Professional Documents
Culture Documents
49196.60x1.50x1.05 m3 77484,65
5. Izgradnja nasipa pomoću
vodonepropusnog materijala iz
posudbene jame.
Za stabilizacijske pragove.
(1,50 + 4,50)
/2x1.50x3.00x9+21.05x0.50x1.5x2+25.9
5x0.50x1,50x7=289.30
Ukupno dodatno iskopavanje: 10933.64
Od toga:
95% mehanički
m3 10386,97
5% ručno m3 546,68
2. Nabava, transport i polaganje geotekstila
400g / m2 pod tamponskim slojem
primjene rijeke. Preklopite geotekstil 50
cm, sve u skladu sa normalnim profilom.
Izračun po m2.
Veličine su povećane za 10% zbog
preklapanja.
Izračun se daje u skladu s priloženim
crtežima.
((17,80 + 3,44) x927.80 + (14,00 + 3,44)
x149.14)) x1.10 = 24538,20
Izračun po m2.
m2 24538,20
3. Nabava, transport i ugradnja materijala
za izgradnju tamponskog sloja ispod
prizme, sve u skladu s priloženim
crtežima i tehničkim uvjetima koji se
primjenjuju na radove. Izračun se daje u
skladu s priloženim crtežima.
1.88x2x3.00x9 = 101,52
Izračun po m3.
m3 101,52
6. Nabava, transport i izlijevanje betona
MB30 u betonsku nožičnu gredu.
Jedinična cijena uključuje armaturu (2 x
Q188), odgovarajuće oplatu i njegu
svježeg betona.
Veličine se daju u skladu s priloženim
crtežima, a radovi se izvode u skladu s
tehničkim uvjetima koji se primjenjuju
na radove.
0,88 x 1076,94
m3 947,70
7. Nabavka, transport i izlijevanje betona
MB30 u krunu grede. Veličine se daju u
skladu s priloženim crtežima, a radovi se
izvode u skladu s tehničkim uvjetima
koji se primjenjuju na radove.
0.24x1076.94
Izračun po m3.
m3 258,46
8. Nabava, transport i izlijevanje betona
MB30 u stabilizacijske pragove.
Veličine se daju u skladu s priloženim
crtežima, a radovi se izvode u skladu s
tehničkim uvjetima koji se primjenjuju
na radove.
24.05x0.50x1.50x2 + 28.95x0.50x150x7
Izračun po m3 m3 188,05
9. Nabava, transport i montaža betonskih
šesterokutnih prizmi debljine 25 cm
nakosini riječne obale. Betonske prizme
moraju se postaviti na prethodno
pripremljenu tamponsku bazu, sve u
skladu s priloženim crtežima i tehničkim
uvjetima koji se primjenjuju na radove.
17.80x927.80 + 14.00x149.14
Izračun po m2.
m2 18602,84
IV GRAĐEVINE
Od toga:
19.68x82.70 m3 1627,50
4. Polaganje humusnog sloja debljine 20
cm i nanošenjem površine, kao što je
naznačeno na crtežima udruživanja.
Koristite prethodno uklonjeni humus
koji je privremeno pohranjen na
privremenoj deponiju, sve u skladu s
uvjetima izvođenja radova.
Veličine se dobivaju prema crtežima
udruživanja.
19.90x82.70 m2 1645,70
TOTAL IV1.1. ZEMLJANI RADOVI:
Za stabilizacijske pragove:
(4.50x3.00+0.50x1.50x29.24)x2+4.50x1
2.22=125.85
Out of which:
5% manually m3 21,53
2. Nabava, transport i polaganje geotekstila
400g / m2 pod tamponskim slojem obale
rijeke. Preklopite geotekstil 50 cm, sve u
skladu sa zatvorenim normalnim
profilom.
