PROJECT SANCTION ORDER

No. RD/PM/3351/19-20 Date : 18-07-2019

Development of Fe-500D/Fe-550DTMT rebars with low carbon


1 Project Title :
equivalent at DSP

K:97:78:53:00:2019
2 Project Number :
00:29:62:08:00:63.80

Name of the Spokesperson & Group : DR. P SARAVANAN (LONG PRODUCT &
3
MECHANICAL LAB. GROUP)

4 Starting Date : 01 June 2019

5 Completion Date : 31 January 2020

6 Engineer-Days required :

LONG PRODUCT &


YEAR MECHANICAL LAB. TOTAL
GROUP
2019-2020 200 200

TOTAL 200 200

7 Sanctioned Cost (Rs in Lakhs ) :

2019-
TOTAL
2020
Capital
0 0

Direct Revenue 5 5

Engineer Days Cost 58.80 58.8

Total 63.80 63.8

8 Sanctioning Authority : APPROVED BY EXECUTIVE DIRECTOR ON 04.07.2019

9 Details of Capital Expenditure (Rs in Lakhs)

Nil

10 Details of Equipment (at #9 costing more than Rs 10,000/-) :


Nil

11 Details of Revenue Expenditure (Rs in Lakhs) :

2019-2020 TOTAL

COST OF ENGINEER-DAYS 58.80 58.80

FABRICATION/MACHINING FROM
1 1
OUTSIDE
MATERIAL, SPARES &
4 4
CONSUMABLES

TOTAL 63.80 63.80

( C MANDAL )
DGM & HOG (PC)

Format No. RD-PR-B01-FR05 Issue Status : 0 Effective


Date :
30.06.2018
REVIEWED BY: APPROVED BY: