Professional Documents
Culture Documents
MBA-621
Operations Management
Case Study #2
Donner
Company
3/8/26
1
Amr A!!as
Problem Definition
The three-year old Donner Company has positioned itself well within
both the small volume,
volume, customize
customized
d (contract
(contract)) printed
printed circuit
circuit boards
market as well as the large volume, generic (captive) printed circuit
boards
boards market
market !arge
!arge electron
electronic
ic firms
firms ("T#T,
("T#T, $%&) produce
produced
d their
their
components in captive shops, while smaller sized companies, or when
large
large and small
small 'uantit
'uantities
ies of simple
simple techno
technolog
logy
y or fast
fast turn-ar
turn-aroun
ound
d
prototype boards were re'uired, these re'uests usually are fulfilled by
contract shops
2
• 2perational and strategic implications of company direction
• !abor utilization
• &aterials
• Capacity
• $nformation flow
• 3val
3valua
uati
ting
ng the
the fol
followin
owing
g per
perform
forman
ance
ce criter
teria1 4ual
uality,
ty,
5roductivity and Delivery
0oll
0ollow
owin
ing
g deta
detail
iled
ed anal
analys
ysis
is of data
data,, proc
proces
ess
s flow
flow and
and inve
invent
ntor
ory
y
strate
strategie
gies,
s, my recomm
recommend
endati
ations
ons will
will be focuse
focused
d on the follow
following
ing
opportunities1
6 Changing
Changing strategy
strategy from current
current position
position to one which
which concentrates
concentrates
on producing only small 'uantities of fast turn-around &2%Cs
7 Changing
Changing strategy
strategy from current
current position
position to one which
which concentrates
concentrates
on producing only large 'uantities of simple technology boards
8 Changing
Changing strategy
strategy from current
current position
position to one which
which concentrates
concentrates
on producing
producing large # small 'uantities
'uantities of simple
simple technolog
technology
y boards,
boards,
through the use of two separate production lines
3
boards to small and large electronic firms and management envisioned
it as one of the industry leaders /owever, in order to achieve this
ob<ective, perhaps Donner needed a management that is more
business oriented rather than being managed by engineers who don.t
necessarily possess the :business sense; to run a firm
4
Donner promised its customers 8 weeks delivery on orders of 6+++
boards or less, and * weeks on orders larger than 6+++ boards @ush
orders (orders of A boards or less) were delivered after = days
1$ Operating pro!lems%
5
interruptions to the production cycle at one operation, which in turn
causes a production bottleneck at the ne9t operation
2$ &rodu'ti(ity pro!lems%
6
"s a result of the operating problems, it is normal to predict, and
e9pect, productivity problems ith fre'uent down times and order
changes, management cited the fact that machines are idle for longer
than e9pected $n addition, standard labor time for each process (as
depicted in e"i!it )-A) did not reflect accurate time at Donner itself,
rather it was based upon industry standards and competitors. $n
addition, Donner.s operation is se'uential in nature, however
management is faced with a decision whether to use manual labor (for
drilling and punch press) or to use the CC machine for the same
purpose $t is evident that management did not prepare a breakeven
analysis to be able to ob<ectively determine which method to use with
which kind of order 0urthermore, the se'uential process flow currently
utilized at Donner can cause a significant idle time for workers "s my
analysis will show, a parallel flow of operations, at certain points, may
alleviate this problem and save time on production cycle time
3$ *uality pro!lems%
)$ Deli(ery pro!lems%
7
imilar to the current se'uential manufacturing policy at Donner, it is
no surprise to note the delivery problems %ecause all these processes
are interconnected, and especially because of the high rate of returns
and re-works, Donner failed to meet is delivery dates (A days late in
eptember) %ecause re-works re'uired pulling operators away from
their current functions, deadlines were not met (due to delays in
manufacturing and finishing work in progress)> Donner continued to
suffer from the inability to meet its delivery dates /owever, rush
orders were not affected and the company continued to promise =
days delivery for such orders (this also caused bottlenecks and shifting
