TARGET ACHIEVEMENT TARGET ACHIEVEMENT TARGET ACHIEVEMENT

FABRICATION HWI FABRICATION NHWI DRAWING CODE A


TARGET LIST MONTH % COMPLETE REMARK TARGET LIST MONTH % COMPLETE REMARK TARGET LIST SUBMIT DUE DATE MONTH COMPLETION % COMPLETE REMARK

Storage Tank March 95% Storage Tank March 30% Storage Tank 3-Mar March 90%

Waste Tank March 95% Primary Combustion Chamber May 0% Waste Tank 3-Mar March 90%

Primary Combustion Chamber May 90% Secondary Combustion Chamber April 0% Primary Combustion Chamber 8-Mar April 75%

Secondary Combustion Chamber April 90% Water Quencher April 50% Secondary Combustion Chamber 3-Mar March 75%

Water Quencher April 35% Dry sqrubber April 50% Water Quencher 3-Mar April 85%

Dry sqrubber April 26% Exhaust Stack April 25% Dry sqrubber 3-Mar April 85%

Exhaust Stack April 90% All Platform March 0% Exhaust Stack 3-Mar April 80%

Neutralizing Tank March 75% Piping April 0% Neutralizing Tank 12-Mar March 75%

All Platform April 0% All Platform 15-Mar April 40%

Piping April 0% Piping 28-Mar April 30%

100%

100%

5%

Piping April 80%