You are on page 1of 6

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/271826154

Power system stability using decentralized under frequency and voltage load
Shedding

Article · July 2014


DOI: 10.1109/PESGM.2014.6939306

CITATIONS READS
16 125

3 authors:

Bakhtyar Hoseinzadeh Filipe Faria da Silva


Aalborg University Aalborg University
24 PUBLICATIONS   172 CITATIONS    110 PUBLICATIONS   346 CITATIONS   

SEE PROFILE SEE PROFILE

C.L. Bak
Aalborg University
230 PUBLICATIONS   1,688 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

HARMONY - Harmonic Identification, Mitigation and Control in Power Electronics Based Power Systems View project

COBRAcable Research Project View project

All content following this page was uploaded by Bakhtyar Hoseinzadeh on 28 April 2019.

The user has requested enhancement of the downloaded file.


Power System Stability Using Decentralized Under
Frequency and Voltage Load Shedding
Bakhtyar Hoseinzadeh Filipe Faria Da Silva Claus Leth Bak
Aalborg University, Denmark Aalborg University, Denmark Aalborg University, Denmark
Email: bho@et.aau.dk Email: ffs@et.aau.dk Email: clb@et.aau.dk

Abstract—Load shedding (LS) is the last emergency control proposed to calculate the stage time delays. In [4], the fuzzy
action against voltage or frequency instability or even system load model and the first fit heuristic was employed to calculate
blackout. Conventional LS relays, often rely on only frequency the relay settings. Different LS methods including a fixed
data and due to equality of the frequency throughout the
entire power system, there is the possibility of coincidence maximal load to shed and proportionality of shed load to the
operation of relays and perhaps over load shedding. Besides, the ROCOF were investigated in [5].
LS locations are already determined regardless of disturbance The work reported in [6] utilizes Artificial Neural Network
location and may not be adaptive to the event scale and place. (ANN) for directly determining the parameters of the most
This paper addresses the decentralized coordination of Under effective LS scheme considering system stability. The work
Frequency Load Shedding (UFLS) and Under Voltage Load
Shedding (UVLS) schemes in the LS relays instead of independent carried out in [7] addresses the estimation of frequency and
methods. The independent and constant frequency and voltage ROCOF using a non recursive Newton type procedure follow-
stage thresholds are merged to achieve a united and new elliptical ing by determination of the disturbance magnitude, whereas
thresholds. Since in addition to frequency, the voltage drop for estimation of event scale, the inertia constant of the
information is also employed in the new method, the load generators should be known. Additionally, the minimization
curtailment is started from the vicinity of failure point and
radially propagates in the network until not only the frequency of total amount of shed load was not considered in [6].
collapse is completely prevented, but also the frequency settles Selecting of demonstrative operation and incident scenarios
down in the permissible range. Numerical simulations which was considered in layout of 81L UFLS relays in [8]. Large
are carried out in DigSilent PowerFactory software confirm the power systems, to some extend, deal with similar daily pattern
efficiency of proposed methodology to stabilize the power system of load, whereas micro grids experience significantly different
after a severe contingency.
scenarios due to intermittent behavior of renewable energies
Decentralized adaptive under frequency load shedding, un-
[9] and this fact was not considered for traditional relays in
der voltage load shedding.
[3–5], and adaptive relays in [6], [7]. The schemes with single
objective of minimal shed load [8] may lead to a significant
I. I NTRODUCTION
undershoot in frequency.
There are new design and security issues that should be In this paper, each set of independent frequency and voltage
