Professional Documents
Culture Documents
DESIGN BACKGROUND
Introduction
Petrochemicals, which are chemical products derived from petroleum, are the
building blocks for a wide range of materials such as solvents, detergents plastic
growth. Despite of its importance, only a few companies have invested to partake
precursor to styrene which is used to make polymers and plastics. Some 20% of
1
benzene manufacturing plant. This plant produces benzene through the
hydrodealkylation of toluene.
Process Description
process used to produce benzene. The main reaction in the process is:
conversion of 90%. The reaction is highly exothermic and the typical operating
conditions are 500 to 660 degrees Celsius, and 20 to 60 bar. Figure 1 shows the
2
The HDA process begins with mixing fresh toluene with a stream of recycle
unreacted toluene, the mixing is achieved in a storage tank. The toluene is then
pumped to combine it with a stream of mixed hydrogen and fresh hydrogen gas.
heater or furnace. In the furnace the stream is heated to 600 C, the reaction
temperature, then introduced into the reactor. The reactor is where the main
reaction happens:
alumina.
selectivity but requires frequent regeneration of the catalyst. The products are
then cooled and introduced into a pair of separators that separate the unreacted
the feed and the reactor. The products leaving the separators are then heated
from the stream and recycle to the feed. This allow for greater conversion. Then
further fractionation separates methane and toluene from the benzene product.
The heating requirements are achieved with low, high and medium pressure
3
Raw Materials
1. Toluene
Toluene is an aromatic hydrocarbon. It is colorless, water Soluble
will serve as the feed for the HDA process and will be converted to
Benzene
The toluene feed of the HDA plant will be bought from Petron
Bataan Refinery which has a Toluene capacity of 150000 MT. The refinery
in petroleum and chemical industries for processing of fossil fuels. The key
hydrocracking.
The hydrogen will be supplied by Air Liquid’s Steam methane
3. Catalyst
The catalyst we will use in the reactor is a Molybdenum based
4
Products
1. Benzene
Benzene is an organic chemical compound with the chemical
styrene which is used to make polymers and plastics. Some 20% of the
and is the main constituent of natural gas. This can be used to fuel fired
supply and demand is driven by other products derived from it. Benzene is a
basic chemical and a building block for many other chemical synthesis of the
5
nitrobenzene, cumene, cyclohexane, alkyl benzene, chlorobenzene, aniline, and
phenol.
chemicals & materials, automotive, textiles and building & construction have
influencing the benzene market growth. Rising population in tandem with the
and bulk materials. Low cost of the feedstock and economical commodity product
disproportionation (TDP).
(HDA) and transalkylation (TA). In HDA, toluene reacts with hydrogen to give
6
the conversion of 1, 2, 4-trimethylbenzene to xylene. This chemical process
as chromium or molybdenum.
layout, and equipment, the designers came up with the idea of hydrodealkylation
processing plant.
Location Plan
Expressway at Limay, Bataan. Several factors are considered for the selection of
geographically located along the coast connected to the sea which means an
easy access for ships and vessels. Furthermore, the location is favorable due to
its proximity to Petron Bataan Refinery where we will get the HDA Plant’s Toluene
Feed.
The plant would provide numerous job opportunities for the people around
the area. To ensure public safety, the plant location is located as far from
7
Figure 2: Plant Location and its proximity to Petron Bataan Refinery
2016–2022: The impetus for this growth comes from demand in Asia, which is
activities.
Major demand for aromatics is expected to come from the Asian region,
since most of the derivative units (styrene, phenol, PET, and gasoline) are
sectors (5 – 6 percent growth) would be the key segments driving the demand.
Around 1.5 MMT capacity additions planned for styrene in Asia and the Middle
yield from lighter feedstock will continue to reduce the output of aromatics in
8
the US and the EU, thus making the regions increasingly import dependent.
This demand from the western markets will be met by surplus capacity
With the wide applications of benzene such as for formulating high octane
fuels, for use as commercial solvent and for making paints, thinners and plastics,
the demand for benzene is projected to be high. To meet this demand, the
CHAPTER II
9
The principal thrust of this project proposal is to design a
Hydrodealkylation Process Plant that will process benzene as its raw materials to
produce toluene.
Specifically, this study aims to meet the following objectives for the
proposed plant in order to come up with a feasible and economical project design
economic aspects that will justify the viability of the proposed project.
3. To assign the proper technical design specifications for the equipment
following:
6.1 Identification and assessment of the hazards;
6.2 Control of hazards;
10
6.3 Control of the processes; and
6.4 Limitations of the loss
7. To choose the best design option following the Worst Case Design
philosophy.
8. To provide a construction management, project scheduling of
CHAPTER III
This chapter presents the data and information as well as the assumptions
related to the technical aspects and economical information needed for the
technically viable design. Technical catalogues were used to carefully identify the
Three Designs are presented and the best design option will be selected
the minimum required equipment. This design helps reduce costs by only
benzene.
configuration of the plant equipment and the streams entering and exiting
each equipment.
