You are on page 1of 14

Section 110

Schlum berger COILED TUBING SERVICES MANUAL


Dow ell Rev A - 98

CT STRING MANUFACTURE

Contents Page
Introduction .................................................................................................... 2
1 CT STRING DESIGN ..................................................................................... 2
2 CT STRING MANUFACTURE ......................................................................... 4
2.1 Strip Production Process ...................................................................... 4
2.2 Skelp Production Process ..................................................................... 6
2.3 Tubing Production Process .................................................................... 6
2.3.1 Strip Preparation ................................................................................... 6
2.3.2 Forming the tube ................................................................................... 8
2.4 Laboratory Testing ............................................................................... 12
2.5 Documentation Package ..................................................................... 13
2.6 Delivery and Spooling ......................................................................... 13
2.6.1 Spooling .............................................................................................. 13

Page 1 of 14
Section 110
COILED TUBING SERVICES MANUAL Schlum berger
Rev A - 98 CT STRING MANUFACTURE Dow ell

Introduction 1 CT STRING DESIGN

Coiled tubing (CT) is manufactured from low-alloy carbon There are many design criteria, or specifications, applied to
steel. To enable delivery of a reliable product with predict- CT string manufacture, many of which relate to the specific
able performance, stringent quality control and assurance conditions (operational) for which the string is being manu-
systems are applied throughout the manufacturing process factured. However, the following general requirements
- beginning as the steel alloy is produced continuing through typically apply to most CT strings:
until the delivery of the completed string and documenta-
tion package. • Meet oil and gas industry specifications for oilfield
tubulars (e.g. NACE MR-01-75 for use in H2S environ-
Limitations in the steel strip manufacturing processes ments).
meant that early CT strings were fabricated from several
short tube lengths butt-welded together to form the required • Be strong enough to withstand reasonable burst and
string length. The resulting tube to tube welds were points collapse pressures.
of potential failure due to fatigue induced in the unavoidable
heat effected zone (HAZ) located at either side of the weld. • Have a reasonable resistance to corrosion and erosion.

Improved steel manufacturing and rolling processes com- • Be sufficiently ductile to be stored on a reel and passed
bined with new tube manufacturing techniques enable over the injector head gooseneck without deforming.
modern CT strings to be manufactured without butt welds.
This has contributed greatly to the general reliability and • Have a good resistance to fatigue caused by cycling the
greater acceptance of CT services. tubing and the corresponding plastic deformation.

There are many steps in the manufacturing process, • Possess good welding characteristics, not only in the
however there are three distinct phases relating to the manufacturing process but also in the less controlled
location of the manufacturing facilities. conditions during field welding of the CT string.

Steel mill - master coils of the required material specifica- • Have a minimum number of butt welds (girth welds) which
tion are cast and rolled. are potential weak spots in the string.

Slit mill - the master coil is slit accurately into the strips • Be economically acceptable, since the tubing string will
(skelps) of the required width for the size (OD) of tubing to have a finite life and is therefor regarded as a consumable
be formed. product.

Tubing mill - In a two-stage process, skelps are assembled The principal limitation imposed on safe running depth for
to the desired string length and then passed through the a CT string comes from the hanging weight of the tubing
tubing mill to form the completed CT string. itself. Simply increasing the wall thickness throughout the
string provides no benefit since the increased string weight
counteracts the increase in load capacity. However, a
compromise is made by designing a tapered CT string,
making it possible to run long lengths of tubing while
maintaining the overall load on the tubing within a desired
safety factor of 80% of the tubing yield strength.

Tapered strings are commonly used in deep well applica-


tions, where heavy walled tubing is required at the surface
to support the load while thinner walled tubing is used
toward the downhole end to reduce the load.

Page 2 of 14
COILED TUBING SERVICES MANUAL Section 110
Schlum berger
Dow ell CT STRING MANUFACTURE Rev A - 98

Figure 1. CT string design - tapered string configurations.