considered in an UVLS scheme and merely relying on UFLS thresholds of UFLS and UVLS schemes are combined to
methods and issuing a relevant control action can not be a obtain a new synthetic threshold set in term of elliptical
remedial countermeasure for a wide range of disturbances boundaries which may be effective to arrest both undervoltage
especially disturbances with under voltage initiating events, and underfrequency initiating disturbances.
since they may not be an appropriate countermeasure for This paper is organized as follows: Section II investigates
voltage collapse situations [1]. the differences in characteristic of the UVLS and UFLS
Serious frequency plunges can happen within a few seconds schemes. The proposed solution to coordinate the frequency
and manual or operator/SCADA (Supervisory Control and and voltage in a new combined LS plan is presented in III.
Data Acquisition) system is generally unable to be fast enough The simulation set up and results are discussed in sections IV
to prevent partial or complete system collapse [2]. Automatic and V, respectively. Finally, the paper is concluded in section
schemes such as decentralized LS methods in which relays VI.
with frequency/voltage measurement are employed, have much
better performance by shedding load blocks at discrete fre- II. T HE C OORDINATION B ETWEEN UVLS AND UFLS
quency or Rate of Change of Frequency (ROCOF) thresholds. According to [2] regarding impacts of voltage variation on
In distributed LS applications, the load curtailment is carried UFLS scheme, a precise perception of the characteristics of
out at the same location of frequency measurement. Therefore, both frequency and voltage collapse is necessary to estab-
the communication system which is accompany with expenses lish a proper and effective coordination between underfre-
of implementation, system reliability reduction and eventually quency and undervoltage tripping schemes. Underfrequency
delays in communication is not needed at all. and undervoltage collapse are to some extend independent
In [3] a hierarchical Genetic Algorithm (GA) technique was incidents and may typically have distinct root causes such
as loss of a huge generation for underfrequency or outage • Hi the inertia time constant of ith generator
of a determinant transmission line for undervoltage collapse. • Seq the equivalent apparent power
Undervoltage event is identified as a local phenomena, whereas • Si the apparent power of ith generator
underfrequency event is classified as a global system incident. • fn the nominal frequency of power system
Generally, voltage collapse influence the frequency profile • df /dt the rate of change of frequency
slightly which may not be sufficient enough to make the un- • l the number of generators
derfrequency schemes to react. Following an underfrequency After a generation outage, the parameters Heq and Seq no
incident, the frequency starts to drop gradually with the event, longer remain constant and their amount of change and conse-
but typically not as fast as undervoltage events [10] due to long quently the resulted error in the active power estimation in (1)
inertia time constants of system generators in conventional will depend on the bulkiness of the lost generator. Therefore,
power systems. in order to obtain the desired accuracy, the terms relevant
Voltage incidents are generally associated with the local lack to the lost generator should be removed from (2). Actually,
of reactive power. A slow voltage drop may come from in the decentralized strategy of emergency control which has
reaching the generator to full capacity of available reactive no communication system between LS relays, it seems pretty
power reserve and a fast voltage decline can be typically difficult or even impossible to distinguish which generator
involved to serious disturbances such as transmission line short has been lost following an unknown disturbance. Thus, the
circuit or loss. Voltage collapse can come to exist in areas dependency of accuracy to the event type in the SFR method