12
Fig ur e 3: Sim ula t io n Pr ocess Flow Diagr am
Hy d ro d e a l k y t i o n o f To l u e n e
S P 2 C1
S 1 4 Re c y c le Hy d ro g e n
S 1 2
S 1 3
S 2 0
S 2 2
S 1 5 S 1
M5
M6 Fuel G as
S 1 6
S P 1 S 2 5
S 1 7
M2 S 7
Hy dr ogen
M4
S 9
S 1 8
R1
S 6
S 8
M3 S 4
S 3 S C 2
S 2 8
S 5
E 2
E 1 E 5 F 1 S 2 6
S 2 S 2 3
S 1 S 1 0
M1 S 2 7
P 1
o lu ene
T
F 2
Benz ene
E 4
S 1 9
S 2 1
E 3
S C 1
S 2 4
o lu e n e Re c y c le
T
13
The process starts with combining the fresh toluene stream S1 with the
recycle toluene stream S24 in the mixer M-1 to form stream S2. The stream S2 is
then pumped (P-1) to 25.5 bar and is combined in a mixer M-3 with stream S16,
this stream is a mixture of fresh feed hydrogen mixed with unreacted hydrogen, it
also contains traces of toluene benzene and methane. The stream S16 is the
outlet of mixer M-2, this mixer combines the fresh stream of hydrogen S17 and
the unreacted recycle stream of hydrogen S14. The two phase stream exiting the
mixer M-3 is then introduced into heat exchanger E-1 in the tube side. High-
pressure stream is used in this heat exchanger in the shell side to heat up the
stream S5 is a one-phase stream of all vapor. The pressure drop for all the heat
The process stream is then introduced into the heater E-2, where it is heated
up to 600 C. This temperature is the required temperature that will allow the
reaction to happen in the reactor. The now heated up stream S6 is combined with
recycle compress hydrogen S15 in mixer M-4. Since the reaction is highly
reactor. The feed is then introduced to the main part of the process the reactor R-
1. The process stream now containing a high amount of benzene exits the
product stream S8 to heat exchanger E-5. In this heat exchanger the process
14
stream is cooled to 38 oC, by using cooling water. The outlet stream, S28, is a
two-phase stream that is introduced into the first separator F-1. This knock out
drum separates mostly all hydrogen and methane and it also contains traces of
toluene and benzene. The pressure and temperature of this flash drum must be
The overhead stream S9 is then split into two streams S11 and S12 in splitter
pressure of 25.5 bar. The compressed gas S13 is then introduced into splitter
SP-2, which splits the splitter into stream S14 and S15. Stream S14 is mixed with
the fresh feed of hydrogen, and stream S15 is used to control the temperature of
The bottom stream S10 of the separator F1 is introduce into the second
separator F2, which separates more hydrogen and methane from benzene and
toluene. The liquid bottom stream S19 is then heated up in heat exchanger E-3
to 90oC. The overhead stream S18 is combined with the overhead of the first
must be specified. In this case 99% of the benzene must exit at the overhead
and 98.85% of the toluene must exit at the bottom of the separation unit. The
15
temperature and pressure of the overhead and the bottom must be specified in
order for the simulation to be properly represented. The temperatures are 112 oC
and 2.43 bar. The bottoms of this stream calculator S24 is the recycle toluene
that is mixed in M1 with the fresh toluene feed. The overhead of this separator is
then introduced into another stream calculator SC2, which simulates the
condenser and reflux drum and pump of the distillation tower. This stream
calculator separates all the hydrogen and methane in the overhead S25, from the
toluene and benzene in the bottoms S26. The stream S25 is then combined in a
mixer M6 with the rest of the gas that composes the fuel gas. The stream S26 is
then introduced into a heat exchanger E4 where the benzene product is cooled
16
B. Design Option 2.
17
Fresh and recycled liquid toluene is pumped from TNK-100 and is
combined with a high pressure hydrogen feed and a recycled gas stream
steam in exchanger E-100 and then heated further to 600 degCelsius in fired
heater E-101 prior to being fed into reactor R-100. The feed enters the reactor
at a pressure of 2500 kPa. The reactors is of the catalytic packed bed type, is
moderate the temperature rise in the reactor. A small flow of cold gas, stream
S24, is used for further reactor temperature control. The reactor effluent is
cooled and partly condensed in exchanger E-102 using cooling water and
partial separation of this stream is achieved in high pressure (V-100) and low
pressure (V-101) flash drums. Part of the overhead vapour from V-100 is
recycled via compressor K-100 to the reaction section. The liquid product from
the low pressure flash drum is heated to near its bubble point in E-103 using
toluene bottoms stream, S19, which is recycled to the toluene storage tank,
and a small non-condensate gas stream, S16, vented from the column’s reflux
drum. This vent stream, the balance of vapour from V-100 and all the vapour
from V-101 are combined in MIX-101 and become fuel gas for use in the plant
or elsewhere on the site. The benzene product from the column is cooled in
exchanger E-104 using cooling water prior to being pumped in the storage.
18
C. Design Option 3
energy is saved by using the outlet stream leaving the reactor as its
coming from the mixer, via a heat exchanger (Fehe) some energy
integration is achieved
the configuration of the plant equipment and the streams entering and
19
Figure 6. Design Option 3 PFD
20
The process starts by combining fresh toluene feed, recycled toluene, and
Hydrogen gas mixed with traces of methane. This initial feed is passed through a
degrees Celsius. The heated feed mixture is then fed to an adiabatic reactor
the aromatics from non-condensable hydrogen and methane. Liquid stream from
traces of hydrogen and methane rom the aromatics. Toluene, benzene, and
biphenyl are separated in two distillation columns. The first column separates the
product – Benzene – from biphenyl and Toluene before being fed to the second
distillation column, which will separate Toluene from biphenyl. Recycled Toluene
from the second distillation column is fed back to the initial stream, which is the
fresh Toluene.
This section includes all the equipment used to run the HDA processing
plant.
A. Mixer
Chemical mixers set up and operate machines that mix chemicals.
mix for a specified period of time and to a desirable quality. They also test
21
resulting solutions for parameters such as viscosity, temperature and
density.
pumps use some sort of compressional action to displace the fluid. This
pressure on the fluid in order to displace it. This motor can be powered by
22
Figure 8. Pump
C. Compressor
increase the pressure on a fluid and both can transport the fluid through
liquids.