bottlenecks as rush orders were treated with special status, raw
materials and workers were simmered to satisfy these orders)
0inally, the new sales manager for Donner, !loyd earby, noted his
concerns that Donner.s sales may not e9ceed F7& in sales (in 6BAA) if
it continued to :bleed; from its 'uality (returns and re-works) and
delivery problems /owever, both !loyd and the president believed
that Donner should continue bidding for low volume orders and
improve their 'uality standards, and believed this should stop the
:bleed; and possibly push Donner towards F8& in sales
Data Analysis:
8
• 5rofit and !oss
• $nventory
$16.00
$14.00
$12.00
$10.00
$6.00
$4.00
$2.00
$0.00
Jan - Jul 1987 Jul-87 Aug-87 Sep-87
Months
9
$t is clear that there was a sharp drop in profits from "ugust till
eptember (total of F66 million loss Hdrop in net profit) 0rom the
information provided by Donner, most of the manufacturing and
delivery problems occurred in eptember, 6BA
0urther analysis of the 5rofit and !oss sheet indicates that there was
76 working days in eptember, 6BA Donner employed 77 employees
who worked A hrs H day shift This amounted to a total of 8B hours
worked in that month Direct labor amounted to FA8 per employee
(F87,8++H8B hrs) Total fi9ed cost was F8=,6++ and variable cost was
FA,++ "dded in e"i!it . is a column to depict the different costs
per unit (based upon *6 units manufactured in eptember)
10
• tandard labor time for an order size of 6, A and 7++ boards
• Drill process1
• 5rofile process1
11
"i!it )-A can also be used to identify bottlenecks within Donner.s
standard process, particularly surrounding the capacity of the dry 0ilm
5hotoresist area $t is critical to realize the true capacity to prevent
bottlenecks and work-overload $f, for e9ample, the ma9imum number
of boards that the D05@ area can handle (due to the set up and run
time involved in the process) is 6++, then Donner should realize that
order size that passes through the drilling process should not e9ceed
6++ units (to match the D05@ capacity) $f the order sized is more than
6++ (hence, more than the ma9imum capacity that the D05@ area can
handle), a bottleneck is created and possibly shifted throughout the
entire manufacturing process $n addition, since the D05@ area
consists of several functions, it is important to be aware of the
ma9imum capacity (as per order size) to prevent bottlenecks within
the D05@ area 39ceeding ma9imum capacity will have a direct
negative impact on 'uality and on-time delivery (two problems that
Donner was already suffering from in eptember) 2f course, the
bottleneck will change from one area of the D05@ to the other,
depending on the order size and the time involved in each process
2rder
size
8 8 8
D05@ area
12
!aminate #
6== B+ 6==
39pose
To translate these numbers into facts, it is clear that in order to avoid
bottlenecks for an order size of A boards, the number of boards that
can be processed per day can not e9ceed 6== boards (by taking the
least number of boards for each of the three stages of D05@, as it
reflects the ma9imum daily capacity of orders processed) $f total
boards did not e9ceed 6==, this is, at least, a guarantee that Donner
should not e9perience bottlenecks at the D05@ area, as well as at other
areas of manufacturing, for an order size of A boards
$t is clear then that based upon the order size, the daily capacity for
the D05@ area changes The larger the order size, the more capacity
the area can handle, however that capacity should not e9ceed the
highlighted figures %ottlenecks can cause work to pile at another
stage of the process, which will impact the entire manufacturing
13
process as a whole, which is a ma<or factor in creating on-time delivery
and 'uality problems
$n addition, the larger the order size, the less e9pensive unit price is
This is a simple application of economies of scale, which should enable
Donner to continue to compete in this volatile market and maintain its
competitive edge for the long term
14
without generating revenue, that amounted to FB+8 every working
day, and F7+,68 a monthK
0urthermore, the standard labor time increases with the order size
5lease refer to e"i!its 84 5 and 1 standard pro'ess +lo area
for complete calculations of labor time for 6, A and 7++ orders
respectively1
2rder
size 6 board A boards 7++ boards
(e9hibit ) (e9hibit A) (e9hibit B)
!abor time
$t is clear that the labor time increases with the order size "s
