Professional Documents
Culture Documents
www.elsevier.com/locate/jlp
Abstract
In refineries and processing plants, the enormous amount of piping is more complex in distribution than other types of equipment. In
general, compared with other types of equipment in these industries, more difficulty in inspection planning is encountered.
However, under-inspection or over-inspection can occur due to the lack of jurisdictional requirements on the inspection interval and
method for piping, or the inspection interval being based only on piping service classifications in the existing regulations, such as API 570.
This can result in unacceptable risks, along with costly loss of resources.
To lessen the piping risk level, more and more companies have adopted and applied risk based inspection (RBI) methodology, leading to
risk reduction and cost benefits since the last decade. This study applied RBI methodology to optimize the inspection strategy of the piping in
a refinery and petrochemical plants in Taiwan. Two actual case studies were corroborated better with quantitative RBI methodology than
without the methodology in terms of risk and cost reductions.
q 2005 Elsevier Ltd. All rights reserved.
Keywords: Piping risk level; Risk based inspection; Risk reduction; Inspection strategy; Quantitative RBI
2. Experimental
Probability Consequence
analysis analysis
portions of the process unit require the most inspection According to the potential losses, the quantitative
attention or other methods of risk reduction. It can also be method could determine risk levels. The LOF is the generic
executed to determine whether a full quantitative study is failure frequency (GFF) for the specific type of equipment,
justified. which is based on a compilation of available equipment
In addition to the qualitative RBI method, the semi- failure histories from various industries, and multiplied by
quantitative method takes account of the inspection results, an equipment modification factor and management system
such as corrosion rate, historical records, and maintenance evaluation factor. The COF can be assessed with the losses,
information, and so on. Under certain circumstance, the i.e. hazard, environment, impact on business interruption
method can alleviate the discrepancies in risk assessment and maintenance expense, etc. The risk calculation concept
induced by a person with subjective judgments. is depicted in Fig. 3. Therefore, the calculated quantitative
Likelihood of Consequence
RISK
failure (LOF) of failure (COF)
Environment
cleanup ($)
Age
Adjacent
Damage repair ($)
mechanisms
and rates
Inspection
Downtime ($)
effectiveness
TOTAL ($)
2.3. Determination on the optimal inspection frequency Chemical plant Refinery (FCC plant)
(Propane plant)
According to API 570, the inspection frequency should Numbers Percentages Numbers Percentages
be scheduled at the half remaining life or established on the High 0 0.00 4 0.68
basis of fluid content, depending on whichever is shorter, as Medium-high 6 2.88 361 61.7
Medium 88 42.31 184 31.45
suggested in Table 1 (American Petroleum Institute, 2000).
Low 114 54.81 36 6.15
However, determining the inspection frequency may Total 208 100 585 100
possibly not only lead to under-inspection of some high-
risk items, but also waste resources on many low-level
risk items. Therefore, the best inspection interval should the possible risk distribution of the piping is generally not
be dictated by combining the piping risk level and considered. To learn the difference between full plant and
inspection effectiveness. The confidence rating is given as piping on RBI results, this article presented two case studies
less than 0.5 for high-level risk items, and more than 0.5 for piping with quantitative RBI. The information of two
for low-level risk items (Chang & Chen, 2001). Inspection plants is given as follows:
effectiveness means the possibility and veracity of the Plants arrangement:
inspection method, which relates to the inspector’s
personal ability and fitness for the selected inspection (1) RBI study for fluid catalytic cracking (FCC) plant, a
method. The highest inspection effectiveness is always thirty years service life with 585 piping for analysis.
defined as 1.0. Accordingly, the inspection interval can be (2) RBI study for propane chemical plant, a 14 years
expressed in Eq. (1) as follows: service life with 208 piping for analysis.