23
Figure 9. Compressor
D. Pre-Heater
A preheater is any device designed to heat a substance before
coil. The purpose of the preheater is to recover the heat from the
boiler flue gas which increases the thermal efficiency of the boiler by
reducing the useful heat lost in the flue gas. As a consequence, the flue
gases are also conveyed to the flue gas stack (or chimney) at a lower
flue gas stack. It also allows control over the temperature of gases leaving
24
Figure 10. Pre-heater
E. Heat Exchanger
A heat exchanger is a device used to transfer heat between two or
more fluids. Heat exchangers are used in both cooling and heating
as engine coolant flows through radiator coils and air flows past the coils,
which cools the coolant and heats the incoming air. Another example is
the heat sink, which is a passive heat exchanger that transfers the heat
25
generated by an electronic or a mechanical device to a fluid medium, often
For better water conservation, an ecofriendly air cooler will have larger
wastage. The cooler will absorb heated air into its system which is passed
through the water and cooling media. It is in this area where the actual
cooling system takes place where heat and moisture is absorbed and
evaporated. The resulting cold air is blown out of the system with the help
of powerful motor driven fans. The piping system distributes cold moisture,
26
Figure 12. Cooler
G. Flash Drum
A flash drum is a very simple vessel which separates vapor from
sometimes not. A liquid or liquid vapor mixture flows in, the vapor that boils
off goes out the pipes at the top and the liquid that remains flows out the
bottom.
27
Figure 13. Flash Drum
H. Splitter
Component splitter works as its name says: it redistributes each of
of both outlet streams, you may need to include an energy stream feeding
28
Figure 14. Splitter
I. Reactor
A chemical reactor is an enclosed volume in which a chemical
Chemical engineers design reactors to maximize net present value for the
given reaction. Designers ensure that the reaction proceeds with the
energy removal, raw material costs, labor, etc. Energy changes can come
29
in the form of heating or cooling, pumping to increase pressure, frictional
storage of heat or cold. The term can be used for reservoirs (artificial lakes
and ponds), and for manufactured containers. The usage of the word tank
common in British English. In other countries, the term tends to refer only
to artificial containers.
30
Figure 16. Storage Tanks
K. Furnace
A furnace is a device used for high-temperature heating. The name
derives from Latin word fornax, which means oven. The heat energy to
furnaces.
31
Figure 17. Furnace
L. Distillation Column
The distillation column is made up of a series of stacked plates. A
liquid feed containing the mixture of two or more liquids enters the column
at one or more points. The liquid flows over the plates, and vapor bubbles
up through the liquid via holes in the plates. As liquid travels down the
column, the vapor comes in contact with it several times due to the
vapor phases are brought into contact because as one molecule of higher
another molecule of the low boiling material utilizes the free energy to
convert from liquid to vapor phase. The base of the distillation column
contains a large volume of liquid consisting mostly of the liquid with higher
boiling point (in our example, this would be water). Out of the base flows
32
some of this liquid, some of which is heated in the re boiler and returned to
air condenser is simply a naked tube where the cooler fluid is the
enclosed in a larger tube so that cooling water is able to pass in the space
the inner tube whilst the cooling water flows upward through the outer
33
Figure 19. Condenser
N. Reboiler
Reboilers are heat exchangers typically used to provide heat to the
bottom of industrial distillation columns. They boil the liquid from the
the column to drive the distillation separation. The heat supplied to the
the condenser at the top of the column. Proper reboiler operation is vital to
driving the separation comes from the reboiler. The reboiler receives a
liquid stream from the column bottom and may partially or completely
vaporize that stream. Steam usually provides the heat required for the
vaporization.
34
Figure 20. Reboiler
Equipment Specifications
35
E-2 Heater S5 S6 Outlet temperature = 600 C
Heat
E-3 S19 S21 Outlet temperature = 90 C
Exchanger
E-4 Cooler S26 S27 Outlet temperature = 38 C
E-5 Cooler S8 S28 Outlet temperature = 38 C
Flash Pressure = 23.9 bar, Temp
F-1 S28 S9,S10
Drum = 38 C
Flash Pressure = 2.8 bar, Temp =
F-2 S10 S18,S19
Drum 38 C
Recycle stream flowrate =
SP-1 Splitter S9 S11,S12
440 kgmol/hr
Recycle to the reactor = 40
SP-2 Splitter S13 S14,S15
kgmol/hr
Duty = 0, product phases,
R-1 Reactor S7 S8 global temp = -22.2 C, 75%
Conversion
Overhead product = 99%
Stream
SC-1 S21 S23,S24 benzene, Bottoms product
Calc.