Tapered strings are manufactured by welding two or more The production lengths of tubing will be approximately
segments of different gauge (wall thickness) strip. If the 3,500 feet. If possible the string should be made from
increment between the thick and thinner walled sections is elements of this length, (with the exception of the interme-
too large, it may not be possible to obtain a reliable joining diate wall sections).
weld. In such cases, short strips of intermediate wall
thickness are used to form a more gradual taper in the The intermediate sections should be at least 1,000 feet in
string. length, to enable damaged sections to be removed without
the risk of removing the intermediate section.
A further development in tapered string design uses strip
segments which are manufactured with a wall thickness During operations no part of the string should exceed 80%
reduction over the length of the strip (Figure 1). This of the published yield. For the purpose of designing the
eliminates the requirement for multiple tapered strips and tapered section, no part of the string should exceed 60% of
associated bias welds, In addition, the stress concentra- the published yield.
tions due to non-uniform load transfer caused by joining
differing gauge materials is also reduced. The taper design should allow for the maximum amount of
tension in each element based on the capacity of the
The exact design of a tapered string depends on the section at the injector head and the rating of the injector
application for which it is intended. However there are head, whichever is lower.
several criteria that should be considered when a tapered
string is designed.

Page 3 of 14
Section 110
COILED TUBING SERVICES MANUAL Schlum berger
Rev A - 98 CT STRING MANUFACTURE Dow ell

2 CT STRING MANUFACTURE sulfur. In the steel making process most of the carbon is
oxidized along with virtually all the silicon and much of the
The following CT string manufacturing sequence details the manganese. Phosphorus and sulfur, which can be detri-
process, and associated checks or tests, performed in a mental to steel quality, are also reduced. Manganese
series of manufacturing steps conducted in several loca- however, is later reintroduced in measured amounts to
tions and manufacturing facilities, including: increase the alloy strength and ductility.

Strip production - steel mill The alloy produced is relatively pure iron containing less
Skelp production - slit mill than 1.7% carbon.
Tube production - tubing mill
Arc Furnace
2.1 Strip Production Process
Iron and steel scrap are fed into the furnace through the
The majority of steel produced for CT string manufacture open roof. The roof is swung into place and carbon
originates in Japan (CT manufacturing plants in U.S.A.) or electrodes are lowered until they are in near contact with the
France (CT manufacturing plants in UK). The following furnace charge. The power is applied and an arc tempera-
production stages are common to most steel strip provid- ture of approximately 6,000 F melts the alloy materials.
ers. When the specified steel requirements are met, the furnace
is tapped and the steel run off into the casting ladle.
Blast Furnace
Casting Ladle
The blast furnace is charged with iron ore, sinter, coke and
limestone, as they descend they are met by a rising volume Immediately after the furnace is tapped, the ladle of liquid
of hot gas formed by combustion of the coke in a forced air steel, at a temperature of approximately 2,950 F, is moved
stream (preheated to 1,800 F). Carbon monoxide produced to the refining station. Here the steel is agitated with an inert
from the burning coke reduces the iron oxide to iron, while gas to provide a uniform temperature and composition.
the limestone removes impurities from the ore. The molten
iron (at 2,700 F) is tapped at the base of the furnace into At the casting ladle, the alloy is tested to ensure that its
ladles. chemical composition meets predefined criteria. The table
in Figure 2 shows a typical specifications for CT string
Iron from the blast furnace contains approximately 5% material. On conclusion of successful testing, the steel
carbon, up to 1% of both manganese and silicon, and much then passes to the continuous caster.
smaller but still significant amounts of phosphorus and

TYPICAL CT MATERIAL CHEMISTRY/COMPOSITION

Chemical composition - %: Carbon: 0.10 to 0.15 range


Manganese 0.60 to 0.90 range
Phosphorus 0.03 maximum
Sulfur 0.005 maximum
Silicon 0.30 to 0.50 range
Chromium 0.45 to 0.70 range
Copper 0.40 maximum
Nickel 0.25 maximum

Figure 2. Typical CT material chemistry/composition.

Page 4 of 14
COILED TUBING SERVICES MANUAL Section 110
Schlum berger
Dow ell CT STRING MANUFACTURE Rev A - 98

Blast furnace
ARC furnace Casting ladle

Continuous
caster

Slab reheat

Rolling mill

Pickling
Oiling Master coil

Figure 3. CT manufacturing process - master coil.