0.50x1.50x(29.24x2+12.22)=53.03
5.64x85.14=480.20
8.00x4.40x0.70+
(15.50+11.10)/2x10.00x0.40=77.80
90 % mechanically m3 36,55
10 % manually m3 4,06
2. Backfilling of the trench using the
excavated material after the completion
of the entrance shaft and exiting head
and laying the pipe. The backfilling to be
done in 30 cm thick layers, and include
spreading and compacting to the required
compactness level. m3 32,09
3. Procurement, transport and installation
of the filter tampon layer under the
entrance shaft and exiting head of the
structure.
4 PIECES
90 % mechanically m3 31,39
10 % manually m3 3,48
2. Backfilling of the trench using the
excavate material after the completion of
the entrance shaft and exiting head and
laying the pipe. The backfilling to be done in
30 cm thick layers, and include spreading
and compacting to the required compactness
level. m3 26,67
3. Procurement, transport and installation
of the filter tampon layer under the
entrance shaft and exiting head of the
structure.
Calculations given in accordance with
the enclosed drawings. m3 0,70
4.
Mechanical preparation, transport and
installation of concrete MB25 in the entry
shaft and exiting head of the structure.
The price includes all required forms and
curing of the fresh concrete.
Calculations given in accordance with
the enclosed drawings. m3 4,50
5
Procurement, transport and installation
of concrete hexagonal prisms 25 cm
thick along the slope of the confluence
area. Concrete prisms are to be laid on
previously prepared tampon base, all in
accordance with the enclosed drawings and
technical conditions applicable to the works.
TOTAL IV4.2:
1 PIECE
5 % manually m3 4,16
2.
Procurement, transport and installation
of materials for the filter tampon layer 10
cm thick under the concrete of the stairs.
Quantities provided in accordance with
the drawings of the stairs.
stairs type 1 2 x 4.95m3 2 pieces
stairs type 2 1 x 3.85 m3 1 piece
stairs on the defended side:
stairs type 1 2x1.28m3 2 pieces
stairs type 2 1x0.02m3 1 piece
Calculation per m3 m3 17,25
3.
Procurement, transport and installation
of concrete MB30 for constructing the
stairs and threshold under the stairs, all
in accordance with the drawings of the
stairs and technical conditions applicable
to the works.
RECAPITULATION STRUCTURES:
TOTAL STRUCTURES:
RECAPITULATION A:
A. RIGHT RIVERBANK
I PREPARATORY WORKS
II MAIN EARTHWORKS
IV STRUCTURES
GRAND TOTAL A:
B: RIGHT SIDE EMBANKMENT
I. PREPARATORY WORKS
Note:
II MAIN EARTHWORKS
1
Mechanical removal of humus topsoil to
the depth of 20 cm, or to the depth of its
complete removal. Humus to be deposited
outside of the construction belt and later used
for covering and grassing area, all in
accordance with normal cross profiles.
19709.17x1.5x1.05 m3 31041,94
3 Construction of embankment using
watertight material from the borrowing
pit.
This includes spreading, rough and fine
evening and compacting of material in layers
not more than 30 cm thick using suitable
machines in order to ensure as good as
possible stability and water tightness of the
embankment. Each layer to be compacted in
the full width to the level of compaction
foreseen in the designs, which is at least 95%
by standard Proctor procedure.
Quantities provided in accordance with
the table of main earthworks. m3 29563,76
4
Laying humus topsoil 20 cm thick and
grassing the areas as shown in cross
sections. Use previously removed humus
temporarily stored at the deposit site, all in
accordance with the conditions of carrying
out the works.
III STRUCTURES
90 % mechanically m3 45,14
10 % manually m3 5,02
2. Backfilling of the trench using the
excavate material after the completion of
the entrance shaft and exiting head and
laying the pipe. The backfilling to be done in
30 cm thick layers, and include spreading
and compacting to the required compactness
level. m3 41,29
3. Procurement, transport and installation
of the filter tampon layer under the
entrance shaft and exiting head of the
structure.
Calculations given in accordance with
the enclosed drawings. m3 0,70
4.