which either the load is supplied by a faraway generation is another drawback which makes it unreliable in practice.
with restricted reactive power support or areas with a low The SFR method may work well for load events, since the
level of local generation and a high portion of motor loads. connectivity of all of the generators to the grid remains intact
Undervoltage events often happen in a shorter range of time and hence, the aforementioned parameters are still same as
in comparison to underfrequency events [10]. before the disturbance, but it can not be a comprehensive and
The UVLS and UFLS plans have different characteristics and reliable solution for a wide range of incidents.
are independently established in power system without any
coordination. Study of UFLS scheme is often carried out using B. The Number of Stages and Amount of Shed Load
the System Frequency Response models (SFRs) [10], [11]. The number of LS steps and the amount of load has to
The effects of voltage changes on the frequency deviation be shed per step are important key factors which should
is not taken into account in these models. Contrariwise, the be carefully determined during the incipient phase of LS
UVLS methods that have been proposed so far for setting procedure. The LS schemes with less steps and thus shedding
of the UVLS relays, do not employ the frequency indices higher amounts of load per each step, are suitable for large
[1]. Combination of both schemes seems to be necessary in scale disturbances, but may cause excessive LS, unnecessary
practice to achieve a more reliable/effective LS scheme. Any interrupt of consumer services and therefore, less profitability
individual use of these indices may lead the power system under small scale load events. In such cases, more steps
toward over load shedding or blackout. Decentralized UVLS with smaller amount of load shed can be more efficient [2].
scheme may be employed to avoid local voltage collapse Contrariwise, insufficient load curtailment in the preliminary
at many substations. By sharing the existing software and stages of LS procedure may lead to an unsuccessful stop of
hardware between both UVLS and UFLS schemes, the UVLS frequency collapse or even system blackout. The amount of
scheme can be implemented in parallel with underfrequency load shed per step is usually associated with the total load
in order to be financially affordable. that should be shed. Regarding to the limited range of step
number, the more the total load to be shed, the more amount
III. P ROPOSED D ECENTRALIZED AND A DAPTIVE UFVLS of load should be shed in each step. The total load shed and
A. Active Power Deficit Estimation the load shed of each step may be defined as below:
The shortage of active power may be estimated using the m P n
P Pdef
SFR method in (1) introduced in section II [11], [12]. The idea Psh = Psh (i, j) , Psh (i, j) = k(i, j). 100 (3)
j=1 i=1
is based on replacing all generation units of large power system
by a single generating unit with equal dynamical behavior to where:
achieve an average frequency response. • Psh the total amount of load shed
• Pdef the active power deficit from (1)
2Heq .Seq df
Pdef = . (1) • m the number of loads which are contributing in LS
fn dt • n the number of steps in relays
l
P l
P • Psh (i, j) the load shed in step i of load j
Seq = Si , Heq = ( Hi .Si )/Seq (2) • k(i, j) the load shed percentage of step i of load j
i=1 i=1
From (3), the Psh can be rewritten as below:
The quantities in (1) and (2) are as below:
m n
• Pdef the active power deficit which should be shed Pdef X X
Psh = . k(i, j) (4)
• Heq the equivalent inertia time constant 100 j=1 i=1
In order to have a proper LS scheme and capture the frequency TABLE I: Frequency and Voltage Thresholds in pu
downfall, the total load shed should be greater or at least equal Boundaries N S1 S2 S3 S4
to the active power deficit as follows:
bf 0.30/60 0.50/60 0.75/60 1.00/60 1.25/60
Psh ≥ Pdef (5) bv 0.050 0.100 0.125 0.150 0.175

