NEW TANAKGES AND ASSOCIATED CIVIL AND PILING WORKS: DETAIL ENGINEERING "S"

CURVE
50.00% 100.00%

45.00% 90.00%

40.00% 80.00%
% Progress / month

35.00% 70.00%

30.00% 60.00%

25.00% 50.00%

20.00% 40.00%

15.00% 30.00%

10.00% 20.00%

5.00% 10.00%

0.00% 0.00%
10-Jul- 10-Aug- 10-Sep- 10-Oct- 10- 10-Dec- 10-Jan- 10-Feb- 10- 10-Apr- 10- 10-Jun- 10-Jul- 10-Aug- 10-Sep- 10-Oct- 10- 10-Dec- 10-Jan- 10-Feb-
18 18 18 18 Nov-18 18 19 19 Mar-19 19 May-19 19 19 19 19 19 Nov-19 19 20 20
Mon. Sch 0.00% 0.00% 0.27% 25.55% 44.71% 8.96% 5.05% 5.74% 5.73% 3.75% 0.12% 0.12% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Mon. Act. 0.00% 1.48% 1.70% 9.92% 5.96% 6.48% 1.22% 2.76% 1.24% 2.56% 3.73% 4.13%
Cum. Sch 0.00% 0.00% 0.27% 25.82% 70.53% 79.48% 84.53% 90.27% 96.00% 99.75% 99.88% 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Cum. Act. 0.00% 1.48% 3.18% 13.10% 19.06% 25.54% 26.75% 29.51% 30.75% 33.31% 37.04% 41.16%