Ref: CSSBB pdf Study guide Q58.

164. In order for a problem to be solved correctly, which of


the following must occur first?
(A) The problem must be defined.
(B) Relevant data must be gathered.
(C) The measurement system must be validated.
(D) The process must be mapped.

Ref: CSSBB pdf Study guide Q60.

165. In comparison to a full-factorial design of experiment


(DOE), a traditional, one-at-a-time approach will
(A) miss interactions
(B) gain efficiencies
(C) save time
(D) cost less

Ref: CSSBB pdf Study guide Q61.

167. Which of the following techniques is NOT effective


when a team leader is giving feedback to the team?
(A) Describing the behavior in context
(B) Describing the reasons for giving feedback
(C) Giving feedback when it is convenient
(D) Providing actionable guidance

Ref: CSSBB pdf Study guide Q64.

168. Which of the following methods is used to develop an


exhaustive list of ideas about a subject?
(A) Benchmarking
(B) Brainstorming
(C) Goal-setting
(D) Problem-solving

Ref: CSSBB pdf Study guide Q66.

169. Which of the following techniques would help increase


process stability when the cause of variation is a cluttered
work station?
(A) 5S
(B) SMED
(C) Preventive maintenance
(D) Visual factory

Ref: CSSBB pdf Study guide Q67.

170. Which of the following tools is commonly used in the


define phase of a project?
(A) Affinity diagram
(B) Control chart
(C) Failure mode and effects analysis

Page 31 of 32
Certified Sixsigma Greenbelt Handbook
Practice Questions
(Selected from the past ASQ Exam questions and Study guide to match the BOK and Cognitive levels)

(D) Data collection checklist

Ref: CSSBB pdf Study guide Q69.

172. Which of the following best describes internal failure


costs?
(A) The economic costs associated with a catastrophic
failure of an internal subsystem.
(B) The unavoidable quality system costs associated with
the production of any product or service.
(C) The opposite of external failure costs.
(D) The costs resulting from a nonconformance detected
before a product or service is provided.

Ref: CSSBB pdf Study guide Q71.

173. According to Juran, when a major quality improvement


project is launched, which of the following describes the
desired change in performance level?
(A) Six sigma
(B) Continuous
(C) Breakthrough
(D) Sporadic

Ref: CSSBB pdf Study guide Q72.

174. According to Deming, which of the following is NOT a


key element of quality leadership?
(A) Established organizational goals to meet or exceed
customer needs
(B) The use of displays and awards to promote employee
motivation
(C) Continual education and training that elevate the level
of technical and professional expertise
(D) Elimination of barriers and distrust to create an
organizational culture that fosters teamwork

Ref: CSSBB pdf Study guide Q73.

Page 32 of 32