You are on page 1of 4

Fact Sheet

July 2012 | Project Principles Series | Paper 1

Basis of design
Oakajee Port and Rail (OPR) is developing a deepwater port north of Geraldton, linked to the region’s
emerging mining operations via a 570km Standard-Gauge, heavy haul railway. This edition of the Project
Principles Series examines the basis of design for the port and rail components.

The Oakajee Task


Described as one of the single most OPR’s design is based on agreed • Berthing capacity for Capesize
important projects for WA’s economic project principles with the State. They vessels; and
development over the next 50 years, include: • Port and rail infrastructure
the State Government’s port and rail • Development of an integrated capable of accommodating
design requirements aim to create logistics chain, allowing the at least 35mpta of ore (the
a new, globally competitive minerals efficient export of mineral equivalent of moving the entire
province in the mid-west. products to world markets; Geraldton Zone’s annual grain
• Open access arrangements harvest every five weeks), with
for third party port and rail capability for staged expansion
infrastructure users; to over 70mtpa.

A Fit-For-Purpose Design
In mid-2009, OPR appointed and foundation customers, based on
experienced Tier 1 engineering, a single rail line operation, ensuring
procurement and construction the optimum amount of equipment is
management company WorleyParsons utilised.
to manage the project’s design and On the current Bankable Feasibility
engineering, along with capital and Study (BFS) base-case - the delivery
operating cost estimates, and oversee of 45mtpa - the OPR model delivers
the work of leading engineering and the lowest unit of cost capacity
specialist consultants. and lowest absolute capital cost,
The resulting design reflects the relative to other gauge and axle load
need to shift large tonnages of combinations.
ore over long distances, as safely The project also satisfies requirements
and efficiently as possible. It is to allow for open access arrangements
driven by the stipulated minimum for third party port and infrastructure
tonnage requirements of the State users.

An Integrated Pit-to-Port Supply Chain


OPR’s port and rail design has been
subject to extensive independent peer
review, including value engineering
assessments. All endorsed the
fundamental basis of design.
As an indication of the quality of work
completed to date, OPR and consultant
AECOM were awarded a 2011 Engineers
Australia (WA) Award for Integrated Iron
Ore Supply Chain Modelling.

Oakajee Port & Rail Pty Ltd. ABN 25 117 240 007
OPR is wholly owned by Mitsubishi Development Pty Ltd.
www.opandr.com
Fact Sheet
July 2012 | Project Principles Series | Paper 1

Basis of Design - Port


The Location
The greenfields site for the Oakajee
deepwater port is 24km north of
Geraldton along Australia’s west coast.
The Oakajee site boasts a natural deep
anchorage - one of very few such sites
on the Western Australian coast. The
seabed is generally rocky with sand
pockets.
However, Oakajee still remains exposed
to ocean swell, occasional storm events
and seasonal strong winds.

Oakajee, 24km north of Geraldton.


The Task and Solution
timely manner; and create 3D physical models and conduct
• Ensuring the safe navigation and wave tank testing.
Port Key Metrics (Initial) mooring of ships into and out of The modelling examined how the
2 Capesize vessel berths the port. breakwater protected moored vessels
Extensive studies have concluded that ranging from 65,000 to 210,000
18.3m maximum laden draft deadweight tonnes (dwt) under various
a breakwater is required to meet the
2.5km breakwater basic criterion of providing adequate wave conditions. These studies will
shelter for loading operations. inform OPR engineers of the suitability
1 shiploader, 1 reclaimer of final breakwater materials and
1 rail car dumper (dual car, single Furthermore, the location, orientation design.
cell), 2 stackers and length of the breakwater will prove
vital in providing protection to allow Shiploading, train unloading and
dredging for navigation channels and stockpile equipment will be set at
the main turning basin. the minimum to achieve the required
throughput.
Apart from optimising operational To measure the impact of local sea
efficiency - in accordance with conditions on moored ships and These will be large, highly-utilized
stipulated minimum vessel size and structures, UK-based hydraulics firm machines of the same standard used for
annual throughput requirements - HR Wallingford was commissioned to decades by other iron ore infrastructure
the ability to withstand local oceanic operators.
conditions, in the context of a 50-
plus year operational life, is a major
consideration in design.
Critical factors (which are also State
requirements) include:
• The breakwater’s ability to sustain
no appreciable damage during
at least one, and preferably two,
successive 1 in 100-year storm
events;
• Ensuring berthed vessels are
adequately sheltered from
prevailing sea conditions to allow
cargo to be handled in a safe and A 3D scale model of the Oakajee breakwater, about to be subjected to massive simulated storm surges.
Breakwater vs Jetty Port configuration*
Port land zone Strategic
industry zone
At the outset of port design
at Oakajee, the merits of
breakwater compared to jetty construction Iron ore
industry zone

were examined. Cardumper


Proposed

While there are a number of unprotected Small boat


desalination plant

harbour facilities
bulk loading berths (jetties) in Australia Br
ea
kw

Por
– most notably Queensland’s bulk coal at
er Stackers

t ac
Tug pen
terminals – conditions are radically

ces

Sto
s ro
different to those experienced at Oakajee.

ckp
ad

iles
The Queensland berths are protected
from Pacific swell by the Great Barrier Cape Class Conveyor Reclaimer
Shiploader
Reef and are only subjected to locally- iron ore
export
generated wind waves. berths

Similarly, South Australia’s Port Bonython


oil terminal is protected from Southern and access trestle (jetty) would likely • Significantly increased downtime,
Ocean swells by the Spencer Gulf. result in: due to adverse weather, leading
Apart from minor influence from the • Inability to carry out cutter to higher demurrage costs; and
Abrolhos Islands, Oakajee enjoys no such suction dredging; • Greater construction risk, due to
relief from Indian Ocean swells. the open-ocean environment.
• Berths being located further out
Preliminary investigations found to sea (approx. 2.7km), in deeper
construction of an unprotected conveyor water; *Note: Slewing yard design shown for
illustrative purposes.

