Professional Documents
Culture Documents
August 2017
P. Anthony Hanson
TN PE License # 22642
Power Transformer Procurement Contract No: 6457-P1
Lenoir City Utilities Board Date: August 28, 2017
Watt Road Substation Rev.: 00
TABLE OF CONTENTS
Exhibit B – STD008 – Power Transformer Tank, Arrestor, and Neutral Grounding Details
REVISION HISTORY
B. Proposals must be clearly marked as bids and include “Bid for Power Transformer for Watt
Road Substation” on the exterior of the mailing package.
C. No bidder may withdraw a bid for a period of ninety (90) days after the date set for opening of bids.
B. Quoted prices shall be FOB at the transformer pad at the substation site. Freight shall be allowed
and pre-paid. Seller has the responsibility of Goods during shipment. Title to the Goods and risk of
loss or damage shall remain with the Seller until the transformer is erected in acceptable condition
at the substation site. Escalated prices are not acceptable.
F. Seller shall provide Certificate of Insurance that lists Buyer and Engineer as additional insureds.
G. Buyer reserves the right to reject any and all bids and to waive any informality in bids. Buyer
reserves the right to award the bid to the lowest and best Bidder, as determined by the Buyer and
Engineer.
H. The Bidder shall provide all information requested. The Bidder shall take care to complete all
portions of the Bid documents and to provide all required submittals. Failure to comply may result
in the rejection of the bid.
I. If Seller recommends any changes or deviations from the documents, Seller shall describe the
change fully and furnish complete information so that Buyer can make a decision based upon the
alternative information provided. If these specifications call for material, equipment or
manufacturing procedures different from the manufacturer's standard, Seller shall clearly identify
all deviations or substitutions in this bid.
A. Watt Road Substation: 14224 Hickory Creek Rd, Lenoir City, TN 37772
1.04 WARRANTIES
Seller warrants that all materials, equipment, and work furnished pursuant to this contract comply in all
respects with the contract; that they are free from latent and patent defects in design, materials and
workmanship; that they are suitable and adequate for the purposes for which they were designed and for
such other purposes, if any, as are specified in the contract; and that they will give efficient and satisfactory
service under such conditions as may be specified, for a period of five years after their first operation or
use by the Buyer, in actual service, or, if the contract provides for an acceptance test, for a period of five
years after they have passed such test.
Seller shall, at its own expense, repair, replace, transport, and install any materials, equipment, or work or
parts thereof, which prove defective or deficient during the warranty period.
This means that Seller will be responsible during the warranty period for the direct cost of (A) removing
Goods or parts from service; (B) transporting said Goods or parts from substation site to manufacturer or
repair facility and back to the substation site; and (C) reinstalling Goods or parts for service after completing
the required acceptance testing. If, however, it is impractical for Buyer to wait for the manufacturer, Buyer
may perform such work at Seller's expense.
Any materials, equipment, work, or parts thereof, which fail to meet the guarantees or other requirements
of the contract may be rejected; provided, however that if correction of the defects or deficiencies can be
made through minor alterations or replacements of minor parts, and Seller proceeds immediately to
complete such alterations, or to furnish and install such new parts as are necessary to meet the guarantees
or other requirements of the contract, then the materials, equipment, or work shall not be rejected on
account of defects or deficiencies so corrected. Any correction of a defect or deficiency will be guaranteed
for a period of one year after such correction is effected. The correction of defects or deficiencies shall not
operate to extend the time for performance of the contract as specified thereunder or to waive any claim
for damages resulting from delay in performance or from any other cause.
Buyer shall give Seller prompt notice of any breach of this warranty. Operation or use by Buyer of the
materials, equipment or work, or any part thereof shall not constitute a waiver of any of Buyer's rights under
this contract.
The total losses quoted (load + no load) shall be considered guaranteed maximum values. If the test values
exceed those quoted, a penalty equal to the difference between the values times the applicable $ per kW
capitalized costs given above shall be invoked. No adjustment shall be made for losses better than
guaranteed maximums.
1. Items on a single transmittal form pertain to the same section of the Contract Documents; and
2. Items on a single transmittal form are either original submittals or the same number resubmittal.
B. Schedule submittals to expedite furnishing the Goods and coordinate submission of related items.
Submittals via email are preferred. Deliver each submittal to Engineer with copy to Buyer.
1. Address correspondence to Engineer as follows:
Patterson & Dewar Engineers, Inc.