Combining of (4) and (5) can yield:


m X
n
X (negative value of both xf and yv ) is the third quarter. Load
k(i, j) ≥ 100 (6)
curtailment in the buses with voltage greater or equal to
j=1 i=1
the value prior the contingency may cause locally reactive
In order to be sure about satisfying the inequality (6) even power shortcoming and exacerbate the situation [2]. Hence, the
under the worst possible cases, one conservative way is to undervoltage aspect of the new scheme also acts as the built-in
assume the minimum value for terms k(i, j) as below: undervoltage block function of conventional relays in order to
k(i, j) = kmin ∀i, j (7) inhibit the malfunction operation of individual underfrequency
relay. Similarly, during the voltage dips which frequency is
By applying (7) in (6), the red line boundary for the load shed still in the normal range, the load release should be avoided
percentage of each step can be determined as: [1]. Therefore, the alloted reign to the LS plan is confined to
the area which in the state angle falls in to the range between
kmin ≥ 100/(m.n) (8)
π + α and 3π/2 − β.
The size of the largest generator or the pick-up capacity of
the interconnecting tie lines in the power system is generally D. Distribution of Shedding Amount
selected as the worst case for estimation of kmin . By alleviation In the large scale power systems which may have thousand
of the strict and conservative assumption in (8) and without of load buses, contribution of all loads in the LS scheme is
sacrificing the system security, the kmin may usually increased not practical [10]. Despite of conventional LS methods, in the
up to 10%. The amount of the load shed in consecutive steps present approach, the LS zone is bounded to a specific area
is usually specified by allotting some portion of the remained in the vicinity of disturbance location [2], [10]. Following
load to be shed in each step. a contingency in the network, the bus voltages inherently
C. Load Shedding Trigger Criteria contain useful information about the location of the event
[11]. The buses nearby the failure point generally experience
The UVLS scheme may be employed as a complementary more voltage drop than the others and the closer they are,
part of UFLS plan in a new combinatorial program in order the more they decrease. Although the frequency decay may
to benefit from both voltage and frequency data. The voltage be same for all load buses to some extend, the magnitude
and frequency information can be measured locally in the LS of voltage drop in load buses can be different depending
relays and may be used as two different state variables in order on their electrical distance to the event location. The buses
to study the dynamical behavior of the power system following with more voltage drop may reach the LS boundaries sooner
an event. The state variables are defined in pu as below: than the others and consequently are shed first. Therefore,
xf = (f − f0 )/f0 , yv = (v − v0 )/v0 (9) during the incipient phase of the LS program, a limited area
in the neighborhood of the incident place is covered and
where f0 and v0 are the nominal frequency and voltage at the discarding some portion of the loads are initiated from this
relay busbar, respectively. By assigning the x axis to xf and reign. If either the frequency, voltage or both continue to
the y axis to yv , the state trajectory can be plotted in the state further decline, the farther loads may gradually get closer to
plane. In the individual conventional UFLS/UVLS schemes, their corresponding elliptical boundaries and fire the related LS
when the frequency/voltage exceeds one of the predetermined step. This deployment may radially propagate in the network
thresholds, some portion of the load is automatically discarded. until not only the frequency and voltage collapse are prevented,
The table (I) indicates the normal reign and the successive but they return back to their permissible values [2].
thresholds for both frequency (bf ) and voltage (bv ) in p.u. One
way to merge the thresholds and make a new combinational IV. T EST S YSTEM
threshold for the new scheme, is to use each set of the
In order to evaluate the superiority of proposed control
thresholds as the focus points of an elliptical boundary as
scheme, the WSCC 3-machine system which is well-known
follows:
as P.M Anderson 9-bus is chosen as case study. The power
(xf /bf )2 + (yv /bv )2 = 1 (10)
system contains of 3 generators, 6 lines, 3 two winding power
In the new LS program, each new step is precisely triggered transformers and 3 loads contributing in the LS plan. The
when the state trajectory crosses the corresponding elliptical static and dynamic data of the test system can be found in [1].
boundary. In addition, the load relief is merely done when the Synchronous generators are equipped with the IEEE standard
frequency/voltage is less than the nominal values. The only governor GOV-IEESGO and automatic voltage regulator AVR-
area in the state plane which meets both above conditions IEEEX1. In order to taking into account of the nonlinear
0.06
1
0.04 1
0.95
0.02

The active power of loads (pu)


0.95 0.9
0
Voltage deviation (pu)

0.85
−0.02
N 0.8
0.9
−0.04
0.5 1 1.5
−0.06
Load A 0.85 Load A
−0.08 Load B S1 Load B
Load C
−0.1 S2 Load C
S3 0.8
−0.12
S4
−0.14
0.75
−0.02 −0.015 −0.01 −0.005 0 0 2 4 6 8 10
Frequency deviation (pu) Time (s)

Fig. 1: The state trajectory of the load buses Fig. 3: The active power of loads

1.02
60
1

59.8 The load voltages (pu) 0.98

0.96 1
Frequency (Hz)

59.6
0.94
59.4 0.95
0.92

59.2 0.9
0.9 Load A
0.88 Load B
59
Load C
0.86 0.85
58.8 0.5 1 1.5
0.84
0 2 4 6 8 10 0 2 4 6 8 10
Time (s) Time (s)

