You are on page 1of 3

Foundation repair

Part I
BY ROBERT WADE BROWN,
MARTIN PRAGER
AND JOE JANSEN.

he success of any concrete

T foundation repair job de-


pends upon the ability of
the contractor who does the
job. If properly executed, founda-
tion repair can almost always be
considered permanent.
These conclusions are drawn
from data collected during a 41⁄2-year
period from some 380 residential
foundation repair jobs in the Dallas,
Texas, area. The data indicates that
proper foundation repair tech-
niques will always be successful
provided the contractor under-
stands the chemical and physical
behavior of the local soil con-
stituents and exhibits reasonable
perseverance.
The Dallas test program involved
two types of foundations: pier and
beam; and slab on grade.

Slab leveling
All slab foundations were leveled
by controlled pressure injection of
either a soil-lime-cement or a soil- Pumping equipment required for slab foundation leveling.
cement grout beneath the slab. The
foundation was thereby literally
“floated” to proper grade. A side To avoid foundation repair—or dency for outside brick to crack and
benefit of this technique is soil sta- perhaps because of a simple lack of pull out from the wall. Restoring the
bilization. In critical areas the lime understanding—many homeown- beam to grade will normally correct
and/or cement content of the grout ers will fill in initial cracks that ap- this problem. If the foundation
can be increased and the methods pear as a relief of stress caused by movement has been severe or al-
altered to provide deeper soil pene- foundation movement. Then when lowed to persist for a long period,
tration and treatment. the foundation is restored to grade, brick mortar or other foreign mat-
Repair to pier-and-beam founda- the free space required to absorb ter lodging between the brick ve-
tions was achieved by mechanically the re-leveling movement is absent neer and sheathing sometimes pre-
raising the exterior beam to proper and new cracks may appear (imme- vent the normal return of the wall.
grade and holding it there by instal- diately or in subsequent weeks). The results may then be a level
lation of specially designed spread Howe ve r, rarely do they re p re s e n t foundation with an unsightly finish.
footings. Interior floor areas were any significant structural problem. Even with the best possible repair
leveled by shimming on existing in- When a foundation beam settles, and technology, a certain responsi-
terior concrete piers. the induced stresses create a ten- bility for maintenance remains with
the property owner for which he
TABLE I
should be aware. There must be
STATISTICAL ANALYSIS OF FOUNDATION REPAIR
provision for adequate displace-
ment of surface water and location
of down spouts. (Any drainage Type Number Number
problem that causes water to collect Foundation Jobs Re-dos Explaineda Unexplainedb
or stand against the foundation
should be corrected.) Location of Slab 285 15(5.3%) 11(3.9%) 4(1.4%)
aesthetic vegetation should be con- Pier & Beam 95 3(3.2%) 3(3.2%) 0(0.0%)
trolled.
The property owner should also Totals 380 18(4.7%) 14(3.7%) 4(1.4%)
consider the problem that tree and
plant roots can cause, either by ex-
a. All three pier-and-beam and six slab foundations were cases of partial repair.
erting pressure against the founda- Five additional slabs were logically explained.
tion or by absorbing water from the
bearing soil, creating a drying action b. The causes of these four slab re-dos could not be definitely established; how-
that causes settlement. ever, after re-do the foundations have remained stable.