= 98.85 % toluene
Stream Overhead product = 100%
SC-2 S23 S25,S26
Calc. H2, 100% CH4
36
TEE-100 Splitter S10 S20, S21 Efficiency ratio = 73%
Level
Outlet Pressure = 2.9
VLV-100 Control S11 S12
bar
Valve
Low
V-101 Pressure S12 S13, S14 Pressure Drop = 0
Flash Vessel
Pressure drop = 0.3 bar
E-103 Pre-heater S14 S15 Outlet temperature = (0
degC
Pressure
Outlet Pressure = 2.6
VLV-101 Control S13 S26
bar
Valve
Fictitious Use Lowest Feed
X-100 S15 S16, S17
unit Pressure Option
Condenser Pressure =
2.5 bar
T-100 Column S17 S18, S19
Reboiler Pressure = 2.8
bar
Outlet Temperature = 38
E-104 Cooler S18 Benzene degC
Pressure drop = 0.2 bar
Outlet Pressure = 25.5
K-100 Compressor S20 S22 bar
Efficiency = 75%
TEE-101 Splitter S22 S23, S24 Flow Ratio = 5%
Control Outlet Pressure = 2.6
VLV-102 S21 S25
Valve bar
S3, S23,
M-100 Mixer S4 Pressure Drop = 0 bar
H2 Feed
S16, S25,
M-101 Mixer Fuel Gas Pressure Drop = 0 bar
S6
Equipm
Equipment Input Output Operating
ent
Type Streams Streams Parameters
Number
37
Toluene Toluene Outlet Pressure = 25.8
P-100 Pump
Feed Feed bar
Hydrogen
Feed,
M-100 Mixer S1 Pressure Drop = 0 bar
Toluene
Feed, S20
Heat Outlet temperature =
HX-100 S1, S4 S2, S26
Exchanger 90C
Operating
E-100 Furnace S2 S3
Temperature = 600C
Pressure Drop = 0.1
bar
R-100 Reactor S3 S4
Outlet Temperature =
38C
E-101 Cooler S26 S5 Pressure Drop = 0 bar
Pressure = 2.8 bar,
T-100 Flash Drum S5 S22, S6
Temp = 38 C
Pressure = 2.8 bar,
T-101 Flash Drum S6 S21, S7
Temp = 38 C
Distillation
D-100 S7, S9, S12 S8, S11
Column
S9, S10 Condenser Pressure =
C-100 Condenser S8
(Benzene) 2.5 bar
Reboiler Pressure =
RB-100 Reboiler S11 S12, S13
2.8 bar
Distillation
D-101 S13 S14, S17
Column
Condenser Pressure =
C-101 Condenser S14 S15, S16
2.5 bar
S18, S19 Reboiler Pressure =
RB-101 Reboiler S17
(Biphenyl) 2.8 bar
Recycled
Outlet Pressure = 25.8
P-101 Toluene S16 S20
bar
Pump
S-100 Splitter S22 S23, S24 Efficiency ratio = 73%
Outlet Pressure = 25.5
K-100 Compressor S24 S25 bar
Efficiency = 75%
Material Balance
38
After designing the process, a material balance calculation for each
Design Option 1
The first design option has a feed of 50000 tonnes of toluene and 1502
39
M-3 mS16+mS3 = mS16
(Mixer) 404.77 + 83.572 = 488.342
40
F-2 mS10 = mS18 + mS19
(Flash Drum) 84.003 = 1.801+ 82.202
= 97.15% conversion
Design Option 2
processes.
41
Table 5. Mass Balance of Design Option 2
R-100
mS7+mff = mS6
(Reactor)
4,713.79 + 681.51 = 5,679.26
42
Conversion = Benzene Output / Toluene Input x 100%
= 80.3% conversion
Design Option 3
processes.
mS2+mwr = mS1
Heater
5,693.49 + 14.27 = 5707.76
mS3+mvr = mS2
Furnace
5,679.26 + 14.23 = 5,693.49
mS26+mSwr = mS4
Heater
4,702.00 + 11.78= 4,713.79
43
mS26+mwr = mS4
Cooler
4,690.25 + 11.76 = 4,702.00
mS6+mS22 = mS5
Flash Vessel
4,645.75 + 28.14= 4,662.10
mS15+mwr = mS14
Flash Vessel
4,662.10 + 27.91 = 4,634.13
mS8+mS19 = mS7
Distillation Column
4622.55 + 11.59 = 4,634.13
= 85.78% conversion
Energy Balance
Design Option 1
44
Equipment Number/ Energy Balance Calculations
Description
Qin = mCp(tout-tin)
Qin = (9751.383976 kg/hr)(6149 J/kg-K)(436.905-
E-1
316.219)(1hr/3600)
(Preheater)
Qin = 2010134.62 J/s = 2010.13462 kW
Qin = mCp(tout-tin)
Qin = (9751.383976 kg/hr)(6149 J/kg-K)(873-
E-2
436.905)(1hr/3600)
(Heater)
Qin = 7263557.141 J/s = 7263.557141 kW
Qin = mCp(tout-tin)
Qin = (6681.287316 kg/hr)(1707.76 J/kg-K)(363-
E-3
311)(1hr/3600)
(Heat Exchanger)
Qin = 164811.6199 J/s = 164.8116199 kW
Qout = mCp(tin-tout)
Qout = (4768.758649 kg/hr)(1700.08 J/kg-K)(385-
E-4
311)(1hr/3600)
(Cooler)
Qout = 166649.4636 J/s = 166.6594636 kW
Qout = mCp(tin-tout)
Qout = (10021.00649 kg/hr)(5354.2 J/kg-K)
E-5
(944.015-311)(1hr/3600)
(cooler)
Qout = 9434468.386 J/s = 9434.468386 kW
Efficiency = 98.5%
45
Design Option 2
processes.
ES4=24,552.25775kW
Ewr=24,552.25775(.0025)
=61.38kW
Heater
ES5=24,552.2577 – 61.38
=24,490.88kW
ES5=24,490.88kW
Evr=24,490.88(.0025)
=61.23kW
Furnace
ES5=24,490.88 – 61.23
=24,429.65kW
ES6=24,429.65kW
Eff=24,429.65(.12)
=2931.56kW
Reactor
ES7=24,429.65(.95) – 2,931.56
=20,276.61kW
46
ES7=20,276.61kW
Ewr=20,276.61(.0025)
=50.69kW
Cooler ES9=20,276.61 – 50.69
=20,225.92kW
ES9=20,225.92kW
ES10=20,225.92(.006)
=121.36kW
Flash Vessels
ES11=20,225.92 – 121.36
=20,104.56kW
mS12=20,104.56kW
mS13=20,104.56(.006)
=120.63kW
Flash Vessels
mS14=20,104.56 – 120.63
=19,983.94kW
ES14=19,983.94kW
Ewr=19,983.94(.0025)
=49.96kW
Heater
ES15=19,983.94 – 49.96
=19,933.98kW
ES15=19,933.98kW
ES16=19,933.98(.006)
=119.60kW
Fictitious Unit
ES17=19,933.98 – 119.60
=19,814.37kW
ES17=19,814.37kW
ES19=19,814.37(.0025)
=49.54kW
ES18=19,814.37 – 49.54
Column
=19,764.84kW
47
ES18=19,764.84kW
Ewr=19,764.84(.0025)
=49.41kW
Cooler Benzene=19,764.84-49.41
=19,715.42kW
Ev=23.3kg/hr x 1hr/3600s
Compressor =6.47E-3 x 15,485.6 kJ/kg
=100.23kW
Efficiency = 80.3%
Design Option 3
processes.