Capesize Berths, Globally Competitive

To ensure long-term, global maximum draft of 18.3m. Known as


competitiveness in the open sea- Capesize, this class of vessel is built
traded iron ore market, Oakajee is to serve deepwater terminals handling
designed to accommodate bulk raw materials, such as iron ore.
carriers up to 210,000dwt, with a

Basis of Design - Rail The Route

OPR’s rail route will serve the region’s


major emerging iron ore producers,
including a main line to Jack Hills and
spur to Weld Range, along with a
short spur allowing connection to
southern mines.

Passing the Moresby Ranges at the


Wokatherra Gap near the coast, further
inland the alignment is largely flat, with
few natural or man-made obstacles.

The proposed rail route has been


approved by the State Government and
now awaits passage through the WA
Parliament.
The proposed 570km rail route.

www.opandr.com
Fact Sheet
July 2012 | Project Principles Series | Paper 1

Basis of Design, Rail - The Technical Solution


and 160-180 wagons will have a gross same rail alignment - the overall capital
Rail Key Metrics weight of 24,000t-26,000t and a cost (including rolling stock) would be
payload of over 20,000t-22,000t. increased by $500m at 45mtpa and
570km single track $1.8b at 100mtpa*.
This is comparable to the iron ore trains
Heavy haul, Standard-Gauge of the Pilbara and the world’s other In addition, the ongoing operating
- 37 tonne axle load (TAL) major iron ore provinces. cost would be considerably greater for
Six 2.5km passing tracks, with Eight of these trains are used in the Narrow-Gauge, compared to Standard-
expansion capability 45mtpa design. The railway allows for Gauge.
* January 2010 costs.
11 bridges, 19 public road rail longer trains if and when required.
crossings This design minimises the number of OPR Standard-Gauge
3190 culverts at 466 locations locomotives and wagons required for vs Existing Mid-West
the fleet; the number of trains occupying
Earthworks - total fill volume
the track at any given time; and the Narrow-Gauge
8.16 million m3, total cut volume number of passing sidings. On a base case of 45mtpa,
5.28 million m3 Standard-Gauge (37TAL) compared
When these factors are considered,
the OPR Standard-Gauge design, to Narrow-Gauge (26TAL) requires:
OPR, with its consultants, has compared to Narrow-Gauge, delivers
developed a comprehensive, fit-for- � Half the number of ore cars
the lowest operating cost and lowest
purpose solution. total capital cost, with the benefit of � A fifth of the locomotives
The track will cater for trains with an iron greater capacity for future expansion. � Up to a third of the train sets
ore payload of more than 20,000t – the If the railway from Oakajee to Jack � Less train movements, delivering
current iron ore industry standard. Hills had been designed to 26TAL less portside congestion and
Trains with two locomotives of 4,400hp rather than 37TAL - even using the faster loading times

An Industry Standard, Tested Over Decades


The Pilbara is regarded as being at the Brazil operator Vale’s Carajás Railroad, The Malmbanan (Swedish for Iron Ore
leading edge of world’s best practice in better known as the EFC, supports the Line) Railway has steadily increased the
bulk freight railways, with trains of up to largest capacity trains in Latin America. axle load on its 100-year-old Standard-
40TAL (tonne axle load) and total train Last year, the axle load for the Broad- Gauge line to 30t and has plans to
gross weights of up to 50,000t, and Gauge EFC was increased to 32.5t and further increase this to 32.5t.
with the smallest trains still over 30,000t Vale has announced plans to lift this Across the world, major iron ore
mass. further to 37.5t in 2016. On its legacy producers are looking to improve
Back in the 1960s, the new heavy-haul Narrow-Gauge networks, such as the efficiencies and competitiveness, by
diesel electric locomotives combined EFVM, Vale has consistency sought to maximising train size and consistently
with advances in head-hardened rail maximise axle loads. lifting their axle loads within the legacy
to open up the renowned deposits of Even for iron ore systems using much constraints particular to each operator –
Mount Newman and Mount Tom Price. older legacy track such as South Africa’s a key consideration in the design of the
Early on, Pilbara operators recognised Transnet and Sweden’s Malmbana mid-west rail infrastructure for the 21st
the need to use high axle load trains on heavy haul railroads, a similar strategy century.
Standard-Gauge rail, even when their has been adopted.
mines were operating at tonnages less Transnet now runs the heaviest axle
than what is proposed for the mid-west. loads of any Narrow-Gauge line
Sign up for eNewsletter
(30TAL), offsetting the Narrow-Gauge Register online at www.opandr.com
Large 35-40TAL trains on Standard-
Gauge rail are considered the lowest disadvantage by running the longest to receive your email copy.
trains in the world (over 4km long) to
120718FSPPS1

cost solution in both capital and


achieve train weights of over 41,000t -
operating cost terms.
albeit at the cost of much more rolling
For more information contact
stock. Perth +61 8 9486 0777
Geraldton +61 8 9938 4900

Oakajee Port & Rail Pty Ltd. ABN 25 117 240 007
OPR is wholly owned by Mitsubishi Development Pty Ltd.
www.opandr.com

You might also like