Continuous Caster Rolling Mill

The continuous caster produces steel strip in a semi- Heated, semi-finished steel slabs are passed through the
finished form. The ladle of liquid steel is tipped into an hot-strip rolling lines comprising sets of rollers that progres-
intermediate, smaller ladle that feeds a water-cooled cop- sively squeeze the slab reducing it to the required thick-
per mould. The partially solidified steel is slowly drawn into ness. This reduction in thickness is achieved with a
a series of rollers that transfers the cast material from a corresponding increase in length and, to a lesser degree
vertical to a horizontal orientation. A travelling torch cuts width.
the ingot or slab into manageable lengths.
The rolling process must be carefully monitored to ensure
Slab Reheat the finished strip is within the strict CT wall thickness
tolerances.
Since the steel slabs are produced in a continuous process,
some of the slabs may have to wait before entering the Pickling Line
rolling mill. To maintain the correct temperature the material
is held in a slab reheat facility. If, during the rolling process The rolled strip is passed through an acid spray and bath to
the slab temperature drops too much, it may also be remove surface scale and oxides which may have been
returned to the reheat facility for reconditioning prior to picked up during the rolling process. The final pickling
finishing. process includes a treatment to ensure residual chemicals
are neutralized.

Page 5 of 14
Section 110
COILED TUBING SERVICES MANUAL Schlum berger
Rev A - 98 CT STRING MANUFACTURE Dow ell

Oiling closed tube are welded using a high frequency induction


welding system.
Immediately following pickling, the strip is sprayed (coated)
with a viscous oil preparation which prevents atmospheric Each skelp received from the slit mill is dimensionally
corrosion or contamination while in storage or during checked for width and gauge and the strip edges visually
transportation to the tube manufacturing facility. inspected for any slitting process defects. A unique iden-
tification number, referencing the master coil identification,
Master Coil is assigned to each strip to ensure traceability throughout
the tube forming process.
Following pickling and oiling, the strip is wound into a spool
known as the “master coil” and prepared for shipment to the 2.3.1 Strip Preparation
slitting mill. Representative strip material from each mill
heat is submitted for chemical composition analysis to Individual skelps are spooled down and spliced to form a
ensure that the steel meets the required specification. continuous strip the length of which is determined by the
length of the CT string required (i.e., CT string length + pre
Each master coil is uniquely identified and supported with and post-mill manufacturing excess).
a documentation package which includes details of the
steel specification, manufacturing process, overall length Bias Welding
and thickness.
To ensure the weld joining each strip forms an integral part
2.2 Skelp Production Process of the assembled strip, the end of the strip is cut at a “bias“
angle which precisely matches the cut in the tail of the
Skelp production is a relatively simple process conducted preceding strip. The strips are then welded together using
at special slit mill facilities located in the U.S.A. or UK. a plasma arc welder with an inert gas shield to form one
continuous strip.
The master coil is spooled down and cut into strips (slit) by
means of rotating blades, the width of the strip being When the tube is formed, this bias weld takes on a helical
determined by the required OD of the finished tubing. The profile making the tube less prone to failure than a tube-to-
resulting strip, or skelp, is then individually prepared and tube (butt) weld.
uniquely identified before shipping to the tubing mill.
Radiographic Inspection
2.3 Tubing Production Process
The weld is visually examined then passed through a
The tubing production process is typically completed in two radiographic inspection station where it is examined for the
distinct phases. following faults:

• Stage 1 - The relatively short lengths (approximately 3500 • Gas porosity


ft) of flat steel strip, of the required properties and
dimensions, are bias welded to form the complete length • Concavity of the bead
of the CT string. Each weld is heat treated in a closely
controlled process to remove any HAZ from the strip • Uneven surface of the bead
material. The assembled strip is wound onto a accumu-
lator reel for transport to the next stage of the manufac- • Surface misalignment
turing process.
• Undercut parent material
• Stage 2 - The flat strip from the accumulator reel is passed
through the forming mill where several sets of rollers bend Any defective weld is cut out and a new joint prepared.
the strip to gradually form the tubular profile. Prior to
passing through the final roller set, the edges of the

Page 6 of 14
COILED TUBING SERVICES MANUAL Section 110
Schlum berger
Dow ell CT STRING MANUFACTURE Rev A - 98

Slitting
Bias welding

Radiography

Planishing

Machining

Heat treatment 1
2
3
4
5
Lay er 1
LAS E R

MPI inspection
Width inspection Length check Strip spool

Figure 4. CT manufacturing process - strip preparation.

Longitudinal weld

Bias weld

Figure 5. CT biased and longitudinal welds.

Page 7 of 14
Section 110
COILED TUBING SERVICES MANUAL Schlum berger
Rev A - 98 CT STRING MANUFACTURE Dow ell

Heat Treatment for the tubing mill.