Mechanical preparation, transport and
installation of concrete MB25 in the entry
shaft and exiting head of the structure.
The price includes all required forms and
curing of the fresh concrete.
Calculations given in accordance with
the enclosed drawings. m3 4,50
5
Procurement, transport and installation
of concrete hexagonal prisms 25 cm
thick along the slope of the confluence
area. Concrete prisms are to be laid on
previously prepared tampon base, all in
accordance with the enclosed drawings and
technical conditions applicable to the works.
4 PIECES
RECAPITULATION B:
I PREPARATORY WORKS
II MAIN EARTHWORKS
III STRUCTURES
GRAND TOTAL B:
RECAPITULATION A + B:
A. RIGHT RIVERBANK
I. PREPARATORY WORKS
Note:
Prior to starting the work, the
Contractor is obliged to obtain
information on the existing
installations (water supply,
sewerage pipes, gas installations,
power supply, etc.) that need to
be displaced in order to avoid any
damage.
1. Marking out the base of the bank
enforcement on the left side of the
Drina River and transferring all
the information from the drawing
to the site. Maintaining all markings
on the site throughout the period from
starting the works until the turnover to
the Contracting Authority.
II MAIN EARTHWORKS
1. Mechanical removal of humus
topsoil to the depth of 20 cm, or to
the depth of its complete removal.
Humus to be deposited outside of the
construction belt and used again for
grassing areas in accordance with
normal cross profiles.
Quantities provided in
accordance with the table of main
earthworks. m2 29077,57
2. Mechanical cleaning of natural
riverbed from trash and materials
brought down by water, of
average thickness of 20 cm on the
left side of the Drina River. The
price includes: Loading, transport for
approximately 5.0 km, and off-
loading to the old depositing site at
location of Lug.
Quantities provided in
accordance with the table of main
earthworks. m2 21066,49
3. Mechanical excavation in material
of III and IV category as wide
excavation on the left side of the
Drina River. Use the excavated
material to fill the surrounding terrain
behind the embankment, and
transport the surplus to the
depositing site at location of Lug. The
price includes: Excavation, loading,
transport for approximately 5.0 km
and off-loading at the depositing site.
Out of total quantity of excavation,
the expectation is that 85% would be
in naturally moist material and 15 %
in the presence of water.
Quantities provided in
accordance with the table of main
earthworks.
Total excavation: 12125.37
Out of which:
- mechanical in naturally moist
material
85% x12125.37 m3 10306,56
- mechanically in the presence of
water
15% x12125.37 m3 1818,80
4. Mechanical excavation of material
of III category in wide excavation
from the material borrowing pit
assuming the layer of 1.50 m
depth (with previously removed
layer of humus of min. 0.50 m) The
price includes: Loading, transporting
for approximately 6.0 km and off-
loading at the location of its use in the
embankment. Looseness coefficient
1.05. Proposal is to use borrowing pit
at the location of the Old Brickyard.
Calculation per m3.
50555.50x1.50x1.05 m3 79624,90
5. Construction of embankment
using watertight material from the
borrowing pit.
This includes spreading, rough and
fine evening and compacting of
material in layers not more than 30
cm thick using suitable machines in
order to ensure as good as possible
stability and water tightness of the
embankment. Each layer to be
compacted in the full width to the
level of compaction foreseen in the
designs, which is at least 95% by
standard Proctor procedure.
Quantities provided in
accordance with the table of main
earthworks. m3 75833,22
6. Laying humus topsoil 20 cm thick
and grassing the areas as shown
in cross sections. Use previously
removed humus temporarily stored at
the deposit site, all in accordance
with the conditions of carrying out the
works.
Quantities provided in
accordance with the table of main
earthworks.
Calculation per m2. m2 22256,51
7.
Transport of surplus materials
from the excavation, after the
completion of the embankment
and filling of the surrounding area
behind the embankment.
Transport to the old depositing site at
location of Lug. The price includes:
Loading, transport for around 6.0 km
and off-loading to the deposit site.