Remedial action
In any event, once movement has ciently prepared. Later a water leak permits a near-exact estimate of the
occurred, remedial action is neces- develops and forces a saturation or shrinkage of a known configuration
sary: the particular technique de- washout of the bearing soil. Either of grout. Under a normal raise, any
pends upon individual circum- instance can produce a new appear- error in estimating the shrinkage is
stances. ance of the foundation problem. insignificant—a direct percentage
Portions of a foundation often Saturation, which can produce of the vertical grout thickness. How-
move while other areas remain al- bearing soil upheaval, usually devel- e ve r, such preciseness is not nor-
most stationary, thus creating the ops from sewer leaks or slow pres- mally possible in situations that re-
tendency for partial repair. Howev- sure leaks. Associated failures can quire extreme raises. On raises of 4
er, the result can be a stabilized sec- usually be precluded if the bearing inches or more, at some points the
tion with unrepaired areas that are soil is properly stabilized during vertical grout thickness might (and
free to move. This magnifies any foundation repair. The option for probably does) approach 12 inches.
movement which later occurs in the soil stabilization generally lies with Raises of this magnitude are fairly
u n re p a i red section. Future move- the property owner. Often, simply to common and represent a possible
ment, consequently, can produce save a few dollars, an owner will re-do.
stresses that are tra n s p o rt e d forego the security of soil stabiliza-
tion, especially if foundation fail- Partial repairs
through the structure to the newly
repaired section. This tends to give ures are not particularly common in Partial repairs are another princi-
the erroneous impression that pre- his area. pal factor contributing to re-dos.
vious repairs have failed when, in The occurrence of washout is im- The Dallas statistics emphasize this
fact, the unrepaired section is at possible to anticipate and difficult, factor beyond its proper proportion
fault. or at least impractical, to guard because of the imposed procedure
against. Fortunately, the frequency for compiling data and because the
Re-dos of washout is limited. In the 380 cas- job statistics fail to reflect the high
As the data in Table I reflect, re- es studied in Dallas, the re c u r re n t percentage of successful partial re-
dos sometimes occur. He re the foundation problem caused by pair. The statistics reflect situations
contractor makes an initial repair washout failed to appear. Howe ve r, where new work on the same house
that, for one reason or another, s e ve ral commercial projects were is categorized as re-do. This proba-
must be tempered, repeated or encountered where water lines part- bly accounted for 4 or 5 of nine par-
supplemented. ed and the flow eroded large vol- tials reported as re-dos.
The causes of re-dos are many. umes of bearing soil from beneath Table I presents the data collected
The largest factor, of course, is in- concrete slabs, thus causing the from repair of the 380 foundations
competency on the part of the re- foundations to settle. compiled over a 4 1/2-year period.
pair contractor. Fortunately, this is Anytime a slab foundation re- According to our best knowledge,
a problem that can be eliminated by quires a gross raise over approxi- these jobs were ultimately 100 per-
careful investigation of the firm se- mately 4 inches, the probability of a cent successful. Certain instances
lected to perform the work. re-do increases. The Dallas study in- required attention subsequent to
Also, for example, assume that a dicates this situation is not com- the initial repair. Of the 380 jobs, the
foundation is adequately and profi- mon, perhaps because technology Texas firm was asked to return on a
total of 18. These were subdivided count for 5 of the remaining 9. the comparison of technique.
as follows: 3. The four remaining were con- The pier and beam re p re s e n t e d
1. Nine were partials. These de- sidered unexplained. That is, no log- only about one-fourth the total jobs
scribe instances where only part of a ical explanation could be developed considered. All the data are statisti-
foundation was initially re p a i re d , for the failures. cal. In the next 380 jobs the data
and represent a condition theoreti- Ne g a t i ve l y, one might conclude could develop more unexplained
cally conducive to recurrence of that the history represents 9 re-dos pier and beam than slab. This then
foundation movement. This, plus out of 380 jobs (2.4 percent). Realis- might tend to equate the percent-
the fact that several of these re-dos tically, as outlined in preceding ages.
were actually new contracts on ar- p a ra g ra p h s, the data reflects 4 re- The data from the Dallas study es-
eas not previously repaired, encour- dos out of 380 (1.1 percent). The re- tablished that foundation problems
ages us to disregard the nine from ally important fact is that out of 380 can be permanently corrected. The
statistics as re-dos. This resolves our jobs all were ultimately successful. technique is extremely important
consideration from 18 to only 9. Most re-dos involve only a grade and might, in fact, be the controlling
2. The firm also established that perfection of 1⁄4-inch or less. They re- factor. Howe ve r, a substantial part
new water leaks produced upheaval late only to a limited area of the of this technique involves proper
in one case (previously repaired for foundation (usually a corner) and treatment of the particular soil. The
settlement). In another instance the occur most often within 15 to 60 key then would be to interpolate
foundation raise was in excess of 5 days after the foundation has been proven procedure in one area to
inches and therefore likely to re- restored. Most problems develop other locales.
quire subsequent attention. (In ex- before 30 days and it is recommend- The remedial techniques used in
treme raises allowance for the ed that remodeling or interior re- this study have been employe d
shrinkage of the grout becomes a pairs be delayed at least 30 days af- with success over a wide area cov-
factor to consider. Because of this, ter restoration. e ring most of Te x a s, and parts of
one could normally expect to top- Isolating the pier-and-beam sta- Louisiana, Oklahoma and
out the grout. Through technology, tistics from the slab data shows that Arkansas.
much has been done to eliminate the slabs required 2.1 percent
this problem.) Two re-dos invo l ve d greater total re-dos. The pier and
situations where, after repair, the beam reflect about the same “ex- This is the first installment of a two-
houses were left vacant for about six plained,” but a much more favor- part article on foundation repair. The
second portion will appear in a future
months which included a hot dry able “unexplained,” 0 percent. Slab issue.
summer; further, in both cases im- repair (mud-jacking) requires con-
proper drainage was not corrected. siderably more on-the-job skill and
Another re-do resulted from the fail- competency than pier and beam PUBLICATION#C710283
ure of a home-owner to correct a se- (mechanical). This introduces a hu- Copyright © 1971, The Aberdeen Group
rious drainage problem. These ac- man influence which might distort All rights reserved

You might also like