Professional Documents
Culture Documents
Scheduling Terminology
Work Breakdown Structure (WBS)
•A deliverable oriented hierarchical decomposition of the work to be executed
by the project team to accomplish the team mission and create the required
deliverables. The WBS defines the project scope.
Team Mission
2
Scheduling Terminology
Deliverable
•Any unique and verifiable product or result that must be produced to
complete a project. Usually the lowest level of the WBS.
Team Mission
3
Scheduling Terminology
Scheduled Activity (task)
•A component of work performed to create a deliverable.
Team Mission
(Scope)
WBS
Activity List
4
Scheduling Terminology
Duration
•Total number of work periods required to complete a scheduled activity.
Usually expressed as workdays. (contrast with “effort”)
•Effort
•Total number of labor units requird to complete a scheduled activity.
Usually expressed as staff hours or a rate. (contrast with “duration”)
•Schedule Milestone
•A significant event in the project schedule, such as an event restraining
future work or marking the completion of a major deliverable. A “measuring
point”. Milestones have “0” (zero) duration and no resource assignments.
5
Basic Bar Chart
(Gantt Chart)
6
Defining Activities/Tasks
•Definition
•Assignment
•Significance
Finish Start
• SS – Start Start
Start Start
• FF – Finish Finish
Finish Finish
9
Leads and Lags
1 7
3
8
6
A D
F
B
E
C G
12
Critical Path
•Sequence of scheduled activities that determines the project
duration
•Longest duration path through the project network
•Activities on the Critical Path are called “Critical Activities”
•Critical activities have no float or slack
•A project can have more than one critical path
•Activities not on the Critical Path are called “Non Critical
Activities
•To shorten the project duration, a scheduler must modify the
critical path activities or dependencies
13
Float (or Slack)
•Total Float – the total amount of time that a scheduled
activity (or milestone) may be delayed or extended without
delaying the project end date or violating a schedule
constraint.
14
Critical Path Method
Activity Node 16
Simple Project consisting of 5 Tasks
WBS Code Activity WBS Code Activity
Activity A Activity B
Early Start (ES) Duration Late Start (LS) Early Start (ES) Duration Late Start (LS)
Early Finish (EF) 7 Late Finish (LF) Early Finish (EF) 5 Late Finish (LF)
Activity D
Early Start (ES) Duration Late Start (LS)
Activity E
Early Start (ES) Duration Late Start (LS)
17
TWO THINGS WBS Code Activity
Activity A
NEEDED TO SET
Early Start (ES) Duration Late Start (LS)
1
Early Finish (EF) 7 Late Finish (LF)
Activity E
Early Start (ES) Duration Late Start (LS)
18
6
Activity A Activity B
Early Start (ES) Duration Late Start (LS) Early Start (ES) Duration Late Start (LS)
1
Early Finish (EF) 7 Late Finish (LF) Early Finish (EF) 5 Late Finish (LF)
Activity D
Early Start (ES) Duration Late Start (LS)
Activity E
Early Start (ES) Duration Late Start (LS)
20
Early Finish = Early Start + Duration
WBS Code Activity WBS Code Activity
Activity A Activity B
Early Start (ES) Duration Late Start (LS) Early Start (ES) Duration Late Start (LS)
1
Early Finish (EF) 7 Late Finish (LF) Early Finish (EF) 5 Late Finish (LF)
8
Total Float (TF) = Total Float (TF) = WBS Code Activity
Activity D
Early Start (ES) Duration Late Start (LS)
Activity E
Early Start (ES) Duration Late Start (LS)
21
Early Start With Single Predecessor
WBS Code Activity WBS Code Activity
Activity A Activity B
Early Start (ES) Duration Late Start (LS) Early Start (ES) Duration Late Start (LS)
1 8
Early Finish (EF) 7 Late Finish (LF) Early Finish (EF) 5 Late Finish (LF)
8
Total Float (TF) =
13
Total Float (TF) = WBS Code Activity
Activity D
Early Start (ES) Duration Late Start (LS)
8
Early Finish (EF) 2 Late Finish (LF)
10
Total Float (TF) =
Activity E