1531 Hunt Club Blvd, Suite 200, Gallatin, TN 37066
Attention: Anthony Hanson
Phone: (615) 838-4197 Email: ahanson@pdengineers.com
2. Address correspondence to Buyer as follows:
Lenoir City Utilities Board
200 Depot Street, Lenoir City, TN 37771
Attention: Jeremy Walden
Phone: (865) 988-0727 Email: jwalden@lcub.com
C. Submit items on sheet size of not less than 8-1/2” by 11” and not more than 24” by 36”. Provide
space for Seller and Engineer review stamps.
D. Number each submittal item consecutively and insert the number in the space provided on the
transmittal form. Assign resubmitted items the same submittal item number as the original with a
suffix of a sequential letter to indicate it is a resubmitted item. For example, the first resubmittal of
submittal item 2 would be number 2A.
F. Revise and resubmit items as required. Identify changes made since previous submittal. Distribute
copies of reviewed submittal items to concerned parties. Instruct parties to promptly report any
inability to comply with provisions.
Where:
“Approved” indicates submittal has been reviewed and appears to be in conformance with
requirements of the Contract Documents. Proceed as shown on the submittal.
“Approved, but make corrections noted” indicates submittal appears to be in conformance with
requirements of the Contract Documents. Incorporate the corrections noted and proceed as
shown on the submittal. No resubmittal is required.
“Revise and Resubmit” indicates submittal does not appear to be in conformance with the
Contract Documents. Engineer's comments will be noted on the submittal or in a separate, cross-
referenced document. Re-check, make necessary revisions and resubmit.
“None – Not Required or Information Only” indicates that the submittal is not called for by the
Contract Documents and that Engineer has not reviewed the material.
B. Prepare a Table of Contents for each volume, with material, equipment, or system description
identified in three parts as follows:
Part 1: Directory, listing names, addresses, and telephone numbers of Engineer, Seller,
subcontractors, and major component suppliers.
1. Drawings
2. Specifications
B. Legibly mark Specifications and record at each “Part 2 - Products” section of the description of
actual equipment and material furnished, including the following:
1. Submit full set of the project record documents to Engineer with claim for final Application for
Payment.
1.12 SHIPMENT
A. Ship the Goods only after receiving written acknowledgment by Buyer of receipt of certified test
reports.
B. Buyer will accept shipments between 8:00 a.m. and 3:00 p.m. local time Monday through Thursday
excluding observed holidays.
E. Accompany each shipment with a packing list of articles included in the shipment.
F. Attach impact recorder to the transformers during transportation periods. Unseal impact recorder
only in presence of Buyer or Engineer.
G. Deliver transformer oil to Buyer’s site including all necessary equipment for the oil filling operation.
B. Furnish equipment and personnel to handle Goods by methods to prevent soiling, disfigurement, or
damage.
D. Cover Goods subject to deterioration with impervious sheet covering. Furnish ventilation to avoid
condensation or potential degradation of Goods.
G. Promptly inspect shipments to assure that Goods comply with requirements, quantities are correct,
and Goods are undamaged.
H. Arrange storage of Goods to permit access for inspection. Periodically inspect to assure Goods is
undamaged and is maintained in acceptable conditions.
1.14 PATENTS
The Seller shall at its own expense defend any suit instituted by any party against the Buyer so far as it is
based on the claim that any apparatus or part thereof furnished under this contract or the Buyer's use of
such apparatus or part for the purpose for which it was designed or for such purposes, if any, specified in
this contract constitutes infringement of any United States patent.
The Buyer shall give to the Seller immediate notice in writing of the institution of such suit, and shall permit
the Seller, through its counsel, to defend the same, and shall give all requisite authority and all needed and
available information and assistance to enable the Seller to do so. The Seller shall pay all damages and
costs finally awarded therein against the Buyer by reason of such infringement, however the Seller shall
not be liable under any compromise made without its consent.
If in any such suit said apparatus or part or such use thereof by the Buyer is held to constitute infringement
and such use is enjoined, the Seller shall at its own expense procure for the Buyer forthwith the right to use
or continue using the said apparatus or part; provided, however, that subject to the Buyer's approval the
Seller may at its sole expense replace said apparatus or part with non-infringing apparatus or parts, or
modify it so that it becomes non-infringing.
Furnish one 161.7-13.2kV 20/26.6/33.3//37.5 MVA power transformer without LTC as specified,
including 5-year warranty, testing, delivering to Watt Road Substation, offloading and assembling
with provision of field services by manufacturer’s field service engineer and furnishing one set of
spare parts.
