Method of Statement For in Situ Box Culvert PDF
Method of Statement For in Situ Box Culvert PDF
1.0 OBJECTIVE
Hydraulic Excavator
Mobile Crane
Pile Rig
Ready - made concrete/ concrete mixer
Welding Set
Compactor Roller
Backhoe
Portable Water Pump
Haulage tippers for disposal of spoils
Small tools
Site Engineer
Site Supervisor
Survey team & equipment
3.1 Introduction
1/7
PENSWASTAAN PENYELENGGARAAN JALAN – JALAN PERSEKUTUAN DI
SEMENANJUNG MALAYSIA (ZON SELATAN)
3.2.3 The traffic team member must wear suitable clothing to ensure
they can be seen clearly by the road users.
2/7
PENSWASTAAN PENYELENGGARAAN JALAN – JALAN PERSEKUTUAN DI
SEMENANJUNG MALAYSIA (ZON SELATAN)
3.3.2 Normally the trench width will be slightly wider (i.e 600mm on
each side) than the width of the Box-culvert to be installed
works. This will be the working space during laying of Box-
Culvert and also for manual compaction of backfilling material.
3.3.3 A breaker will be used to cut the top surface of the road along
the marked lines to ensure the cut section will be neat in
appearance and with less damage to the adjacent road during
the excavation work.
3.4 Excavation
3.4.1 Prior to the excavation works, the area shall probably marked
as a guide to control the longitudinal alignment of the culvert
crossing.
3.4.4 The supervisor must monitor the excavation work and check the
level from time to time to avoid over excavation and to ensure
the correct gradient for the laying work is achieved.
3/7
PENSWASTAAN PENYELENGGARAAN JALAN – JALAN PERSEKUTUAN DI
SEMENANJUNG MALAYSIA (ZON SELATAN)
3.4.6 The excavated soil shall be stockpiled nearby and shall be used
as backfilling material if found suitable. Unsuitable soil shall be
removed from site a soon as possible.
4/7
PENSWASTAAN PENYELENGGARAAN JALAN – JALAN PERSEKUTUAN DI
SEMENANJUNG MALAYSIA (ZON SELATAN)
5/7
PENSWASTAAN PENYELENGGARAAN JALAN – JALAN PERSEKUTUAN DI
SEMENANJUNG MALAYSIA (ZON SELATAN)
A Slab
3.7.1 The area of the proposed slab shall be set out with timber
shuttering supported in place to cast the concrete slab.
3.7.2 A minimum 30/20 concrete mix shall be used. This will ensure a
concrete of 30N/mm2 and the biggest aggregate size of 20mm.
3.7.3 The required reinforcement bars shall high tensile bars be
placed in position, ensuring the required cover and the slab
length is maintained.
3.7.4 Place and compact the concrete to the finishing depth, making
sure the concrete is under the channels.
3.7.5 The slab shall be compacted using a vibrating screed and poker
vibrator, to ensure the removal air trapped during the mixing
process.
6/7
PENSWASTAAN PENYELENGGARAAN JALAN – JALAN PERSEKUTUAN DI
SEMENANJUNG MALAYSIA (ZON SELATAN)
B Wall
3.7.6
7/7