48
Table 9. Mass Balance of Design Option 3
ES1=24,552.25775kW
Ewr=24,552.25775(.0025)
=61.38kW
Heater
ES2=24,552.2577 – 61.38
=24,490.88kW
ES2=24,490.88kW
Evr=24,490.88(.0025)
=61.23kW
Furnace
ES3=24,490.88 – 61.23
=24,429.65kW
ES3=24,429.65kW
Eff=24,429.65(.12)
=2931.56kW
Reactor
ES4=24,429.65(.95) – 2,931.56
=20,276.61kW
ES4=20,276.61kW
Ewr=20,276.61 (.0025)
=50.691525kW
Heater ES26=20,276.61– 50.691525
=20,225.91848kW
ES4=20,225.91848kW
Ewr=20,225.91848 (.0025)
=50.56479619kW
Cooler
ES26=20,225.91848kW -50.56479619kW
=20,175.35368kW
49
ES5=20,175.35368kW
ES22=20,175.35368kW (.006)
=121.0521221kW
Flash Vessels
ES6=20,175.35368kW -121.0521221kW
=20,054.30156kW
ES6=20,054.30156kW
ES21=20,054.30156kW (.006)
=120.3258093kW
Flash Vessels
ES7=20,054.30156kW - 120.3258093kW
=19933.97575kW
ES7 =19933.97575kW
ES19 = 19933.97575kW (.0025)
=49.83493938kW
Column ES8= 19933.97575kW – 49.83493938kW
=19,884.14081kW
ES18=19,884.14081kW
Ewr=19,884.14081kW (.0025)
= 49.71035203kW
Condenser Benzene=19,884.14081kW - 49.71035203kW
=19,834.43046kW
Efficiency = 85.78%
50
CHAPTER IV
This chapter presents all the required calculations and the data regarding
the financial aspects of the designed Hydrodealkylation Plant. In this chapter the
DESIGN OPTION 1
All capital and expenses for operation and construction of the designed
A. Capital Expenditures
Total Cost
PLANT EXPENSES Quantity Cost (Php)
(Php)
Admin 1 14,100,000.00
Control Room 1 18,600,000.00
Workshop and
Buildings 1 16,900,000.00
Powerhouse
Warehouse 1 13,700,000.00
Security Office 1 6,900,000.00
51
15,000
Land 5000/sqm 75,000,000.00
sqm
Vehicles 5 1,800,000.00 9,000,000.00
Toluene Feed
1 1,512,930.00 1,512,930.00
storage tanks
Mixers 6. 200,000 1,800,000
Pump 1 238,215.00 238,215.00
Compressor 1 200,000.00 200,000.00
Preheater 1 13,329,900.00 13,329,900.00
Furnace 1 29,049,250.00 29,049,250.00
Equipments Cooler 2 12,645,019 25,290,038
Heater 1 11,650,000.00 11,650,000.00
Flash Drum 2 500,000 1,000,000
Splitter 2 1,100,000.00 2,200,000.00
Distillation
2 41,736,000.00 83,472,000.00
Column
Benzene Storage
1 1,512,930 1,512,930
Tanks
Water
Treatment Reverse Osmosis 36,500,000.00
Facility
Storage
4 3,760,000.00 15,040,000.00
Facility
30% of Building
Installation Contractor Fee and Equipment 70,200,000.00
cost
Personal
Protective 12,000 5,000.00 60,000,000.00
Equipments
Health and
Safety Fire
150 3,000.00 450,000.00
Extinguishers
CCTV System 120 10,000.00 1,200,000.00
52
B. Operating Expenditures
Operating expenditure or OPEX will be the ongoing cost for running the
53
Admin. Staffs 15 264000 264000
Plant 288000 288000
12
Operators
Chemist 5 300000 300000
Laboratory 210000 210000
3
Staff
Plant 360000 360000
5
Mechanics
Plant 360000 360000
2
Electricians
Security 144000 144000
5
Guards
Doctor 1 300000 300000
general plant upkeep and
overhead, payroll overhead,
Plant packaging, medical services, 15% of total
Overhead safety and protection, capital 76,326,789.45
Cost restaurants, recreation, investment
salvage, laboratories, and
storage facilities
External tree planting, feeding program 400,000
D. Economic Indicators
54
Net present value (NPV) is the difference between the present value
of cash inflows and the present value of cash outflows to analyze the
profitability the project. Table 4.6 shows the NPV of the proposed power plant
= 3,339,546,684 - 3,285,344,105
=Php 54,202,578
55
2. Payback Period
point.
the proposed power plant after years of operation, and calculated as follows:
DESIGN OPTION 2
All capital and expenses for operation and construction of the designed
56
A. Capital Expenditures
57
0
1,100,000.0
Splitter 2 2,200,000.00
0
5,500,000.0
Mixer 2 11,000,000.00
0
Valve 3 275,000.00 825,000.00
Water
Treatment Reverse Osmosis 36,500,000.00
Facility
Storage 3,760,000.0
4 15,040,000.00
Facility 0
30% of
Building and
Installation Contractor Fee 36,195,492.90
Equipment
cost
Personal
Protective 12,000 5,000.00 60,000,000.00
Equipments
Health and
Safety Fire
150 3,000.00 450,000.00
Extinguishers
CCTV System 120 10,000.00 1,200,000.00
B. Operating Expenditures
Operating Expenditure or OPEX will be the ongoing cost for running the
processing plant. Table 15 represents the summary of the CAPEX of the HDA
Plant.