previously noted, the breakeven point for the drilling process is
boards, and the breakeven point for the profile process is 7++ boards
@eviewing the table above, for an order size of 6 board, it is more cost
effective for Donner to utilize an entirely manual procedure, as it takes
about =+ hrs to finish an order and have it ready to be shipped "s
the order size increases (for e9ample, 7++ boards), it is clear that it is
past the breakeven point and therefore takes less time to be processed
utilizing CC drill and router rather than manual processing
15
$t is clear from the calculations that if the order size is 6 board, it is still
cost and time effective to utilize an entirely manual process (standard
labor time for an entire manual processing is 8B hrs), however once
the order size increases to A boards ( e"i!it 5 proposed strategy),
it is less time consuming for Donner to utilize CC drill L manual
punch press, rather than an entirely manual or automated process
(labor time for the proposed strategy ? CC drill L punch press - is
reduced to 6+7* hrs)
0or order size of e9actly 7++ boards, Donner should utilize CC drill
and may choose between punch press or CC router (as 7++ boards is
the breakeven point at which CC drill must be utilized for time and
cost effectiveness, and both punch press and CC router take the
same amount of time ? 7*+ minutes) !abor time is reduced to 8+
hrs with the proposed strategy (e"i!it 1 proposed strategy )
0or orders above 7++ units, it is more efficient for Donner to implement
a process than utilizes both CC drill and router to ensure less labor
time, less manufacturing lead time and better utilization of their
resources The following table illustrates the proposed strategy and
labor time.s savings for orders of A and 7++ boards1
16
2rder size
A boards
(e"i!it 5 ? 66* hrs 66A* hrs
1$2. rs 686 hrs
standard #
proposed)
7++ boards
(e"i!it 1 6*8*B hrs 8+ hrs
8+ hrs 6*8*B hrs
? standard #
proposed)
$f the order size is above 7++ (for e9ample, 7*+ boards), then the labor
time is 8** hours when CC is used for drilling and profiling (entirely
automated process), which is less than the time taken when manual
processes are utilized The breakeven points play a big role in these
situations This poses a suggestion that if Donner decided to focus on
large volume orders (over 7++ boards)> it may be beneficial to buy a
second CC machine, particularly if they followed a parallel
manufacturing process (detail e9planation of this process will follow in
the recommendation section)
"s mentioned earlier, when Donner received an order and the bid had
been accepted by the customer, it took about 7 days for purchasing to
locate the raw material at a low price $t also took about = days from
that moment until 0laherty (shop upervisor) received the order and
prepared the blueprints, scheduled work orders and allocated proper
resources "i!it 11 demonstrates the actual order sizes for the
month of eptember, 6BA 0urther analysis of the inventory strategy
17
followed by Donner is depicted in e"i!it 12, which is the stock of
each raw material ordered by Donner throughout eptember $t is
suggested that Donner should carry some inventory to minimize the
lead time from the moment the bid is accepted until it reaches
0laherty To determine which raw material Donner should carry
depends on the strategy followed $f Donner followed a strategy that
focuses on small orders only, it makes sense to carry over a
percentage of the commonly used raw material for such orders
(suggested 7+E, which follows the A+H7+ rule) To illustrate1 in
eptember, Donner received a total of + orders from customers,
where A+E of these orders were below 6++ boards 2nly 7+E of these
orders were for orders above 6++ boards $f Donner decided to focus
on small orders (ie orders of less than 6++ boards), then it would
make sense to carry about 7+E the following raw materials1 stock
codes ", %, C, D, 3, 0 and possibly M as well $f Donner decided to focus
on orders of 6++ boards and above, then the following stock codes
should be carried by the firm1 ", D and possibly & "s mentioned
earlier, stocking some of these raw materials should minimize
manufacturing lead time as the firm will not be at the mercy of locating
the entire amount once an order is received $n addition, 0laherty will
not have to wait for = days to begin planning for each pro<ect
$t is worth mentioning that despite the fact that A+E of orders received
