You are on page 1of 1

INGENIERÍA DE DETALLE ESTACIONES TRAMO C LÍNEA 7

METRO DE SANTIAGO
120.00%

99.89%
100.00% 100.00%

90.80%

80.00%
77.57%
68.08%
% Avance

60.00%
51.00% 60.60%
56.10%
43.93%

40.00% 33.94%

19.58%
20.00%
10.41% PROGRAMADO EARLY- % AVANCE ACUM.
5.17%
1.61% PROGRAMADO LATE - % AVANCE ACUM.

0.00%
Aug  2021 Sep  2021 Oct  2021 Nov  2021 Dec  2021 Jan  2022 Feb  2022 Mar  2022 Apr  2022 May  2022 Jun  2022 Jul  2022 Aug  2022 Sep  2022

MES Aug  2021 Sep  2021 Oct  2021 Nov  2021 Dec  2021 Jan  2022 Feb  2022 Mar  2022 Apr  2022 May  2022 Jun  2022 Jul  2022 Aug  2022 Sep  2022

PROGRAMADO EARLY- HH GANADAS MENSUAL 1,304.00 2,872.00 4,240.00 7,410.00 11,604.00 8,071.00 5712 4120 3639 6045 7663 10694 7348 87
PROGRAMADO EARLY - HH GANADAS ACUM. 1,304.00 4,176.00 8,416.00 15,826.00 27,430.00 35,501.00 41,213.00 45,333.00 48,972.00 55,017.00 62,680.00 73,374.00 80,722.00 80,809.00
PROGRAMADO EARLY - % AVANCE MENSUAL 1.61% 3.55% 5.25% 9.17% 14.36% 9.99% 7.07% 5.10% 4.50% 7.48% 9.48% 13.23% 9.09% 0.11%
PROGRAMADO EARLY- % AVANCE ACUM. 1.61% 5.17% 10.41% 19.58% 33.94% 43.93% 51.00% 56.10% 60.60% 68.08% 77.57% 90.80% 99.89% 100.00%
PROGRAMADO LATE - HH GANADAS MENSUAL 949.00 2,399.00 3,252.00 5,038.00 9,452.00 9,986.00 7078 5837 3729 5951 7133 10724 8434 847
PROGRAMADO LATE - HH GANADAS ACUM. 949.00 3,348.00 6,600.00 11,638.00 21,090.00 31,076.00 38,154.00 43,991.00 47,720.00 53,671.00 60,804.00 71,528.00 79,962.00 80,809.00
PROGRAMADO LATE - % AVANCE MENSUAL 1.17% 2.97% 4.02% 6.23% 11.70% 12.36% 8.76% 7.22% 4.61% 7.36% 8.83% 13.27% 10.44% 1.05%
PROGRAMADO LATE - % AVANCE ACUM. 1.17% 4.14% 8.17% 14.40% 26.10% 38.46% 47.22% 54.44% 59.05% 66.42% 75.24% 88.51% 98.95% 100.00%