58
Electricity 4,000,000
Utilities Water 1,500,000
Fuel 1,000,000
Office
100,000
Supplies
Property
15% of total
Taxes,
capital 53,105,570.39
Permits and
investment
Licenses
10% of total
Maintenance capital 35,403,713.59
investment
General
1 60,000/month 720,000
Manager
Plant
Operation 2 50,000/month 1,200,000
Manager
Engineering
8 40,000/month 3,840,000
Supervisor
HSSE
1 35,000/month 420,000
Supervisor
Accounting
1 30,000/month 360,000
Manager
Admin. Staffs 15 22,000/month 3,960,000
Operating
Labor Plant
12 24,000/month 3,456,000
Operators
Chemist 5 25,000/month 1,500,000
Laboratory
3 17,500/month 630,000
Staff
Plant
5 30,000/month 1,800,000
Mechanics
Plant
2 30,000/month 720,000
Electricians
Security
5 12,000/month 720,000
Guards
Doctor 1 25,000/month 300,000
59
general plant upkeep and
overhead, payroll overhead,
Plant packaging, medical services, 15% of total
Overhead safety and protection, capital 53,105,570.39
Cost restaurants, recreation, investment
salvage, laboratories, and
storage facilities
External tree planting, feeding program 400,000
D. Economic Indicators
of cash inflows and the present value of cash outflows to analyze the
profitability the project. Table X.XX shows the NPV of the proposed
(1ton/1000kg)
60
Gross Income = AxBxC
= Php3,212,000,000 - Php3,168,240,854
1 43,759,146 -310,277,989.90
2 43,759,146 -266,518,843.90
3 43,759,146 -222,759,697.90
4 43,759,146 -179,000,551.90
5 43,759,146 -135,241,405.90
6 43,759,146 -91,482,259.90
7 43,759,146 -47,723,113.90
8 43,759,146 -3,963,967.90
9 43,759,146 39,759,178.10
10 43,759,146 83,554,324.10
1. Payback Period
61
Payback period refers to the length of time required to recover the
follows:
DESIGN OPTION 3
All capital and expenses for operation and construction of the designed
A. Capital Expenditures
62
Capital investment refers to the fund needed for the proposed procesing
63
5,500,000.0
Mixer 1 5,500,000.00
0
Water
Treatment Reverse Osmosis 36,500,000.00
Facility
Personal
Protective 10,000 5,000.00 50,000,000.00
Equipment
Fire
150 3,000.00 450,000.00
Extinguishers
Health and
Safety
CCTV System 1 250,000.00 250,000.00
B. Operating Expenditures
presented in table 20
Table 19. Estimation of Operating Expenditure
64
Property 49,922,890.77
15% of total
Taxes,
capital
Permits and
investment
Licenses
10% of total
Maintenance capital 33,281,927.18
investment
General
1 60,000 60,000
Manager
Plant
Operation 2 50,000 100,000
Manager
Engineering
8 40,000 320,000
Supervisor
HSSE
1 35,000 35,000
Supervisor
Accounting
1 30,000 30,000
Manager
Admin. Staffs 15 22,000 330,000
Operating
Labor Plant
12 24,000 288,000
Operators
Chemist 5 25,000 125,000
Laboratory
3 17,500 52,500
Staff
Plant
5 30,000 150,000
Mechanics
Plant
2 30,000 60,000
Electricians
Security
5 12,000 60,000
Guards
Doctor 1 25,000 25,000
general plant upkeep and
overhead, payroll overhead,
Plant packaging, medical services, 15% of total
Overhead safety and protection, capital 49,922,890.77
Cost restaurants, recreation, investment
salvage, laboratories, and
storage facilities
65
External tree planting, feeding program 400,000
3,572,859,099
Operating Expenditures
D. Economic Indicators
of cash inflows and the present value of cash outflows to analyze the
profitability the project. Table 4.6 shows the NPV of the proposed power plant
(1ton/1000kg)
66
Gross Income = Php3,615,108,426 (Assume to include taxes)
Payback Period
point.
67
Payback Period = Php332,819,271.80/ Php42,249,326.53
the proposed power plant after years of operation, and calculated as follows:
68
CHAPTER V
Processing Plant and the mitigation to lessen their effect to the safety and health
Positive benefits are being extended for the local community in terms of
the income for local economy and employment for residents during the
construction and operational phase of the designed power plant. Employment for
administration staff, medical staff and even catering services will be offered.
These personnel will be mostly hired from the residents of Limay, Bataan. Local
equipment to be used during the construction of the processing plant will also
result to economic boost to the resources coming from the community and will
produce a positive impact. The construction phase will also require numerous
skilled and semi-skilled employment. The management will also offer training
which is necessary for many new staff which will boost their skills and additional
techniques will be offered for the local market. When the operation phase started,
employment opportunities will also be offered especially for those skilled worker
in the community. The project will also provide revenue to local supporting
businesses within Bataan. During local activities such as fiestas and holidays, the
69
management will also offer assistance as well as participation can also be
expected. Since the management believe of what education can do, it will offer
scholarship for selected students from the local community. In conclusion, the
management would do its best to manage all the concerns and expectation of the
the management will always consider virtues such as patronage, charity and
Laws and regulation has always been a part of every decision making
according to laws and regulation. Compliance from the national and local
government laws will be highly perceived during the construction and operation
ethical principles and shared values in the society. Ethical principles will be
based on the values of the people living in Bataan. In making ethical decisions,
70
the management will perceive and eliminate unethical alternatives to prevent
ethical violations.