from customers in eptember were for small volume boards, B+E of
the total number of circuit boards manufactured was for orders of 6++
boards or more This means that large volume orders represented the
largest portion of total number of boards made by Donner for
eptember This may play a role when Donner decides whether to
focus on large or small volume orders, and whether it can afford to lose
the customer base for each type of orders if they decided to drop one
18
$t is clear however that Donner needs to carry some inventory
(regardless of their strategy) "ssuming a monthly cost of 7E (cost of
carrying inventory), and assuming that Donner carried over some
inventory from "ugust (to show total impact on total cost and cost per
unit), we note the following1
19
7e'ommendations
7e'ommendation #1%
20
costs) $n short, the firm could continue to supply large and prestigious
firms such as $%&, "T#T or Digital 3'uipment in addition to the smaller
electronics firms> thus allowing Donner to target all manufacturers in
the electronics industry (for low-order volumes)
Third, senior management has cited the firm.s ability to anticipate and
resolve problems encountered during the design and production of
small volumes of &2%Cs as one of its strengths and distinguishing
features when compared to the competition Coupled with
management.s desire to continue fulfilling low-volume orders (where
they e9perienced no problems with re<ects or on-time delivery), the
firm should pursue a policy of serving this market segment with vigour
since it possesses both the e9perience and confidence to assure a high
degree of success
0inally, although only a three-year old firm, its profits have grown
consistently year-on-year, as shown in following graph1
21
Donner Company Net Proit !eore Ta"
$33,500
35000
30000
25000
20000
15000
Sales in USD $2,100 Year
10000
Sales
5000
0 1985 1987
1986
-5000
-$6,900
-10000
1 2 3
Year 1985 1986 1987
Sales -$6,900 $2,100 $33,500
Year
$t is interesting to note that they have already e9ceeded last year.s
earnings in the first nine months of this year (6BA) uch financial
facts are further evidence that the firm is clearly well positioned in the
industry of producing small 'uantities of fast turn-around &2%Cs,
while avoiding the possible problems that are associated with large-
volume orders (ie bottlenecks, sudden changes to the designs by
customers, which may result in long idle time)
22
• Materials
Currently, raw materials are being :simmered; by those who are
fulfilling e9pedited orders, namely by "rthur Dief uch a practice may
consistently lead to an order remaining as a ork in 5rogress ($5)
order, in the firm.s manufacturing stream for longer than necessary
$5 are further delayed as it awaits another shipment of raw materials
that were originally ac'uired for its use but now consumed by the
:rush; orders 0ulfilling only small-volume, 'uick turn-around orders
would re'uire the firm to either hold larger inventories of raw materials
or to ac'uire materials in a more timely fashion, but would decrease
the probability of this inefficient process from continuing to hamper the
entire manufacturing process
• ,a!or utili:ation%
The :simmering; of materials also has the added disadvantage of
increasing the amount of labor re'uired to produce a board hen a
$5 is interrupted by an e9pedited order, it may incur additional set-up
costs $n addition, workers then remain idle until the machine heHshe
was using is made available again (after the rush order has been
completed) Therefore, small 'uantity orders should alleviate such a
problem since all orders being filled by the firm will be of similar size
and have similar delivery dates, thus eliminating the :special status;
given to rush orders and reducing the idle time, which amplifies
workers. productivity
• Capa'ity%
The ability of the firm to increase its production capacity is being
hampered by the :shifting bottleneck;, which appears throughout
various stages of the manufacturing process without any particular
23
pattern This phenomenon mainly occurs due to the variation in the
order sizes and the unremitting interruption of current work flow (work
in progress) in favor of rush orders Thus, by adapting a small order
volume only policy, which will eliminate both the great difference in
order size and the concept of the :rush; order, the firm.s
manufacturing throughput will improve significantly
• 9n+ormation 0lo%