Accepted welds are induction heated to raise the tempera- Due to the exacting welding processes and subsequent
ture of the weld area, thereby eliminating the hardness and extensive inspection procedures, strip assembly typically
embrittlement which occurs during any welding process (in requires more time to complete than the tube milling
the heat affected zone). process. Consequently, there are typically several accu-
mulator reels prepared to enable the tube mill to be operated
Planishing efficiently.

This optional process minimizes the amount of material 2.3.2 Forming the tube
removed in the next step by passing the weld area between
high-pressure rollers to smooth and prepare the weld area. The second stage of tube manufacture involves several
continuous phases which form the flat steel strips into
Machining tubing of the desired physical properties. The process must
be highly controlled and uninterrupted if a high-quality,
In order to achieve a smooth transition between strips, and consistent product is to be produced.
over the weld itself, excess material remaining after weld-
ing and planishing is removed by a precision grinding Due to the nature of the product, destructive testing of
process. material samples can only be conducted at the beginning
or end of the mill run. Also, physical tests cannot be
Magnetic Particle Inspection conducted on the material during manufacture. To ensure
the correct heat treatments are applied, an initial sample is
The surface of the strip is sprayed with a magnetic particle milled at the beginning of each string. The mill is stopped
solution and placed in a magnetic field. With the field active, and the sample tested for the following properties and
indications of imperfections will become apparent when the characteristics before the milling process is restarted.
site is viewed in ultraviolet light.
Once started, the milling process cannot be interrupted
Dimensional Inspection without jeopardizing the properties or integrity of the tubing
string. To confirm that the desired properties have been
The strip at the weld site is checked for thickness, width, maintained throughout the mill run, a test sample is
hardness and alignment, each measurement must fall retrieved from the tail end of the milled string. The tests and
within the original strip tolerances before the weld is checks listed below are performed, with a tubing sample
ultimately accepted. identified and stored for quality assurance purposes.

When the weld has passed inspection, a unique number • Dimensional checks
identifying the weld is assigned and marked on the strip at
both sides of the weld. Documentation relating to the weld • Ovality
is retained for inclusion in the CT string manufacturing
record. • Wall thickness

Length Counter • Seam-weld mismatch

The strip length is measured as it leaves the assembly area • Crush test
prior to being wound onto the strip accumulator reel.
• Flare test
Accumulator Reel
• Tensile test
The assembled strip is spooled up on an accumulator reel
which is used to store and transport the strip in preparation

Page 8 of 14
COILED TUBING SERVICES MANUAL Section 110
Schlum berger
Dow ell CT STRING MANUFACTURE Rev A - 98

The following steps or phases are included in the tube Two basic techniques are used for flash removal:
milling process.
• Flash material cut and removed at the tubing mill
Forming Stands
• Flash material cut at the tubing mill and then removed
The forming stands comprise a series of rollers that during the string flushing process following manufacture
gradually form the tube from the flat skelp. This manipula-
tion is designed to evenly “work” the material and avoid Seam Annealer
areas of high stress. The tube forming process also
incorporates the longitudinal welding process which occurs The formed tube passes to the seam annealer which heat
immediately the two skelp edges are closed. treats the weld area (approximately 1650 °F) to recrystal-
lize the material in the heat affected zone. This process
Longitudinal Welding relieves the stresses resulting from the welding process.

The longitudinal weld is made using a high frequency Cooling Station


electrical induction weld system. Heat for the weld is
generated by electrical resistance induced by a coil which The tube is slightly cooled before progressing to the next
encircles the tubing. The heat produced (approximately stage of the manufacturing process.
2500 °F) is confined to a narrow area along the edges of the
closing tube. The final set of forming rollers force the edges Weld Inspection
together at fusion temperature to produce the weld. Since
no filler material is added during the welding process, the Electronic inspection of the seam weld is carried out using
composition of the weld is the same as the body of the tube. an electromagnetic (eddy current) testing system. The
testing station continually records the inspection data and
The tubing is welded slightly oversize with the emphasis on automatically identifies and precisely marks any area that
the weld quality rather than on the final dimension. may require further inspection by magnetic particle testing
and radiography.
Flash Removal
Sizing Stand
A small quantity of weld flash material is extruded on the
inner and outer surfaces of the tube. This is removed from After inspection the tubing is drawn through the sizing mill
the outer surface by a contoured cutting tool located where precisely set rollers form the final string OD.
directly after the welding station. On larger CT sizes (>1-3/
4-in.) the internal weld flash can also be removed if desired.