Early Start (ES) Duration Late Start (LS)
22
Early Start With Multiple Predecessors
WBS Code Activity WBS Code Activity
Activity A Activity B
Early Start (ES) Duration Late Start (LS) Early Start (ES) Duration Late Start (LS)
1 8
Early Finish (EF) 7 Late Finish (LF) Early Finish (EF) 5 Late Finish (LF)
8
Total Float (TF) =
13
Total Float (TF) = WBS Code Activity
Activity D
Early Start (ES) Duration Late Start (LS)
13
Early Finish (EF) 3 Late Finish (LF)
8
Early Finish (EF) 2 Late Finish (LF)
10
Total Float (TF) =
Activity E
Early Start (ES) Duration Late Start (LS)
23
Start-to-Start Relationships (A to E)
WBS Code Activity WBS Code Activity
Activity A Activity B
Early Start (ES) Duration Late Start (LS) Early Start (ES) Duration Late Start (LS)
1 8
Early Finish (EF) 7 Late Finish (LF) Early Finish (EF) 5 Late Finish (LF)
8
Total Float (TF) =
13
Total Float (TF) = WBS Code Activity
Activity D
Early Start (ES) Duration Late Start (LS)
13
Early Finish (EF) 3 Late Finish (LF)
8
Early Finish (EF) 2 Late Finish (LF)
10
Total Float (TF) =
Activity E
Early Start (ES) Duration Late Start (LS)
1
Early Finish (EF) 3 Late Finish (LF)
4
Total Float (TF) =
24
Completed FORWARD Pass
WBS Code Activity WBS Code Activity
Activity A Activity B
Early Start (ES) Duration Late Start (LS) Early Start (ES) Duration Late Start (LS)
1 8
Early Finish (EF) 7 Late Finish (LF) Early Finish (EF) 5 Late Finish (LF)
8
Total Float (TF) =
13
Total Float (TF) = WBS Code Activity
Activity D
Early Start (ES) Duration Late Start (LS)
13
Early Finish (EF) 3 Late Finish (LF)
8
Early Finish (EF) 2 Late Finish (LF)
10
Total Float (TF) =
Activity E
Early Start (ES) Duration Late Start (LS)
1
Early Finish (EF) 3 Late Finish (LF)
4
Total Float (TF) =
25
Critical Path Method
Activity A Activity B
Early Start (ES) Duration Late Start (LS) Early Start (ES) Duration Late Start (LS)
1 8
Early Finish (EF) 7 Late Finish (LF) Early Finish (EF) 5 Late Finish (LF)
8
Total Float (TF) =
13
Total Float (TF) = WBS Code Activity
Activity D
Early Start (ES) Duration Late Start (LS)
13
Early Finish (EF) 3 Late Finish (LF)
8
Early Finish (EF) 2 Late Finish (LF)
The last activity
10
Total Float (TF) = Early Finish
(EF) will default
to be the Late
WBS Code Activity
Finish (LF).
Activity E
Early Start (ES) Duration Late Start (LS)
1
Early Finish (EF) 3 Late Finish (LF)
4
Total Float (TF) =
27
Late Start (LS) = Late Finish (LF) - Duration
WBS Code Activity WBS Code Activity
Activity A Activity B
Early Start (ES) Duration Late Start (LS) Early Start (ES) Duration Late Start (LS)
1 8
Early Finish (EF) 7 Late Finish (LF) Early Finish (EF) 5 Late Finish (LF)
8
Total Float (TF) =
13
Total Float (TF) = WBS Code Activity
Activity D
Early Start (ES) Duration Late Start (LS)
13 13
Early Finish (EF) 3 Late Finish (LF)
8
Early Finish (EF) 2 Late Finish (LF)
10
Total Float (TF) =
Activity E
Early Start (ES) Duration Late Start (LS)
1
Early Finish (EF) 3 Late Finish (LF)
4
Total Float (TF) =
28
Late Starts with Single Successors
WBS Code Activity WBS Code Activity
Activity A Activity B
Early Start (ES) Duration Late Start (LS) Early Start (ES) Duration Late Start (LS)
1 8 8
Early Finish (EF) 7 Late Finish (LF) Early Finish (EF) 5 Late Finish (LF)
8
Total Float (TF) =
13
Total Float (TF) =
13 WBS Code Activity
Activity D
Early Start (ES) Duration Late Start (LS)
13 13
Early Finish (EF) 3 Late Finish (LF)
8 11
Early Finish (EF) 2 Late Finish (LF)
10
Total Float (TF) =
13
Activity E
Early Start (ES) Duration Late Start (LS)
1
Early Finish (EF) 3 Late Finish (LF)
4
Total Float (TF) =
29
Late Start with Multiple Successors
WBS Code Activity WBS Code Activity
Activity A Activity B
Early Start (ES) Duration Late Start (LS) Early Start (ES) Duration Late Start (LS)
1 1 8 8
Early Finish (EF) 7 Late Finish (LF) Early Finish (EF) 5 Late Finish (LF)
8
Total Float (TF) =
8 13