Fig. 2: The grid frequency Fig. 4: The load voltages

behavior of the loads, the voltage dependency of the load ac- deviation which has been defined in (9). The x and y axis
tive power is considered proportional to the voltage deviation show the state variables of xf and yv in pu, respectively. The
(constant current load type) such as discharge lighting and the terms S1 to S4 are standing for the first to forth step of the
cumulative lumped load of many commercial establishments. LS relays. The Fig.1 displays the state trajectory of the loads
Furthermore, it is assumed that the reactive power of the loads A to C. Following the G3 trip at 0.5s, bus voltages fall almost
are changing proportional to the square of the voltage deviation instantly (Fig.1 and Fig.4), whereas frequency is still in the
(constant impedance load type) [11]. normal range in Fig.1. The variation of the voltage is always
much larger and faster than the frequency changes [10]. The
V. S IMULATION R ESULTS AND D ISCUSSION
state trajectories may intersect the LS boundaries depending on
The numerical simulation is conducted in DIgSILENT the magnitude of the event and as well as the electrical distance
PowerFactory 15.0.2 software. The outage of generator G3 is to the fault location. The distances between the trajectories are
considered as a serious disturbance with the capacity almost due to difference in the voltages. The more drop of load bus
equal to 27% of system load at 0.5s. Figs.1-3 and Tab.II show voltage, the more relevant trajectory far from the origin and
the simulation results throughout 10 seconds of simulation. therefore, crossing the boundaries sooner than the other loads.
Before the contingency at 0.5s, the power system is in the The state trajectory of the load C crosses over the first and
steady state and all of the variables are in the range such as second elliptical boundaries, but the corresponding curve of
the frequency which is equal to 60 Hz (Figs.2-3). In Fig.1, the load B only exceeds the first boundary (Fig.1). Although
the deviation of voltage has been plotted it term of frequency the state curves cut the boundaries and relays detect this
TABLE II: The load shed details indicated in the Tab.II. Supremacy of the proposed LS scheme
Step Load A Load B Load C is obvious in localizing the load curtailment in the vicinity of
event location.
S1 10.4% 18.9% 16.7%
S2 4.1% 4.8% 3.3% VI. C ONCLUSION AND F UTURE W ORKS
Total 14.5% 23.7% 20.0% The conventional LS procedures are merely based on fre-
quency data and may not be an effective and comprehen-
sive solution for widespread range of disturbances especially
event, the relays do not react in this situation which is called for undervoltage initiating events. This study addresses a
undervoltage block level, since this reign has been located decentralized and adaptive approach for LS relays which
in the area which defined with the angle α that discussed in benefits from both locally measured frequency and voltage
details in the end of section III-C. informations. In addition to approximate the shortage of active
After the outage at 0.5s and before the first LS step at power based on ROCOF following a serious contingency, the
1.0s (Tab.II), two different phenomenas with same origin are locally measured voltage in the relay busbar is employed to
noticeable in Figs.4 and 3. First, the voltage drop just after the localize the LS plan in the reigns with higher voltage decay.
generator outage instantaneously affect the active and reactive This research demonstrates that the voltage drop magnitude
power of the loads [11] and hence active power of the loads may be a beneficial criteria of proximity to the event location.
gradually decline due to the voltage dependency of the loads Thus, the UVLS aspect of the proposed UFVLS plan may
which discussed in section IV as can be observed in Fig.3. act as a complementary part of the conventional UFLS plan.
Second, due to the loads active power decrease, the voltages The proposed methodology needs to be evaluated by a bigger
tend to recover toward nominal values to some extend. The power systems, more realistic load divisions and frequency
new upward trend of the voltages causes augmentation of the dependent load models.
active power of the loads again. Although, the effect of the R EFERENCES
voltage deviation on the loads behavior alleviates the shortage