To identify the defects, one should use different
Estimate steps:
inspection methods for piping defects with various
corrosion types, different piping locations and operating Data collecting / Site survey / Data confirming /
conditions. Both a qualified No-Destructive Examination Piping history review /Define corrosion loop /
(NDE) inspector and right inspection procedures are Define plant information / RBI analysis/ Final
essential requirements for carrying out piping inspection. ranking results.
NID Z hCRL (1)
Estimate software:
where NID, next inspection date (year);
With DNV ORBIT Onshore (Det Norske Veritas, 2001)
h - inspection effectiveness ratio (value range 0–1); software for quantitative RBI methodology.
C confidence rating (value range 0–1, based on the risk
ranking); The study evaluated the risk of both units based on the
RL remaining life (year). probability of failure of the piping that could result in a leak
and hence cause hazard and financial consequences. It also
took into account the current confidence in the condition
2.4. Two case studies on processing piping with RBI based on the nature of the inspections previously performed
methodology and their ability to characterise the extent and rate of the
different damage mechanisms. This was achieved by
Actually, most risk occurred at a few equipments, which applying the DNV/API RBI methodology (Lee & Teo,
mostly based on full plant practice results. That means 2001) using the software (Det Norske Veritas, 2001) version
2.3.14 for analysis. The risk overview is presented in
Table 1 Table 2 and Figs. 4 and 5. Here, Figs. 4 and 5 demonstrate
Recommended maximum inspection intervals (American Petroleum that 20% piping and 10% piping account for 75 and 95%
Institute, 1997)
risk for FCC plant and propane plant, respectively.
Type of circuit Thickness Visual external
measurements
Class 1 5 years 5 years
Class 2 10 years 5 years 3. Results and discussion
Class 3 10 years 10 years
Injection points 3 years By piping class Based on the two case studies, we can obtain valuable
Soil-to-air interfaces NA By piping class
results as follows: (1) Piping also has similar risk
NA, not applicable. distribution, compared with full plant. That means most
M.-K. Chang et al. / Journal of Loss Prevention in the Process Industries 18 (2005) 397–402 401
Table 3
Risk ranking distributed after highly efficient inspection
Risk Plant
ranking Chemical plant Refinery (FCC plant)
(Propane plant)
Numbers Percentages Numbers Percentages
High 0 0 1 0.17
Medium– 3 1.44 136 23.25
high
Medium 90 43.27 385 65.81
Low 115 55.29 63 10.7
Total 208 100 585 100
References
American Petroleum Institute (2000). Base resource documentation for risk Jansen, H. J. M., Fasten, M. M., & Pots, B. F. M. (1998). Piping risk based
based inspection (1st ed.). Washington, DC, USA: API Publication 581. inspection and outline of methodology. Amsterdam, The Netherlands:
Chang, R. R., & Chen, J. J. (2001). Risk management application on Shell International Exploration and Production, B.V..
refinery piping inspection The 17th annual conference of Asia pacific Lee, C. G., & Teo, Y. S. (2001). Det norske veritas RBI study for the
occupational safety and health organization, Taipei, Taiwan, ROC pp. ammonia storage plant. Taiwan, ROC: Taiwan Fertilizer Kaohsiung
404–414. Ammonia Terminal.
Chang, R. R. (2004). Remaining life prediction of error caused by Mahoney, D. (1998). Large property damage losses in the hydrocarbon
temperature effects in ultrasonic thickness measurement 12th Annual chemical industries—a thirty years review (17th ed.). New York: J and
conference of non-destructive testing, Section 4C-A18, Taiwan, ROC. H Marsh and McLennan.
Det Norske Veritas (2001). ORBIT RBI Onshore, Version 2.3.14, UK. SIEP 98-5214 (1998). Maintenance management guideline: Risk based
Festen,M. M., & Ravedtein,M. H.(1997). Guidelinefor risk basedinspection. inspection in explorations and production. Amsterdam, The Nether-
Hague, The Netherlands: Shell Research and Technical Service. lands: Shell International Exploration and Production, B.V..