Total Float (TF) =
13 WBS Code Activity
Activity D
Early Start (ES) Duration Late Start (LS)
13 13
Early Finish (EF) 3 Late Finish (LF)
8 11
Early Finish (EF) 2 Late Finish (LF)
10
Total Float (TF) =
13
Activity E
Early Start (ES) Duration Late Start (LS)
1
Early Finish (EF) 3 Late Finish (LF)
4
Total Float (TF) =
30
Finish-to-Finish Relationships (D to E)
WBS Code Activity WBS Code Activity
Activity A Activity B
Early Start (ES) Duration Late Start (LS) Early Start (ES) Duration Late Start (LS)
1 1 8 8
Early Finish (EF) 7 Late Finish (LF) Early Finish (EF) 5 Late Finish (LF)
8
Total Float (TF) =
8 13
Total Float (TF) =
13 WBS Code Activity
Activity D
Early Start (ES) Duration Late Start (LS)
13 13
Early Finish (EF) 3 Late Finish (LF)
8 11
Early Finish (EF) 2 Late Finish (LF)
10
Total Float (TF) =
13
Activity E
Early Start (ES) Duration Late Start (LS)
1 13
Early Finish (EF) 3 Late Finish (LF)
4
Total Float (TF) =
16
31
Completed BACKWARD Pass
WBS Code Activity WBS Code Activity
Activity A Activity B
Early Start (ES) Duration Late Start (LS) Early Start (ES) Duration Late Start (LS)
1 1 8 8
Early Finish (EF) 7 Late Finish (LF) Early Finish (EF) 5 Late Finish (LF)
8
Total Float (TF) =
8 13
Total Float (TF) =
13 WBS Code Activity
Activity D
Early Start (ES) Duration Late Start (LS)
13 13
Early Finish (EF) 3 Late Finish (LF)
8 11
Early Finish (EF) 2 Late Finish (LF)
10
Total Float (TF) =
13
Activity E
Early Start (ES) Duration Late Start (LS)
1 13
Early Finish (EF) 3 Late Finish (LF)
4
Total Float (TF) =
16
32
6
Activity A Activity B
Early Start (ES) Duration Late Start (LS) Early Start (ES) Duration Late Start (LS)
1 1 8 8
Early Finish (EF) 7 Late Finish (LF) Early Finish (EF) 5 Late Finish (LF)
8 8 13 13
Total Float (TF) =
0 Total Float (TF) =
0 WBS Code Activity
Activity D
Early Start (ES) Duration Late Start (LS)
13 13
Early Finish (EF) 3 Late Finish (LF)
8 11
Early Finish (EF) 2 Late Finish (LF)
10 13
Total Float (TF) =
3
Activity E
Early Start (ES) Duration Late Start (LS)
1 13
Early Finish (EF) 3 Late Finish (LF)
4 16
Total Float (TF) = 12
34
6
Activity A Activity B
Early Start (ES) Duration Late Start (LS) Early Start (ES) Duration Late Start (LS)
1 1 8 8
Early Finish (EF) 7 Late Finish (LF) Early Finish (EF) 5 Late Finish (LF)
8 8 13 13
Total Float (TF) =
0 Total Float (TF) =
0 WBS Code Activity
Activity D
Early Start (ES) Duration Late Start (LS)
13 13
Early Finish (EF) 3 Late Finish (LF)
8 11
Early Finish (EF) 2 Late Finish (LF)
10 13
Total Float (TF) =
3
Activity E
Early Start (ES) Duration Late Start (LS)
1 13
Early Finish (EF) 3 Late Finish (LF)
4 16
Total Float (TF) = 12
36
Task A Task C Task F
2 days 1 days 5 days
Start
Task B Task D Fin
3 days 2 days
Task G
2 days
Task E
4 days
8 days
St – A – C – F – Fin: ________
7 days
St – B – D – G – Fin: ________
St – B – E – G – Fin: ________
9 days
37
Task A Task D Task H
4 days 5 days 7 days
Task B Task E
6 days 10 days
Task J
Start 2 days
Task F Fin
5 days
Task C
8 days
Task G
8 days
St – A – D – H – Fin: ________
16 days
St – B – E – J – Fin: ________
18 days
15 days
St – C – F – J – Fin: ________
38
16 days
St – C – G – Fin: ________
Activity Duration Preceding Activity
Start (Milestone) 0 --
Task A 4 days Start
Task B 3 days Start
Task C 5 days Task A
Task D 7 days Task B
Task E 3 days Task B
Task F 10 days Task C & Task D
Task G 4 days Task D & Task E
Task H 2 days Task E
Task I 2 days Task F & Task G
Task J 4 days Task H
Finish (Milestone) 0 Task I & Task J
39
Task C
Task A 5 days
4 days Task F
10 days
Start Task I
Task D 2 days
Task B 7 days
3 days Task G
4 days Fin
Task E
3 days
Task H Task J
2 days 4 days
21 days
St – A – C – F – I – Fin: ________
22 days
St – B – D – F – I – Fin: ________
St – B – D – G – I – Fin: 16 days
________
12 days
St – B – E – G – I – Fin: ________
40
St – B – E – H – J – Fin: 12 days
________