Safety is the top priority of our management. We value the health and
safety of our employees and staff more than anything else. The local public holds
a positive attitude about the project and believe it can improve the development
management to consider the health and safety of the local community as well.
Here is the main step the management will implement to ensure the health and
processing plant. Staffs assign per worksite and machine operations are
well trained and tasked to ensure that each equipment is taken care of so
indicated to ensure that they work according to its purpose in a safe and
tasked to obey the site’s safety and health rules and regulations.
B. Medical Services
The company provides a professional doctor to employ medical
care not just for the employees but for the near residences. Medicines for
71
both in-site and travelling purposes are also provided by the company. The
company also has its own medical equipment in case of urgent needs.
will have their own PPEs issued by the company to minimize exposure to
employee on how to use all equipment included in their PPEs. PPEs are
Table 22.
Summary of Recommended PPE According To Hazard
OBJECTIVE WORKPLACE HAZARD SUGGESTED PPE
72
Respiratory Dust, fogs, fumes, mists, Facemasks with appropriate filters
protection gases, smokes, vapors for dust removal and air purification
(chemicals, mists)
D. Security
Security personnel are located in every entry and exit point within
the plant to ensure that all person that enters and exits the plant are
to ensure that all personal materials of workers that enters and exits the
plant will not cause any trouble in both the operation and the safety of all
staff. Closed Circuit Television Cameras (CCTV) are installed all over the
area for high security purposes. Footage will always be checked every
now and then. These measures are implemented to make sure that all the
workers are secure and safe and can work without any worries in their
minds.
E. Workplace Inspection
The management conducts monitoring and inspection, both
73
sure that all employees have the knowledge of each escape route near
their location. Alarms are also installed all throughout every facility to
Waste Management
Waste are the by-product of each process within the plant that cannot be
reused and needs disposal. Waste management is the process in which waste
that can cause impact on the environment as well as the surrounding community
international legal framework. Proper disposal are studied and planned to make
sure that it will cause the least amount of effect on the environment and the
community around the processing plant. Water treatment facilities are also
implemented to ensure that the waste water generated from the plant will not
affect the groundwater and the water system where the waste will be disposed.
Here are the waste that the HDA processing plant will produced and the ways on
A. Unused Toluene
Toluene, also known as toluol, is an aromatic hydrocarbon. It is a
74
As the solvent in some types of paint thinner, contact cement and
1. Turn off any sources of ignition or any device that can spark. Toluene and
2. Put on safety glasses and safety gloves. Liquid toluene can chemically
burn the skin, causing redness, and toluene vapor can damage the eyes.
3. Clean up any toluene spills by covering them with sand, clay, dirt or an
hazardous waste.
B. Wastewater
75
Wastewater (or waste water) is any water that has been affected by
Wastewater Treatment
and the production of potable water. The result is that the solute is
retained on the pressurized side of the membrane and the pure solvent is
76
not allow large molecules or ions through the pores (holes), but should
Mitigation Measures
Mitigating measures are set of plans and activities to lessen the effect of
the processing plant on the environment as well as the local government. Here
are the list of the primary mitigating measures that the processing plant will
A. During Construction
1. The construction team will implement the covering of piles of cement
B. During Operation
1. Air quality will be monitored all throughout the process to ensure that
emissions are of the level allowable by the local and national law.
77
emission will exceed the standard and that welfare of the employees
social interaction and to monitor the safety of the local residents and
the environment. Problems that may arise will be dealt with immediate
action.
5. Waste disposal will be according to the local and national standards to
ensure that it will cause no harm with the nearby communities and the
Environmental Standards
This section provides the list of the main laws and regulation that the
Statement
78
B. Republic Act (RA) 6969: Philippine Toxic Substances and Hazardous
transit, of hazardous and nuclear wastes and their disposal into the
Management Act
This Act makes provision for the efficient solid waste management,
for the volume reduction of the waste, its environment friendly disposal,
79
proper segregation, collection, transport, storage, treatment and disposal
of solid waste
80
CHAPTER VI
considered. The table below presents the summary of the multiple realistic
Multiple
Realistic Design Option 1 Design Option 2 Design Option 3
Constraints
Percent
97.15% 80.3% 85.78%
Conversion
Net Present
Php33,180,517.0 Php83,554,324.10 Php89,673,993.50
Value
Level of
High Low Medium
Waste
Design Philosophies
Using scale from one to ten, each realistic constraints are scored and are
Design Option 1:
81
100%:10 = 97.15%:X; X = 9.72
Design Option 2:
Design Option 3:
Design Option 1:
Design Option 2:
Design Option 3:
Design Option 1:
Design Option 2:
82
No waste:10 = Low Waste: X; X = 9
Design Option 3:
Environmental 3 9 6
Based on the Worst Case Design philosophy, the designers find that
83
B. Pareto Optimum Design
Degree of Importance:
Technical = 4
Economical = 3
Environmental = 5
Environmental 3 9 6 5
= 65.76
= 104.96
= 94.2
84
Based on the Pareto Optimum Design philosophy, the designers find that
CHAPTER VII
plant in Limay, Bataan is presented in this chapter. This chapter discusses about
well as during operation phase of the processing plant. This includes the
discussion of the scope of the work, the goal of the execution plan, allocation of
The scope of the project execution plan involves the sequence of events
that will be involved in the construction phase, the resources and the
organization of the project including the personnel to make the HDA processing
85
plant possible. The planning phase as well as the preparations to be made
before the construction of the plant are also included in this section. The
engineers and experts involved in the construction phase will decide and
consider details and studies for the erection of the hydrodealkylation processing
plant such as the plant location, resource allocation, the current demand and the
forecast on the local and international market, technical details and construction
plan.