"s shown in e"i!it 2, David 0laherty, the shop supervisor, has the
greatest number of informational in and out flows " high proportion of
information, both inter-departmental and inter-firm, has to pass
through 0laherty "llowing him to operate effectively and efficiently
will have tremendous impact on Donner.s overall performance
0laherty had indicated that due to the sizeable variations in order
types, work in progress remain in the manufacturing stream for longer
than necessary %y making the order-types as uniform as possible,
0laherty should find it easier to plan resources and share information
0urthermore, carrying inventory of necessary raw materials should
alleviate the need for long lead time to plan for work
• Deli(eries
24
ince all these items are inter-linked, an improvement in one area will
lead to an improvement in all hould the firm decide to produce only
small 'uantities of fast turn-around &2%Cs, it will be able to fi9 the
flaws in all of these areas ince new employees typically take only
appro9imately 8 N months to become proficient in their assigned
areas and if the order size is small, managing the orders would be
easier taff could work either individually or in teams to ensure their
orders are of high 'uality and free of errors, from the moment the
order is received till the moment it is shipped to the customer The
productivity and morale of workers should also benefit from this as the
floor staff are given more responsibility for assuring their orders
efficiently move along the manufacturing process
25
#al$e o a%t$al shippments in Septem&er' 1987
140000
124836
120000
100000
80000 80276
D
S 71463 71639
70312
U 69188
n 63627 62337
i 60000
e
$ 53557
l
a
# 36389 44560
40000 36536 40341
28734 30610
26339
28050
20000 17909 17939
15683
13987 13216
11118 9930 10070
8430
4057 5926 3952 5561
16962226 2395 2560 2275
0 -1188 -684 -147 176 -1327
1 -7975
9 /
-20000
11- 12- 13- 14- 15- 18- 19- 20- 21- 22- 25- 26- 27- 28- 29-
1-Sep 4-Sep 5-Sep 6-Sep 7-Sep 8-Sep
Sep Sep Sep Sep Sep Sep Sep Sep Sep Sep Sep Sep Sep Sep Sep
Daily 11118 -1188 4057 1696 2226 8430 2395 -684 2560 5926 -147 3952 13216 10070 5561 2275 176 -1327 -7975 17939 44560
u!ula"i#e 11118 9930 13987 15683 17909 26339 28734 28050 30610 36536 36389 40341 53557 63627 69188 71463 71639 70312 62337 80276 124836
Dates
Daily Cumulative
"lso favourably affected will be the financial health of the firm since it
will be able to bill its customers sooner and will carry smaller inventory
of work in progress
7e'ommendation #2%
26
production runs (proto-types), the e9perience Donner has gained over
the last three years would facilitate the firm to concentrate on the
large 'uantities of imple Technology boards This will enable Donner
to utilize their current core competency and resources, and focus on
gaining new strengths, yielding improved 'uality and on time delivery
• ,a!or <tili:ation%
Donner.s current labor use will re'uire changes "s the chart below
shows, significant time is saved per board when using the CC Drill
and @outer (for orders over 7++ boards)> hence no re'uirements for
manual drill or punch press 3mployment could be reduced or workers
could be re-deployed to work in other areas in the firm (Donner.s
management cited the fact that workers are well cross-trained and
able to perform different functions throughout the manufacturing
process)
27
=
The increase in batch size will reduce the time per average board for
manufacture and subse'uently reduce labor time $n addition,
previous calculations of breakeven points depicted the very fact1 the
larger the order size, the less time the process flow looked using the
CC machine, as opposed to manual processes 5erhaps Donner
should purchase a second CC machine to accommodate this new
strategy (advantageous for large-volume orders)
• Capa'ity%
"s previously mentioned, capacity is dependent on the order size,
product mi9 and technology choices %y choosing to manufacture <ust
the large 'uantity simple technology boards, product mi9 is no longer
an issue, the technology is set and order size will always be high,
hence producing at a lower average time per board (and low cost by
utilizing economies of scale) The bottlenecks inherent in the current
process would be easier to identify and solve, without further
reoccurrences
• Materials%
The need to source raw material on a regular urgent basis should
decrease in number substantially $n effect, there should be more
