CONTROL DE OBRA (Curva "S")

100% 99.97% 100.00%


95.98%
90%
84.42%
80%
% de Avances Acumulados

72.06%
70%
64.57%
60%
56.72%

50% 51.11%

43.64%
40% 39.50% 40.15% 39.14%
35.19%
31.88%
30% 28.76% 29.55%
28.06%
22.60%
20%

10%

0%
CORTE AL 06 DE
FEB 2020 MAR 2020 ABRIL 2020 MAY 2020 JUN 2020 JUL 2020 AGO 2020 SET 2020 OCT 2020 NOV 2020 DIC 2020 ENE 2021 FEB 2021
FEB 2020
PROGRAMADO 28.76% 29.55% 31.88% 35.19% 39.14% 43.64% 51.11% 56.72% 64.57% 72.06% 84.42% 95.98% 99.97% 100.00%
EJECUTADO 22.60% 28.06%
FINANCIERO 39.50% 40.15%