agreement and setting of a plan for the processing plant. Set of time frame will
assigned to each activity to make sure that each task were accomplished. These
commissioning of the project. Target goals and objectives for every activity will be
Organizational Considerations
project construction is required for the execution of the project. This would
overall operation. A general manager will be assigned for the task. The
department will serve as the framework of the project. The main function of this
86
The financial department will manage the costs, revenues, and other
financial aspects that is concerned with the construction and operation of the
project. The department will study the cost effectiveness while considering the
quality of the equipment and materials required for each phase of construction as
well as operation.
detailed engineering plans in the construction of the power plant. This includes
the structural details, piping layout, electrical layouts and instrumentation details
that will be installed. This department also weighs in the economical aspect of
the construction along with the technical expertise that the construction of the
Construction Management
location based on the three key requirements for the viability of plant which are
the fuel source, ease of access for transportation and source of water as well as
the consideration of the location of the supplier of raw material which is the
87
engineers and quality control specialists to ensure the legitimacy of the
checked by the engineers to ensure that it is optimal for the operation and could
This stage also pertains to the control towards the quality of the product
through the emissions that may be released and the waste generated from the
plant are also covered in this section. The procedures in controlling the quality is
to ensure that the generated toluene adheres to the quality criteria or meets the
temperature and pressure capacity which will take part in the continuous plant
when limitations are met. For the total capacity of the plant, each of the
Resources Allocation
main focus of this section. The management and allocation of the resources must
be optimal to ensure that every department will be able execute their work in the
best way. Resources will be allocated and scheduled economically and will be
88
monitored to prevent over-allocation and under-allocation. The project manager
Plant Layout
the figure below. This includes the key equipment which requires installation. The
order to save time and costs for transportation and is essential to operation. It is
between the components while taking into account the safety measures involved.
hydrodealkylation processing plant, the facilities shown include the parking area,
89
manufacturing area which houses the components necessary for
hydrodealkylation process.
be obtained from the government. This includes the management of the different
contracts and permits which may refer to building, lease, purchase and
changes to be performed.
their own respective functions. The overall system and components of the
observed, since it is the key to achieve the designed output. The size of the
design chosen is considered for the land occupancy on its erection. Safety
The plant performance can be calculated and evaluated and it is ideal to test
them to assure proper functioning and can start with the operations.
unceasing procedure as long as the plant is running and this should be complied.
To enable the processing plant, meet its plant life effectively and efficiently,
90
Through the phase of project development, proper schedule should be
otherwise it will have an adverse effect to the construction period of the plant that
The construction of the plant will be able to provide opportunities for the
locality that they may have development in the community. Building ties with the
understanding. Such negative effects that the plant may impart should be solved,
execution phase will need to plan, budget, oversee and document all aspect of
the erection of the processing plant. They may work closely with the upper
management to make sure that the scope and direction of the construction phase
set to be achieved with the given resources and time. A Gantt chart is presented
below which shows the planned construction execution, with the activities listed
91
Figure 22. Summary of Tasks in the Construction of the Proposed HDA
Processing Plant
Figure X shows the pacing of every task with the given time frames in which
it should be followed, when a certain task is slacking, the project manager will
have to shift from monitoring to controlling in order to achieve the task within the
allocated time due to the possibility of one task piling over the other and thus,
delaying the construction phase, and ultimately, the start of commission and
92
CHAPTER VIII
Summary of Findings
materials, toluene (5708 kg/hr) and hydrogen (301 kg/hr) is sufficient to produce
110 tons of benzene annually which will able the plant to meet the growing global
supply the local industries and manufacturers, specifically polymers, which have
Bataan, near other industrial plants. The land area for the proposed plant is 1.5
(CAPEX) estimate that the total project of the equipment cost specification for the
93
designed plant is approximately Php354,037,135.90 and the operating
Conclusions
Based from the analysis of information and data gathered, the proponents
1. The annual growth estimation rate of benzene material indicates its high
escalation in terms of demands and use. With the current demand trend of
evaluating the capability of the proposed plant, which has the capacity to
produce 4,583 kg/h of benzene material, to meet the growing demand of the
benzene material.
the best design was conducted based on the conversion, net present value,
94
4. The proposed hydrodealkylation production plant has an approximate
production plant. Recovery system for the waste produced, such toluene and
waste water, are installed for further use of the materials, thus decreasing the
cost requirements for materials. The recovered materials will then be stored
hazards that may be produced before, during and after the construction and
environment and to the staffs. Mitigations, preventions and protections are also
readily identified to prevent the people and environment from these hazards.
preparation is set for the smooth flow which are the conceptualization phase,
feasibility study phase, basis of design phase and basic design phase.
Different phases are also set for the quality control and assurance.
Recommendations
95
1. Installation of water treatment facilities for further processing of the
water collected in water reserve tanks. The treated water can be used for other
activities inside the plant and thus can also be reused in the process.
process and other factors affecting the process are required to develop cost-
the efficiency of the process and prolong the life of equipment. A regular
production of benzene.
6. Larger plant capacity is also suggested for the next advocates of this
production plant, since the demand trend of the benzene globally is very high.
7. Further research for more efficient waste treatment of the plant must
96