LUMP SUM BID PRICE:
and ___/100
(Use Words)
and ___/100
(Use Figures)
Quoted prices shall be FOB to the Points of Destination and shall include offloading onto Buyer’s concrete
foundation, assembly on pad, testing, and certification that Goods are ready for energizing. Seller has the
responsibility of Goods during shipment. Freight shall be allowed and pre-paid.
1.03 DELIVERY
A. The time proposed for submittal of approval drawings (ARO) is
1.04 WARRANTY
The proposed warranty period is .
1.05 ACKNOWLEDGEMENTS
A. Bidder acknowledges receipt of addenda as follows:
C. Bidder has inspected site and has developed offloading plan to accommodate existing structures
and agrees to be responsible for offloading at the pad.
C. Method of shipment:
D. Total Weight:
E. Shipping Weight:
J. List spare parts, with net prices shown FOB site, recommended by manufacturer.
Company
Contact
Address
Phone/Email
Issue PO to
Phase V V V
H Winding
X Winding
Transformers in Bank To Transformer From Phase Connected To Transformer From Phase Connected
INSULATION LEVELS
ITEMS
100 % 1.0
110 % 0.8
W Height
W Width
Load Full Load 3/4 Load 1/2 Load 1/4 Load Total Mass
Shipped lb (kg)
Power Transformer Procurement Contract No: 6457-P1
Lenoir City Utilities Board Date: August 28, 2017
Watt Road Substation Rev.: 00
B. Performance Requirements
2. Audible Sound Level: Average A-weighted, measured in accordance with ANSI C57.12.90, not
to exceed:
a. 20 MVA: 73 db
b. 26.6 MVA: 76 db
c. 33.3 MVA: 77 db
d. 37.5 MVA: 77 db
a. Design bushings, connectors, leads, and all auxiliary equipment for continuous full load
duty and for emergency service at 1.4 times the transformer full load current at the ONAF,
ONAF rating for a period of eight hours.
5. All electrical characteristics and mechanical features not herein specified shall be in
accordance with applicable ANSI and NEMA standards.
C. Seismic Performance
2. Transformer(s) shall be designed so there will be neither structural damage nor loss of function
immediately after an earthquake when subject to design seismic loads occurring
simultaneously with dead and normal operation loads.
B. Shop Drawings:
1. Electronic file, containing a 3D model, suitable for opening or importing into AutoCAD 2014 or
later version. Suitable file types are (but not limited to): AutoCAD (.dwg, .dxf), STEP (.stp, .ste,
.step), ACIS (.sat)
2. Outline showing general arrangement, legend, plan, elevation, base details, weights,
dimensions, and gallons of oil with location of center of gravity with and without oil on outline
a. Excitation and ratio correction factor curves for each secondary ratio
6. Nameplate data, including all current transformer taps. Resubmit nameplate drawing after
factory tests with all test data completed.
7. Physical drawings showing equipment arrangement, terminal block locations, cable entrance,
and panel layout
12. Detailed description of procedure for vacuum filling of transformers with insulating oil
1. Design Data:
a. Certified seismic qualification tests and analyses, in accordance with IEEE Std. 693-2005.
b. Certified short circuit withstand test results on units of comparable rating and design.
C. Elevation above sea level: Less than 3,300 feet, National Geodetic Vertical Datum
1.05 WARRANTY
A. Provide five-year manufacturer’s warranty on Goods and Services provided.
1. Overload capabilities: In accordance with ANSI C57.91 and the requirements specified herein.
a. Continuous Ratings:
Bid Item 1:
2. Number of phases: 3
3. Frequency: 60 Hz
5. Primary to secondary impedance: Match existing unit at 9.8% (See Exhibit C for nameplate)
6. Primary winding:
a. Voltage: 161.7-kV
b. Connection: Delta
7. Secondary winding:
a. H winding: 750-kV
b. X winding: 110-kV
c. The hottest spot temperature rise for the 55º C average temperature rise ratings shall not
exceed 65º C. The hottest spot temperature rise for the 65º C average temperature rise
ratings shall not exceed 80º C.
11. Angular phase displacement: per ANSI C57.12.00-2000, Primary to Secondary: 30º lagging
1. Construction: Welded steel plate, liquid tight, with bolted and gasketed manhole on top of tank,
mounted on steel skid base, and suitable for skidding in any direction.
2. Provide with jacking lugs and pulling eyes for lifting or moving along either axis when
completely assembled and oil filled.
