• 4.0 - Introduction
• 4.1 - Recognizing The Steps of Negotiation
• 4.2 - Recognizing Differences Between Pre- And Post-
Award Negotiations
• 4.2.1 - Recognizing Special Considerations For
Equitable Adjustments
• 4.2.2 - Recognizing Special Considerations For
Termination Settlements
• 4.3 - Identifying Documentation Requirements
The contractor side may lose more than just the profit
projected for the lost Government contract.
Win/Win
<--------------------------------------
---------------------->
Win/Lose
• Think win/win;
• Sell your position;
• Win results not arguments;
• Everything is negotiable; and
• Make it happen.
Exchange Interview
Date: _______________
Subject:
________________________________________________________________
Documents Reviewed:
_____________________________________________________
________________________________________________________________________
Action Items:
____________________________________________________________
________________________________________________________________________
__________________________ __________________________
Product Control
• Contract type;
• Warranties;
• Delivery schedule; or
• Other business terms and conditions
• Emphasize:
o The Government's commitment to a win/win approach
to contract negotiation
o That the Government's principal negotiator's role
is the principal speaker and "chairperson" of the
Government team. Other team members must realize
that the principal negotiator is the only
individual authorized to negotiate with the
contractor.
o That other team members are at the negotiation to
provide support, listen, and evaluate information
provided by the contractor. They must not address
the contractor's negotiator(s) unless directed by
the Government's principal negotiator.
o That, during negotiation sessions, other team
members must not openly disagree with the
Government position on any point under
discussion. If they have a concern, they should
discretely communicate with the principal
negotiator. If necessary, the principal
negotiator could call for a caucus to address the
concern.
• Assure that each team member understands his/her
specific role in the negotiation session.
o Identify any issue that the team member should be
prepared to address during negotiations.
o Assure that the team member understands the
related Government position.
o Review their anticipated role (e.g., present the
Government position, answer contractor questions
about that position, or both).
• For all negotiations, warn team members:
o Not to communicate with contractor personnel
outside the negotiation conference on issues
related to the negotiation.
o To safeguard information on the Government
position from contractor personnel and other
unauthorized persons.
o About ethical considerations (e.g., no free
lunches or favored treatment).
• For competitive negotiations, warn team members not to
engage in conduct that:
o Favors one contractor over another;
o Reveals a contractor's technical solution,
including unique technology, innovative and
unique uses of commercial items, or any
information that would compromise a contractor's
intellectual property to another contractor;
o Reveals a contractor's price without that
contractor's permission;
o Reveals the names of individuals providing
reference information about a contractor's past
performance; or
o Knowingly furnishes source selection information
to anyone other than Government personnel who
have a need to know.
• 4.0 - Introduction
• 4.1 - Recognizing The Steps of Negotiation
• 4.2 - Recognizing Differences Between Pre- And Post-
Award Negotiations
• 4.2.1 - Recognizing Special Considerations For
Equitable Adjustments
• 4.2.2 - Recognizing Special Considerations For
Termination Settlements
• 4.3 - Identifying Documentation Requirements
• Changes clause;
• Government Property clause;
• Suspension of Work clause;
• Government Delay of Work clause;
• Stop-Work Order clause; or
• Differing Site Conditions clause.
PNM Cost Element Summary. When you use cost analysis, your
cost element summary should address the offeror's
estimating rationale, the Government's objective, and the
amount considered negotiated. Commonly, this summary begins
with a tabular presentation similar to the following:
Cost Considered
Element Proposed Objective Negotiated Reference
Engineering $1,000,000 $900,000 $925,000 See Para
Direct A
Labor
Engineering $2,500,000 $2,025,000 $2,127,500 See Para
Overhead B
Subtotal $3,500,000 $2,925,000 $3,052,500
G&A $350,000 $292,500 $305,250 See Para
C
Total Cost $3,850,000 $3,217,500 $3,357,750
Using this type of tabular cost element summary,
you can identify the areas and degree of
differences and provide a general format more
detailed analysis.
• In Paragraph A, summarize:
o The rationale used by the offeror in
developing the proposal.
o Any technical or audit recommendations.
Focus on any differences between the
proposal and the recommendations.
o The reasons for any differences between
technical or audit recommendations and
the Government objective.
o The reasons for any differences between
the Government objective and the amount
considered negotiated. (Note: You and the
contractor will likely not agree on each
element of cost so the amount considered
negotiated is your analysis of a the cost
used to arrive at a reasonable price.)
• In Paragraphs B and C, address the same
subjects covered in Paragraph A with one major
addition. Since dollars are calculated using
overhead and G&A rates, you need to address
whether the dollar differences are the result
of differences in the application base, the
rates themselves, or both.
PNM Price When you use price analysis, your price summary
Summary should address each unit price, the Government's
objective, and the price negotiated. Commonly,
this summary begins with a tabular presentation
similar to the following:
Item Proposed Objective Negotiated Reference
0001 $15,000 $14,000 $14,250 See Para A
0002 $10,000 $9,750 $9,750 See Para B
0003 $4,500 $4,400 $4,500 See Para C
• If the same rationale applies to all items,
a single explanatory paragraph should be
enough.
• If different rationales apply to different
items, you may need to provide several
explanatory paragraphs.
5.0 Introduction
• Feel better;
• Perform better; and
• Be perceived better by others.
• Technical requirements;
• Data requirements;
• Contract start;
• Contract type;
• Contract financing;
• Delivery;
• Options; and
• Government furnished property.
8.0 Introduction
• Discussions:
o Are conducted with each contractor determined to
be within the competitive range.
o With each contractor are tailored to that
contractor's proposal.
o Consider significant weaknesses, deficiencies,
and other aspects of each contractor's proposal
that could be altered or explained to materially
enhance the proposal's potential for contract
award.
• At the conclusion of discussions, each contractor
still in the competitive range must be given an
opportunity to submit a final proposal revision by an
established cut-off date.
• The final source selection decision is then based on a
comparative proposal assessment against all source
selection criteria established in the solicitation.
• Proposal deficiencies;
• Significant proposal weaknesses; or
• Other proposal aspects that could, in the opinion of
the contracting officer, be altered of explained to
materially enhance the proposal's potential for
contract award.