Electrical update

1. Electrical take off for wiring accessories, light fittings, fire alarm system, cables, isolators,
earthing and lightning protection completed
2. Routing the containment for power, lighting, fire alarm system, ELV system and CBS system is
under progress
3. RFQ for electrical already sent to the suppliers and got some quotation such as light fittings,
earthing and lightning protection for aircraft
4. Tender clarification for electrical already sent awaiting the response from the client
5. SCADA System for mechanical and electrical equipment has sent to subcontractor but still
looking for some other suppliers
6. 400 Hz Cable Reel are used to supply to aircraft (on board power, radar station and
communication system I don’t have supplier for this item
7. Lighting Inverter no specification and detail I couldn’t be able to send enquiry
8. External Telecommunication I’m not sure if fibre optic cables and connection of main telecom
line to telecom room is part of our scope
9. I am not sure if Load bank need to be supply by contractor or for the purpose of load testing
only by third party
10. Containment and secondary containment for Lighting, Power, FA, CBS and ELV System
11. Supply and Install 3 Nos. Prime Rated Generator 1,360KVA and 1 No of Emergency Diesel
Generator
12. Seismic Protection for Electrical and Mechanical Equipment need to include
13. Emergency Lighting and Access Control system no layout given need to be clarify system
required on the building
14. Electrical BOQ 80 Percent complete external work and containments are pending