3. Mount a fall control ring on the top of each transformer tank to accommodate worker safety
device attachment. Form 4-inch rings from ½ inch diameter rod. Locate so that a worker
wearing a 6.5-foot safety tether can work anywhere on top of the transformer, including the
bushings, while hooked into the fall control ring.
4. Provide with two copper faced ground pads at diagonal corners near base, with two bolt
terminal connectors.
5. Mount separate blocks on both corners of the tank on the high voltage and low voltage sides,
in a vertical line spaced no more than 3-feet apart to support the ground cable loop when
connected to the high voltage surge arresters. See Exhibit B for grounding details.
8. Transformer concrete pad is existing. Transformer shall be sized to utilize existing pad with
dimensions of 15’6” x 12’.
B. Core:
1. Material: Highest quality, non-aging, cold rolled, grain oriented, stress free, thin silicon steel
laminations, with high permeability and low hysteresis loss.
3. Provide each sheet with an insulated surface treatment impervious to hot transformer oil.
4. Carefully assemble, rigidly clamp, and block to prevent deteriorating vibrations, interference with oil
circulation, objectionable noise conditions, and distortions due to short circuit and shipment.
5. Securely ground to the tank at the top of each transformer in a location accessible from
6. Provide with means for properly lifting and moving core assembly when untanked.
C. Windings:
1. Material: Electrolytic copper with high conductivity characteristics, conforming to ASTM B3-74
or B48-68.
2. Provide with thermally upgraded paper insulation system of high dielectric and mechanical
strength, arranged to permit free circulation of oil.
3. Make up, shape, and brace to provide for expansion and contraction due to temperature
changes and to avoid abrasion of insulation.
4. Adequately clamp and brace to prevent distortion or increase in noise above specified limits
due to aging in continuous service at rated operating conditions.
5. The transformer shall be constructed using only power transformer class construction practices
and materials. Only copper, circular windings of disk and/or helical construction are
acceptable. Rectangular windings, oval windings or layered windings are not
acceptable. The core shall be of circular, multistep, cruciform construction.
D. Cooling Equipment:
2. Radiators:
b. Welded construction, with flanged connections and provisions for draining and venting
d. Furnished with oil tight valves at all connections to main tank that will allow removal of
radiators without taking transformers out of service
3. Fans:
b. Provide magnetic motor starter, and protective devices and manual/automatic selector
switch.
d. Provide individual disconnecting means for each fan motor in the form of a weatherproof,
locking plug for each.
a. Automatically controlled by the winding temperature device, provided with air circuit
breaker of suitable rating, automatic starting switches, auxiliary relays, alarm contacts,
select switch for AUTOMATIC/OFF/MANUAL operation and any other necessary devices.
b. Include provisions for SCADA control and status indication of all stages of cooling
equipment by tap changer control and/or transformer monitors.
d. Designed so either stage of cooling equipment can be selected for operation with first stage
forced cooling.
e. Control power transformer, if required, shall have a minimum of 20-percent spare capacity.
E. Transformer Oil:
1. Pure mineral oil obtained by fractional distillation, unmixed with other substances, meeting the
requirements of ASTM D3487
2. Prepared and refined especially for transformer use; free of moisture, acid, alkali, PCBs, and
injurious sulfur compounds
4. Dielectric strength: Not less than 26,000 volts between 1” discs spaced 1/10” apart
5. Oil shall be tested for corrosive sulphur according to ASTM D1275 extended test
6. A bleed tube for gas blanket dew point measurement shall be provided from the gas space to
an elevation of six feet above the base of the transformer.
7. Suitable valves shall be provided to permit purging the gas space and testing the seal on the
tank by admitting dry nitrogen under pressure.
8. Pressure relief device shall be of the mechanical automatic resealing type with alarm contacts.
X 200 cubic foot Nitrogen cylinder mounted less than 2 feet above base.
X Pressure Regulator
X Cylinder Pressure Gauge (w/alarm contacts - 10% volume remaining.
X Transformer Pressure Gauge (with alarm contacts - High & Low wired to main
control cabinet).
Other:
10. The normal transformer tank pressure is to be between plus (+) 1/2 and plus (+) 8 psig.
11. The system gauges, valves, regulators, etc., shall be contained within a separate steel housing
with single handed, lockable access door.
G. Bushings:
a. Type: Interchangeable
7. Neutral Bushing:
2. Leads:
c. Mark leads with permanent sleeve markers to indicate taps and polarity.
b. Accuracy Class:C400
c. Rating Factor: 2
2. Provide with indicating pointer, dial, and means for locking in any position.
4. Provide for capability of withstanding full transformer short circuit current without damage.
5. Configure to prevent leaving a winding open or short circuited when operating handle is in
locked position.
