BOQ of Proposed Bungalow For Providing Approximate Cost
BOQ of Proposed Bungalow For Providing Approximate Cost
B / TO :- Mr.KARMENDRA BANSORE
S / OF :- Shree A>A BANSORE
A. in ordinary soil.
2. Earth work in foundation
for
Footing and
disposal of Excavated
earth, lead up to 50.0m
1.5m. Disposed earth to
be done.
a. In Black cotton
soil.
b. In ordinary soil 178.65 Sq. M 75.00 13398.75
21.42 Sq. M 115.00 2463.3
3. Earthwork: - Earth
work in excavation in
foundation trench of
drains (not exceeding
1.50m. In width or 10.0
sqm. In plan) Including
dressing of side and
Ramming of bottoms,
lift up to 1.50 m.
including getting out
The soil
a. In Black cotton
soil. 14.4 Sq. M 85.00 1224.00
C.C. grade M-
15,Crushed stone
aggregate 20mm
nominal size graded
excluding cost of
Centering shuttering and
reinforcement up to
plinth level, for
foundation footings,
bases of column / walls 47.60 Cq. 3850.00 183260.00
i/ c attached Pilasters, M
buttresses, plinth String
courses, landings shelves
and their Supports.
Balconies, lintels,
Chhajjas of any
thickness pillar Posts &
struts, staircase,
excluding Landings but
including repairing of
top surface of G. Floor
& First Floor.
10. R.C.C: - Reinforced
cement concrete work
with C.C. Grade M-20,
crushed stone aggregate
20mm nominal size
graded, excluding cost of
d. Providing and
fixing standard
M.S. Section
and square bars
,stair case
railing complete
in all respect.
24. Distempering: -
Distempering (two or
more Coats) with oil 833.40 Sq. M 35.00 29169.00
bound Washable
distemper of Required
shade on new work Over
and i/e a. priming coat.
25 Total Amount 2558657.55
26. Electrical work: - @2% 51200.00
Electrical work
27. Sanitary and Water @ 4 % 102400.00
Supply