1364.21+12125.37+15641.14=29
130.70
Out of which:
95% mechanically m3 15173,65
5% manually m3 798,61
2. Procurement, transport and laying
of the geotextile 400g/m2 under
the tampon layer of the riverbank
enforcement. Overlap the
geotextile 50 cm, all in
accordance with the enclosed
normal profile.
Calculation per m2.
Quantities have been increased
by 10% because of the overlaps.
0.24x 430.80+0.24x3x1094.20
Calculation per m3. m3 891,20
8. Procurement, transport and
pouring of concrete MB30 into the
stabilization sills. Quantities are
provided in accordance with the
enclosed drawings, and works to be
carried out in accordance with the
technical conditions applicable to the
works.
24.20x0.50x1.50x4+29.45x0.50x
1.50x6
Calculation per m3. m3 205,13
9. Procurement, transport and
installation of the concrete
hexagonal prisms 25 cm thick on
the riverbed slopes. Concrete
prisms are to be laid on previously
prepared tampon base, all in
accordance with the enclosed
drawings and technical conditions
applicable to the works.
13.90x430.80+19.70x1094.20
Calculation per m2. m2 27543,90
IV STRUCTURES
IV1 CONNECTION WITH THE
EXISTING RIVERBED AT THE
BEGINNING OF THE BANK
ENFORCEMENT
Note: Out of structures on this
transitional section at the
beginning of the riverbank
enforcement, foreseen are the
stabilization sill and flank
embankment, and they are
covered in Chapter II of this Bill of
Quantities.
1. Forming the bank and protection
of the slope using a layer of rock,
section km 0+023.70 downstream
from the stabilization sill,
attachment number 44. Forming
the slope and fitting the bank
enforcement into the natural
riverbed to be done by use of
rocks of kernel size dav=30 cm.
The price includes procurement,
transport and installation of the
stones, all in accordance with
attachment number 44 and
technical conditions applicable to
the works.
(11.20+9.80)/2x5.70x0.40=23.90
90 % mechanically m3 34,78
10 % manually m3 3,87
2. Backfilling of the trench using the
excavate material after the
completion of the entrance shaft
and exiting head and laying the
pipe. The backfilling to be done in 30
cm thick layers, and include
spreading and compacting to the
required compactness level. m3 30,25
3. Procurement, transport and
installation of the filter tampon
layer under the entrance shaft
and exiting head of the structure.
Calculations given in accordance
with the enclosed drawings. m3 0,70
4. Mechanical preparation, transport
and installation of concrete MB25
in the entry shaft and exiting head
of the structure. The price includes
all required forms and curing of the
fresh concrete.
Calculations given in accordance
with the enclosed drawings. m3 4,50
5. Procurement, transport and
installation of concrete hexagonal
prisms 25 cm thick along the
slope of the confluence area.
Concrete prisms are to be laid on
previously prepared tampon base, all
in accordance with the enclosed
drawings and technical conditions
applicable to the works.
3 PIECES
90 % mechanically m3 50,30
10 % manually m3 5,59
2. Backfilling of the trench using the
excavate material after the
completion of the entrance shaft
and exiting head and laying the
pipe. The backfilling to be done in 30
cm thick layers, and include
spreading and compacting to the
required compactness level. m3 46,81
3. Procurement, transport and
installation of the filter tampon
layer under the entrance shaft
and exiting head of the structure.
Calculations given in accordance
with the enclosed drawings. m3 0,98
4. Mechanical preparation, transport
and installation of concrete MB25
in the entry shaft and exiting head
of the structure. The price includes
all required forms and curing of the
fresh concrete.
Calculations given in accordance
with the enclosed drawings. m3 4,90
5. Procurement, transport and
installation of concrete hexagonal
prisms 25 cm thick along the
slope of the confluence area.
Concrete prisms are to be laid on
previously prepared tampon base, all
in accordance with the enclosed
drawings and technical conditions
applicable to the works.