[1] H. Bevrani and A. Tikdari, “An ann-based power system emergency
of the active power, it can not be sufficient to balance the control scheme in the presence of high wind power penetration,” in
load-generation level, thus the power system still suffer from Wind Power Systems. Springer, 2010, pp. 215–254.
active power deficit and frequency continues to decline steadily [2] IEEE, “Ieee guide for the application of protective relays used for
abnormal frequency load shedding and restoration,” IEEE Std C37.117-
(Fig.2). 2007, Power System Relaying Committee, pp. 1–43, 2007.
During the voltage recovery phenomena (Figs.1 and 4), the [3] Y.-Y. Hong and S.-F. Wei, “Multiobjective underfrequency load shedding
load C has the maximum voltage drop and by gradually decline in an autonomous system using hierarchical genetic algorithms,” Power
Delivery, IEEE Transactions on, vol. 25, no. 3, pp. 1355–1362, 2010.
of frequency meets the first checkpoint (S1) sooner than the [4] Y.-Y. Hong and P.-H. Chen, “Genetic-based underfrequency load shed-
other loads. As a result, the first step of load C is triggered at ding in a stand-alone power system considering fuzzy loads,” Power
1.0 s with 16.7% load shed (Tab.II). The first shedding step Delivery, IEEE Transactions on, vol. 27, no. 1, pp. 87–95, 2012.
[5] T. Tomšič, G. Verbič, and F. Gubina, “Revision of the underfrequency
of the load C has a major influence on the state trajectories, load-shedding scheme of the slovenian power system,” Electric power
voltage profile and active power of the loads and it returns the systems research, vol. 77, no. 5, pp. 494–500, 2007.
state variables back into the limited area called S1 boundary. [6] E. J. Thalassinakis, E. N. Dialynas, and D. Agoris, “Method combining
anns and monte carlo simulation for the selection of the load shedding
The relevant voltage and active power jumps are noticeable. protection strategies in autonomous power systems,” Power Systems,
Since the aforementioned shed load is not enough to make a IEEE Transactions on, vol. 21, no. 4, pp. 1574–1582, 2006.
balance between load and generation, the frequency still drops [7] V. V. Terzija, “Adaptive underfrequency load shedding based on the mag-
nitude of the disturbance estimation,” Power Systems, IEEE Transactions
but with a lower value of ROCOF in comparison to before the on, vol. 21, no. 3, pp. 1260–1266, 2006.
first LS step of the load C, thus the state trajectory of the other [8] L. Sigrist, I. Egido, and L. Rouco, “A method for the design of
loads get gradually closer to the S1 boundary. The state curve ufls schemes of small isolated power systems,” Power Systems, IEEE
Transactions on, vol. 27, no. 2, pp. 951–958, 2012.
of load B and A meets the first boundary S1 at 1.15 s and [9] B. Hoseinzadeh and Z. Chen, “Intelligent load-frequency control con-
1.17 s with 18.9% and 10.4% of shed load, respectively. The tribution of wind turbine in power system stability,” EUROCON, 2013
trigger sequence of relays are visible in Fig.3. The next phase IEEE, pp. 1124–1128, 2013.
[10] J. Tang, J. Liu, F. Ponci, and A. Monti, “Adaptive load shedding
of the shedding steps associated with the second boundary has based on combined frequency and voltage stability assessment using
been demonstrated in Tab.II. synchrophasor measurements,” Power Systems, IEEE Transactions on,
Finally, the frequency reaches the steady state in another oper- vol. 28, no. 2, pp. 2035–2047, 2013.
[11] U. Rudez and R. Mihalic, “Analysis of underfrequency load shedding
ation point greater than the minimum value of the permissible using a frequency gradient,” Power Delivery, IEEE Transactions on,
range. In the steady state, the state variables revert to the vol. 26, no. 2, pp. 565–575, 2011.
normal elliptical boundary N as mentioned in Fig.1 and Tab.I. [12] ——, “Monitoring the first frequency derivative to improve adaptive
underfrequency load-shedding schemes,” Power Systems, IEEE Trans-
The maximum shed load of 23.7% is discarded in the load B actions on, vol. 26, no. 2, pp. 839–846, 2011.
(Fig.3) which is one of closest load to the event location. The
second place in term of magnitude of the shed load belongs
to load C with 20.0% and the last place is associated with
load A with minimum amount of shed load about 14.5% as

View publication stats

You might also like