control over the raw material stock levels as more time is available to
source and locate raw material ( as delivery time for large orders is
typically less restrictive) 0urthermore, raw material re'uired for large
orders should be freed from the continuous :simmering; by rush
orders This being said, a new strategic policy should be applied with
relation to the stocking levels of raw materials to satisfy large orders
(ie carry certain percentage of inventory as previously e9plained)
28
• 9n+ormation 0lo%
"nalyzing all processes within the company, by far the most fractured
and comple9 (and confusing) is the information flow ( e"i!it 2 ) The
ma<ority of the returned boards were a result of the firm missing or
failing to complete one or two re'uired design specification Currently,
until an order is shipped, 0laherty keeps the factory order and
blueprint at all times throughout the process This indicates that
possibly, vital information is not being disseminated throughout the
production line eptember 6BA.s pre-shipment re<ection rate
amounted to E, causing a large amount of rework This information
flow policy must change from being centered on 0laherty 0laherty.s
role should be redefined and restructured to improve the flow of
information and communication $n addition, the current process of
e9pediting rush orders through the manufacturing process is adversely
affecting the rest of the production process and increasing the
information over load 0ocusing on only large volume boards should
allow for enhancements within information flow
" new 4uality strategy should be adopted "rthur Dief (senior worker)
could be used in this role due to his knowledge of the entire
manufacturing process and the fact that he had a zero return rate
There are various 'uality control strategies that could be implemented
throughout the entire manufacturing process to detect (early) and
prevent product defects, and to monitor the entire manufacturing
process (ie si9 sigma, 5C or T4&) orkers should be trained to
29
utilize such methods and to utilize new technologies 5roductivity
should be increased due to the decrease in bottlenecks throughout the
manufacturing process @egarding the financial performance of
Donner, if the sales manager (earby) can generate the desired sales
and focus on the large 'uantity simple technology boards, there should
be a marked improvement in Donner.s financial health The on-time
delivery should be enhanced significantly due to the company.s new
strategic policy of concentrating on the large 'uantity boards, as well
as the reduction in product returns and re-works
7e'ommendation# 3%
30
Currently, Donner is already operating and manufacturing for both
segments of the market with considerable success and a solid
customer base /owever, in serving both the low # high volume
markets, it is becoming increasing evident that the production
processes and facilities are under significant stress $t is also clear that
the present production facilities have been designed primarily around
small order size production (since Donner originally started as a
producer for contract markets) "t the same time, Donner is trying to
adapt itself, workers and facility to cope with the diversification in
product lines (the penetration of :captive markets;) !loyd earby.s
sales forecast looks very promising for the company, yet this will only
be realized if the company can achieve faster delivery time, coupled
with fewer work in progress and re-works " large part of the problem
in meeting these faster delivery times and the increased number of re-
works and work in progress appears to be the effects that :rush
orders; have on the entire production process ork in progress ($5)
is usually delayed in order to e9pedite these rush orders in a delivery
time of four days ith the additional 6A++-s' feet of factory space
available in the near future, it may be the best time make a strategic
move to develop two separate production facilities, with two separate
product lines This e9tra production line should be designed to meet
small volume # rush orders The e9isting production line can then be
fully devoted for large volume production purposes and Donner should
purchase a second CC machine and run two separate production lines
to accommodate this new strategy (advantageous for large-volume
orders)
31
the contract and captive markets, thus increasing the overall customer
base
• ,a!or <tili:ation%
"t the present time, Donner.s workers are only working productively