6. Provide with two 2½-percent taps above and two 2½-percent taps below rated voltage.
J. Surge Arresters:
1. Polymer, station class, metal oxide type, Ohio Brass Dynavar PVN or approved equal
2. Rating:
3. Mount 3 arresters on the high voltage side of the tank and 3 arresters on the low voltage side
of the tank in side of LV cabinet.
1. Wiring:
d. All external wiring shall be run in rigid galvanized steel conduits painted to match the
transformer tank.
e. Terminated with crimp type, ring tongue connectors with non-insulated short shanks;
maximum of two terminations per terminal point
i. Internal device and terminal block identification shall be based on the functional device
code and not the physical location of the device. Both may be used, but functional
identification must be present.
2. Terminal Blocks:
a. Provided with bases and barriers molded integrally with brass inserts
e. Installed in sufficient quantity to provide 20-percent minimum spares for each type block
L. Control Cabinet:
4. Doors: Vertically hinged with locking provisions, stainless steel, single-handle, 3-point latching
system (if center support section is utilized, it must be removable for access during wiring.
9. Provide a copper ground bus inside the cabinet suitable for connecting a 2/0 copper cable to
external ground. Ground bus shall be accessible from the front door without disassembly of
components. All connections to ground shall be through the ground bus.
M. Nitrogen Cabinet:
3. Doors: Vertically hinged with locking provisions and single-handle, 3-point latching system.
1. 120/240 VAC single phase for fans, space heaters, and other accessories
1.08 ACCESSORIES
A. Provide power transformer(s) with the following accessories:
1. Sudden pressure relay device 63 Qualitrol model 900 wired to a Qualitrol model 909 seal-in
relay (Device 63x): Main tank 125 VDC control voltage, with separate, isolated alarm and trip
contacts. All items needed for testing the relay mechanism shall be provided with the unit.
Provide two (2) alarm contacts and two (2) trip contacts.
2. Oil level indicator: Magnetic type with low level nonadjustable two (2) 125 VDC alarm contacts
3. Oil temperature indicator: Main tank dial type with adjustable, separate, two (2) 125 VDC
isolated alarm and trip contacts
4. Winding temperature indicator: Four sequential operating contacts, operating from a current
transformer in one phase of the low voltage winding (two contacts for the operation of cooling
equipment, two (2) contacts for alarm, and two (2) contacts for tripping). Indicator shall be
located not less than 5’ or more than 6’ above the base of the transformer, and shall not be
obstructed. Provide RTD input of all three phases to SEL-2414.
5. Cover-mounted, automatic reseal, shielded pressure relief valve device with spring loaded
visual signal flag and two (2) 125 VDC alarm contacts, Qualitrol XPRD. Pipe discharge to level
6. High inert gas-pressure and vacuum gauge with two (2) alarm contacts
7. Low inert gas pressure gauge: Two (2) alarm contacts for nitrogen supply cylinder with contacts
set to activate when cylinder pressure drops below 200 psi
8. Furnish a 120 volt, 100 watt incandescent light fixture with SPST switch and a 120 volt, 20
ampere single phase duplex GFI type receptacle, complete with protective circuit breaker.
10. All indicators shall be located not less than 5’ or more than 6’ above the base of the transformer,
and shall not be obstructed. Liquid temperature and winding temperature indicators shall be
mounted within 1’ of each other.
7. Features:
i. RTD
i. RTD
1.09 FINISHES
A. All external hardware shall be stainless steel.
B. Clean and treat tank interior and exterior surfaces according to manufacturer’s standards.
1. Impulse Test:
c. Do not perform additional impulse tests after the tests have been accepted.
d. After impulse tests are completed, use the average absolute voltage voltmeter method to
measure excitation loss.
2. Winding Impedance
a. Provide impedance test results for positive and zero sequence values of Zps.
a. Use test equipment and general method in accordance with IEEE C57.12.90.
c. Include results of corona test and measured apparent charge level in certified test report.
6. Short-circuit capability: Warrant that the transformers will meet requirements of ANSI
C57.12.00.
9. Temperature rise test for ONAN and maximum load. (Test results from identical unit maybe
accepted by Buyer if adequate documentation is submitted.)
10. Dielectric tests on control devices and wiring per NEMA ICS-1.
a. Low frequency, one minute 2,500 volts to ground dielectric test on secondaries.
b. Provide electronic and printed copies of the results to Buyer and Engineer.
