You are on page 1of 2

L1 L2 L3 L4

Site Cleaning
Setting Out
Mobilization - -
Fencing
Site office Installation
Formwork
PCC
Concrete
Reinforcement
Formwork
Footings Concrete
Minor Repair works
Waterproofing
Reinforcement
Formwork
Concrete
Substructure Neck Columns (upto Plinth)
Finishing
Protective Coat
Filling with Solid blocks upto plinth
Formwork
Structural Plinths Concrete
Backfilling upto Slab on grade
Reinforcement
Formwork
Grade Slab
Concrete
Finishing Works
Reinforcement
Formwork
Column
Concrete
Minor Repair works
Super structure Reinforcement
Formwork
Slab & Beam
Concrete
Minor Repair works
Blockwork Masonry works
Installation of Outdoor/ Indoor
Unit -
Installation of A/C Ducts -
Mechanical
Installation of Air purifier
/mechanisms -
Installation of grills and diffusers -
Installation of conduits -
MEP Fixing of GI box -
Electrical
MEP
Electrical Pulling Electrical wires -
Fixing of Electrical points -
Fixing of MDB and DB -
Installation of Drainage pipes/
Water lines -
Plumbing
Fixing of Bath Accessories -
Connection to pumps -
Installation of sprinklers -
Fire Fighting
Installation of Smoke detectors -
Fixing Wall Angle
Support from ceiling
Ceiling Ceiling - gypsum
Fixing C channel
Fixing ceiling tiles
Surface Preparation
Plastering -
Application of Plaster
Surface Smoothening
Painting 1st coat
Painting -
Painting final Coat
Floor epoxy paint
Surface Smoothening
Finishes Tiling Fixing of tiles
Grouting
Floor tiles
Surface Smoothening
Skirting Fixing of tiles
Grouting
Aluminum fabrication as per site
measurements
Windows
Glass tempering
Windows & Doors, Fixing of windows
Carpentry joinery Fixing wooden frames
Fixing of architraves
Door
Fixing of Solid wooden door (along
with ironmongeries)