for only 8 hours of their working day and idle (unproductive) for *
hours (8B total hours in eptember, however only 6*86 hours are
actually worked for the month of eptember) This issue stems from
three main problems1
32
"lso, it is clear that the current manufacturing process results in
having too many responsibilities lie on the shoulders of very few
people (namely1 0laherty) ith two production lines in operation
simultaneously, David 0laherty could be made responsible for the large
volume production line, with "rthur Dief (as a senior and e9perienced
worker) managing the smaller production line "rthur Dief is, clearly,
valuable to Donner "lso, new workers could receive their training
from "rthur This strategy will allow Donner to better utilize all
available resources and focus on improving productivity, 'uality,
information flow, delivery and, in essence, the bottom line
33
commences During such time it is also evident that there is a total of
** minutes of idle time that occurs at the CC drilling station The
worker who is responsible for the CC drilling is, literally, idle and
waiting for the artwork generation, then for the inspect and sheer
process, then for the punch tooling hole processes to be completed
then he or she would begin the CC set up (which takes 7=+ minutes)
Inspect and
%heer –
325
minutes
34
cycle time (87= min vs 7B min proposed under the parallel process
flow) @educed cycle time will translate into better efficiency and
productivity, which will add to Donner.s bottom line and improve the
on-time delivery process
The parallel process flow can be utilized at any stage of the production
cycle, regardless of the order size $t is another method to improve
productivity $n addition, eliminating any non-value-added processes
from the manufacturing process will improve productivity (ie un-
necessary time spent to transfer completed boards to the tanks ? back
and forth ? and other low hanging fruits that hamper the overall
productivity)
• Capa'ity%
The capacity of Donner.s current production facility is not being fully
realized, as it is not fully optimized for low or high volume circuit board
manufacturing %y utilizing two production lines, each can be
optimized for their respective production purposes, and potential
bottlenecks will be easier to identify and resolve This strategic move
should allow Donner to achieve the potential sales volume of F8 million
by 6BAA as, predicted by the sales manager
• Materials%
Donner.s current delivery problems stem from several reasons,
including re-works, rush orders and the effect they have on $5s, and
also the inade'uate inventory policy e9isting within the company
David 0laherty had acknowledged that he often delayed his scheduling
for several days until the raw materials arrived from the vendor "s
previously analyzed, it is understandable that it would not be possible
to stock all raw materials, but a certain core raw materials should be
35
stocked to avoid valuable days being lost in the present order
processing system, as well as to avoid vendors. volatilities The costs
incurred by carrying inventory should be realized with sales figures
increase, improved 'uality and on-time delivery
• 9n+ormation 0lo%
The current information flow within Donner can be described as
incredibly inade'uateK "dopting this strategy will succeed only if
information flows faster and becomes more readily available Gust as
there are bottlenecks in the production process, there are also
bottlenecks in the current information system 2rders are taking up to
four days to reach 0laherty, after the bid has been accepted This
e9cessive time period is adding to the e9isting delivery problem "s
previously described, Donner will hold certain levels of inventory of
specific raw materials> which will lead to a shorter lead-time of
manufacturing and information to 0laherty, as well as to his workers
The amount of inventory carried can be determined by the A+H7+ rule,
which means that Donner could hold 7+E inventory of core raw
materials based upon A+E of their individual order sizes in eptember
(Donner could determine a monthly baseline or, should they elect to,
'uarterly baseline to determine appropriate level of inventory) "lso,
by improving information flow and simplifying the process, Donner
could become a market leader in the delivery time of its products, as
well as in 'uality and fewer product return rates
36