B. Unseal impact recorders and inspect impact recorder tapes in the presence of Buyer and Engineer
immediately upon delivery. Ensure that impact recorders are reinstalled prior to placement on
foundations by Buyer or Buyer’s construction contractor.
1. Perform unloading and re-inspect each impact recorder readings after placement onto
foundations by Buyer’s construction contractor.
2. Perform transformer field assembly. Record shipping gas pressure prior to assembly.
7. Test oil prior to filling and prior to energizing to determine if the dielectric strength is acceptable.
Filter the oil, if necessary. Testing shall be done by an Independent Testing Laboratory.
Results shall be immediately sent to Buyer and Engineer for approval.
9. Test all wiring and components for continuity and megger for insulation resistance.
10. Verify operation of heater, auxiliary, convenience outlet, and light circuits.
11. Provide equipment for and perform vacuum filling of transformer with insulating oil in
accordance with ANSI C57.12.11.
12. Disconnect the main core ground and megger the core insulation resistance. Reconnect the
13. Perform manufacturer’s standard and optional field tests and field test in accordance with ANSI
C57 12.11.8-1980, and submit written results of tests performed, including the following:
14. Perform Sweep Frequency test on unit(s) after assembly and compare to factory results.
15. After field installation is complete, provide certification that transformer(s) ready to be
energized.
EXHIBIT A
Standard Transformer
Information System
Power Transformer
Communication
Transformer Monitor
Input Map
TRANSFORMER MONITORS
INPUT MAP
TRANSFORMER MONITOR #1
OIL LEVEL MAIN TANK TM-1 SEL-2414 IN301
PRESSURE RELIEF DEVICE MAIN TM-1 SEL-2414 IN302
INERT-AIR SYSTEM HP TM-1 SEL-2414 IN303
INERT-AIR SYSTEM LP TM-1 SEL-2414 IN304
INERT-AIR SYSTEM EC TM-1 SEL-2414 IN305
63 SEAL IN RELAY MAIN TANK TM-1 SEL-2414 IN306
LIQUID TEMP. MAIN TANK 95°C TM-1 SEL-2414 IN307
WINDING TEMP. ALARM 105°C TM-1 SEL-2414 IN308
FAN BANK STATUS #1 TM-1 SEL-2414 IN601
FAN BANK STATUS #2 TM-1 SEL-2414 IN602
STATUS
INPUTS FAN STAGE #1 OVERLOAD STATUS TM-1 SEL-2414 IN603
FAN STAGE #2 OVERLOAD STATUS TM-1 SEL-2414 IN604
43-1 AUTO STAGE 1 COOLING TM-1 SEL-2414 IN605
43-1 MANUAL STAGE 1 COOLING TM-1 SEL-2414 IN606
43-2 AUTO STAGE 2 COOLING TM-1 SEL-2414 IN607
43-2 MANUAL STAGE 2 COOLING TM-1 SEL-2414 IN608
LOSS AC TM-2 SEL-2414 IN501
LOSS OF POWER IN STAGE #1 TM-2 SEL-2414 IN502
LOSS OF POWER IN STAGE #2 TM-2 SEL-2414 IN503
LOSS OF POWER IN COOLING CONTROL TM-2 SEL-2414 IN504
LOSS OF DC TM-2 SEL-2414 IN505
A PH WINDING TEMP (IF RTD) or ANALOG IN TM-1 SEL-2414 INTRTD01
ANALOG B PH WINDING TEMP (IF RTD) or ANALOG IN TM-1 SEL-2414 INTRTD02
INPUTS / RTD C PH WINDING TEMP (IF RTD) or ANALOG IN TM-1 SEL-2414 INTRTD03
MAIN TANK OIL TEMP TM-1 SEL-2414 INTRTD04
Power Transformer Procurement Contract No: 6457-P1
Lenoir City Utilities Board Date: August 28, 2017
Watt Road Substation Rev.: 00
EXHIBIT B
Power Transformer
Tank, Arrestor, and Neutral
Grounding Details
Power Transformer Procurement Contract No: 6457-P1
Lenoir City Utilities Board Date: August 28, 2017
Watt Road Substation Rev.: 00
EXHIBIT C
Existing Nameplate
Power Transformer Procurement Contract No: 6457-P1
Lenoir City Utilities Board Date: August 28, 2017
Watt Road Substation Rev.: 00
EXHIBIT D
Substation General
Arrangement