TOTAL IV3.2:
3 PIECES
(71.10+7.65+42.10)x4.00
Calculation per m2. m2
2. Procurement and transport of
gravel and gritting material for
constructing the driveway 4.00 m
wide. The driveway to be
constructed in two layers using
gravel (of natural granulation) of
thickness d=27 cm in rolled state,
and finishing layer of gritting
material 3 cm thick, including
compressing to the compression
level of minimally 60 MN/m2.
(71.10+7.65+42.10)x4.00x0.30 m3
RECAPITULATION C:
C. LEFT BANK
I PREPARATORY WORKS
II MAIN EARTHWORKS
IV STRUCTURES
GRAND TOTAL C:
D. LEFT EMBANKMENT
FROM KM 0+000 TO KM
0+632.69
I. PREPARATORY WORKS
Note:
Prior to starting the work, the
Contractor is obliged to obtain
information on the existing
installations (water supply,
sewerage pipes, gas installations,
power supply, etc.) that need to
be displaced in order to avoid any
damage.
1. Marking the basis of the
embankment on the right side of
the Drina River by transferring all
the data from the drawings on the
site. Maintaining all markings on the
site throughout the period from
starting the works until the turnover to
the Contracting Authority.
II MAIN EARTHWORKS
1 Mechanical removal of humus
topsoil to the depth of 20 cm, or to
the depth of its complete removal.
Humus to be deposited outside of the
construction belt and later used for
covering and grassing areas, all in
accordance with normal cross
profiles.
Quantities provided in
accordance with the table of main
earthworks. m2 5649,02
2 Mechanical excavation of material
of III category in wide excavation
from the material borrowing pit
assuming the layer of 1.50 m
depth (with previously removed
layer of humus of min. 0.50 m) The
price includes: Loading, transporting
for approximately 6.0 km and off-
loading at the location of its use in the
embankment. Looseness coefficient
1.05. Proposal is to use borrowing pit
at the location of the Old Brickyard.
5084.43x1.5x1.05 m3 8007,98
3 Construction of embankment
using watertight material from the
borrowing pit.
This includes spreading, rough and
fine evening and compacting of
material in layers not more than 30
cm thick using suitable machines in
order to ensure as good as possible
stability and water tightness of the
embankment. Each layer to be
compacted in the full width to the
level of compaction foreseen in the
designs, which is at least 95% by
standard Proctor procedure.
Quantities provided in
accordance with the table of main
earthworks. m3 7626,64
4
Laying humus topsoil 20 cm thick
and grassing the areas as shown
in cross sections. Use previously
removed humus temporarily stored at
the deposit site, all in accordance
with the conditions of carrying out the
works.
Quantities provided in
accordance with the table of main
earthworks.
10 % manually m3 2,92
2. Backfilling of the trench using the
excavate material after the
completion of the entrance shaft
and exiting head and laying the
pipe. The backfilling to be done in 30
cm thick layers, and include
spreading and compacting to the
required compactness level. m3 21,05
3. Procurement, transport and
installation of the filter tampon
layer under the entrance shaft
and exiting head of the structure.
Calculations given in accordance
with the enclosed drawings. m3 0,70
4. Mechanical preparation, transport
and installation of concrete MB25
in the entry shaft and exiting head
of the structure. The price includes
all required forms and curing of the
fresh concrete.
Calculations given in accordance
with the enclosed drawings. m3 4,50
5. Procurement, transport and
installation of concrete hexagonal
prisms 25 cm thick along the
slope of the confluence area.
Concrete prisms are to be laid on
previously prepared tampon base, all
in accordance with the enclosed
drawings and technical conditions
applicable to the works.
TOTAL III1:
3 PIECES
D. LEFT EMBANKMENT
I PREPARATORY WORKS
II MAIN EARTHWORKS
III STRUCTURES
GRAND TOTAL D:
RECAPITULATION C+D:
C. LEFT BANK
D. LEFT EMBANKMENT