PHYSICAL PROPERTIES OF 70,000 YIELD STRENGTH MATERIAL

Physical properties: Minimum yield strength: 70,000 psi


Minimum tensile strength: 80,000 psi
Minimum elongation: 30%
Minimum hardness: 22C Rockwell

Figure 6. Physical properties of 70,000 yield strength material

Page 9 of 14
Section 110
COILED TUBING SERVICES MANUAL Schlum berger
Rev A - 98 CT STRING MANUFACTURE Dow ell

Forming stand Longditudinal Flash removal Seam anealling


Strip spool
weld

Water cooling Weld inspection Final sizing Length check

Diameter check Stress relief Air cooling End fitment Weld inspection
welding

Hydro-testing Drift and purge Spooling

Figure 7. CT manufacture - tube forming process.

Length Check Dual Axis Laser

The formed tubing is accurately measured to confirm that A dual axis laser continuously scans the outer surface of
the overall length is that of the required CT string. The the tube to ensure the diameter of the tube is within the
length recorded at this station is considered “string length selected specifications.
as manufactured”.

Page 10 of 14
COILED TUBING SERVICES MANUAL Section 110
Schlum berger
Dow ell CT STRING MANUFACTURE Rev A - 98

Full Body Stress Relief Spooling

The tubing passes through a reheat station where the entire When the CT string is spooled onto a shipping drum the
tube body is heated to between 900 and 1400 °F. The exact string is spooled back to front, i.e., the downhole end of the
heat treatment specifications are carefully controlled to CT string is at the spool core. This ensures the string will
achieve the desired physical characteristics from the be correctly oriented when it is eventually spooled onto the
material being milled. The heat treatment ensures a consis- CT work reel. While this may not be so important for parallel
tent material grain structure throughout the body of the tube strings, it is obviously essential that tapered strings are
and relieves any residual stress induced during manufac- correctly handled and spooled.
ture. The characteristics of the tubing material combined
with the heat treatment at this stage determine the ultimate End Fitment Welding
physical characteristics of the completed CT string (Figure
6). The end fitting, typically a WECO 1502 “wing-half” , is
welded to the string to simplify the spooling (to work reel)
Air Cooling operation. This connection makes up to the corresponding
connection on the reel axle.
In preparation for spooling, the tubing is air cooled over an
interval between the tubing mill and spooling stand.

Nom. Wall Coiled Tubing OD (in.)


Thickness (in.) 1-1/4 1-1/2 1-3/4 2-3/8 2-3/8 3-1/2

0.075 1.000 - - - - -
0.080 1.000 1.1875 - - - -
0.087 0.875 1.1875 - - - -
0.095 0.875 1.1875 1.375 - - -
0.102 0.875 1.1875 1.375 - - -
0.109 0.875 1.1875 1.375 - - -
0.116 0.875 1.1875 1.375 - - -
0.125 0.875 1.125 1.375 2.000 - -
0.134 0.875 1.125 1.375 2.000 - -
0.145 0.875 1.125 1.375 1.875 2.500 -
0.156 0.750 1.0625 1.250 1.875 2.375 -
0.175 0.750 1.0625 1.250 1.875 2.375 3.000
0.190 - 1.000 1.250 1.875 2.375 3.000
0.204 - 1.000 1.250 1.875 2.375 3.000
0.224 - - 1.1875 1.750 2.250 2.875
0.250 - - 1.125 1.750 2.250 2.875
0.280 - - - 1.625 2.188 2.750
0.300 - - - 1.625 2.125 2.750

Figure 8. Recommended CT gauge-ball sizes.

Page 11 of 14
Section 110
COILED TUBING SERVICES MANUAL Schlum berger
Rev A - 98 CT STRING MANUFACTURE Dow ell

Weld Inspection On completion of the pressure testing procedure, the test


fluid is purged from the string using air or nitrogen and an
The end fitting weld undergoes radiographic inspection. internal corrosion inhibitor applied to protect the tubing
Typically, three shots are taken at 120° intervals around during transportation and storage. If the string is to be
the circumference of the weld, offset from the weld centre. delivered or stored in a cold climate, freeze protection may
also be applied to prevent damage from freezing of any
The resulting film is inspected for the following flaws and, residual water/moisture.
on successful conclusion of the checks, placed in the
string file:
2.4 Laboratory Testing
• Gas porosity
Tubing samples taken from the beginning and end of each
• Concavity of the bead mill run are subjected to the following tests or checks.

