INSPECTION & TEST RECORD

STAIRCASE INSTALLATION INSPECTION REPORT


Project No:
Inspection Date :
RFI No:
Drawing no:
Identification no:

Inspection findings
Item Description of check QC inspector
Satisfactory Unsatisfactory

The Staircase are installed at the right location

The Staircase are sitting properly on the foundation

The orientation of the stairs is correct

The floor level of the Structures are correct

The alignment of the Structures are correct

Bolting of Staircase is done properly

No damages for the Staircase in transportation

The handrails are aligned properly

Grouting of structures completed (If applicable)

Remarks

SPACEMAKER PARSONS EXPO 2020


Name

Signature

Date
PRO-F-44 REV.00