• Uneven surface of the bead Dimensional Checks

• Surface misalignment Samples are dimensionally checked for:

• Undercut parent material • Ovality

Hydro Testing • Wall thickness

The completed CT string is hydro tested to 90% of the string • Seam-weld mismatch
yield pressure for a minimum of thirty minutes. The test
pressure and duration are recorded on a chart and become Crush Test
part of the permanent string record.
Completely flattens a test section of tubing with the seam
Drifting And Purging weld orientated at the apex of the fold. No open defects are
permitted in the weld.
While the string is being filled with water, a steel gauge ball
of a specified diameter is run through the tubing to ensure
there are no obstructions. Recommended gauge ball sizes
are shown in Figure 8.

Crush Flare Ovality Seam weld Tensile Wall thickness


mismatch

Figure 9. CT string manufacture - laboratory testing.

Page 12 of 14
COILED TUBING SERVICES MANUAL Section 110
Schlum berger
Dow ell CT STRING MANUFACTURE Rev A - 98

Flare Test • Weld log including bias weld and butt weld positions

Stretches the open end of the tubing over a mandrel with a • Hydrostatic test pressure including:
60° taper, the tubing must expand 21% above the initial Test duration
diameter before failure (splitting). Failure should not occur Maximum pressure
at the seam weld. Crush and flare tests are carried out in Minimum pressure
accordance with ASTM A450. Temperature
Test fluid
Tensile Test
• Details of purging/drying or freeze protection procedures
Full section test samples are marked to enable % elonga-
tion to be determined, placed in a tensile test facility. A • Details of drift ball pumping program
tensile load is gradually applied until the sample is tested
to destruction. The resulting data is used to determine: • Record of spooling during the manufacturing and testing
program.
• Yield strength
2.6 Delivery and Spooling
• Ultimate yield strength
On receipt of a new CT string there are several inspection
• Elongation and check procedures necessary before the string is
spooled to the work reel.
2.5 Documentation Package
• Visual inspection of shipping spool and string including:
The documentation package prepared for each tubing Protective crating
string comprises data relating to the string material, manu- Spool hub and handling/mounting points
facturing processes and test or inspection procedures. Not String union/connection for reel core (WECO)
all information contained in the package will be provided General condition of visible wraps
with the string on delivery. However, a complete package
is archived at the tubing mill in the event of subsequent • Review of documentation package/string record, includ-
enquiry. ing:
Confirmation of material order and delivery note
The documentation package should contain the following Confirm the required certification package is complete
information or data.
Prior to spooling, all protective crating and banding is
• Unique string identification number removed from the shipping spool. In addition, any nitrogen
pressure contained within the string for shipping should be
• Tube grade and serial numbers carefully released.

• Chemical composition 2.6.1 Spooling

• Heat number(s) The shipping spool is mounted on a stand which enables


rotation, under a controllable back tension, while the string
• Mechanical properties: is spooled to the work reel. Accurate spooling is essential,
Hardness especially on the reel bed wraps, to ensure no damage is
Tensile strength(s) caused to the string.
Yield strength(s)

• Identification and position of tapered string segments

Page 13 of 14
Section 110
COILED TUBING SERVICES MANUAL Schlum berger
Rev A - 98 CT STRING MANUFACTURE Dow ell

Several checks or inspections should be made at time of


spooling, including:

• Confirm length - at least two independent measuring


devices should be used to confirm the string length.

• OD monitoring - the string should be run through a UTIM


(Universal Tubing Integrity Monitor) to enable a base
record of diameter/ovality to be established.

• Surface protection - application of an external surface


corrosion inhibitor (or similar) should be considered.

• Pressure test - Once the CT string is fully spooled onto the


CT reel, the complete assembly is pressure tested to the
working pressure of the CT string (nominally 5,000 psi)
using water as the testing medium. On completion of the
test the water is completely purged from the string with air
or nitrogen. If the string is to be stored before use, an
internal corrosion inhibitor may be applied.

• String File Record - The documentation package provided


with the string should be used to start the string file or
record. If an electronic string monitoring and recording
system is used, the string details should be entered.

Page 14 of 14

You might also like