You are on page 1of 9

GAMMON

VER INDIA LIMITED VERSION 1 (SEPT 2014)


GENERAL CONDITIONS OF WORK ORDER

These General Conditions of Work Order shall be read in conjunction with the Special Conditions, if any and shall form an integral and binding part of the Work Order placed on the Subcontractor / Piece
Rate Worker (PRW) or the Subcontract Agreement signed with the ‘Subcontractor’ by Gammon India Limited (hereinafter referred to as the Main Contractor or the Company) and collectively referred as
Parties for the execution of the ‘Subcontract Works’ / ‘PRW Works’.

Applicability of these General Conditions shall be as follows:


Section Applicability
Section I & Section II Subcontractor
Section I & Section III PRW
Section IV Equipment Hire
Section V Vehicle Hire

S E CT I O N I
1. DEFINITIONS 1.10 PRW Works: ‘PRW Works’ mean the its rates accepted by the Company and after 3. NOTICES, APPROVALS, CERTIFICATES,
In these General Conditions, the following words work(s) to be executed, items and / or activities deduction of all rebates/debits as per the CONSENTS, DETERMINATIONS, REQUESTS
and expressions shall have the meanings hereby to be carried out and / or services to be Accepted Priced Bill of Quantities of the AND DISCHARGES AND OTHER
assigned to them: performed in accordance with the Work Order Subcontract enclosed with the Letter of Intent or COMMUNICATION
or part(s) thereof as the case may be and shall the Work Order or the Subcontract for the Wherever these Conditions provide for the giving
1.1 Employer: ‘Employer’ means the include all permanent and temporary works or execution and completion of Work fit for the or issuing of any notices, approvals, certificates,
Government/ Government Body/ Company/ extra or additional or altered or substituted purpose including the remedying of defects consents, determinations, requests and
Association of Persons/ Proprietary Firm/ works as required for the performance of the therein in accordance with Clause 10 ‘ The discharges, unless otherwise specified; such
Partnership Firm/ Individual or like as stated / Work Order and urgent measures which in the Scope of Work’ of these Conditions. notices, approvals, certificates, consents,
defined in the Letter of Intent or Work Order or opinion of the Company become necessary 1.17 Subcontractor / PRW’s Equipment: determinations, requests and discharges shall be
Subcontract Agreement and the legal successors during the process of work to obviate any risk of ‘Subcontractor/ PRW’s Equipment’ mean all in writing and the words ‘notify’, ‘approve’,
in title to, or assignees of such person, as accident or failure including the remedying of apparatus, plant, equipment, machinery, ‘certify’, ‘confirm’ ‘determine’, ‘request’ or
notified to the Subcontractor/ PRW from time to defects therein. vehicles, tools, tackles, and other things required ‘discharge’ shall be construed accordingly.
time by the Company. 1.11 Subcontractor: ‘Subcontractor’ means a for the execution and completion of the All communication from the Company to the
1.2 Main Contract: ‘Main Contract’ means the person (i.e. an individual, company, body Subcontract Works fit for the purpose and the Subcontractor/ PRW shall be delivered by hand
Agreement / Contract entered into between the corporate, HUF) or a firm (proprietary or remedying of defects therein and which belong (against receipt), or sent by Registered A. D.
Employer and Gammon India Limited or between partnership) or an Association of Persons (i.e. to and/or is provided by the Subcontractor/ PRW. Post or by courier service or through official
the Employer and Joint Venture in which consortium, a joint venture, or by whatever However, Subcontractor/ PRW’s Equipment electronic mail to the Authorized Officer of the
Gammon India Limited is one of the constituents. nomenclature called) or like whose Offer has excludes Temporary Works, Employer’s and/or the Subcontractor/ PRW as notified by the
1.3 Main Contractor or Company: ‘Main been accepted by the Company and named as Company’s Equipment, if any; Plant, Materials and Subcontractor/ PRW from time to time.
Contractor’ or ‘Company’ means Gammon India Subcontractor in the Letter of Intent or the Work any other things intended to form or forming part All communication from the Subcontractor/ PRW
Limited, having its Registered Office at Gammon Order or the Subcontract and the legal of the Permanent Works. to the Company shall be delivered by hand
House, Veer Savarkar Marg, Prabhadevi, successors in title to this (these) person(s), but 1.18 Subcontractor’s Documents: (against receipt), or sent by Registered A. D.
Mumbai- 400025 and shall deem to mean and not (except with the prior written consent of the ‘Subcontractor’s Documents’ mean the Post or by courier service or through official
include its successors and assigns. Company) any assignee of this (these) calculations, computer programs and other electronic mail as follows:
1.4 Subcontract or Subcontract Agreement: person(s). software, drawings, manuals, models and other a) Day to day communication shall be addressed
‘Subcontract’ or ‘Subcontract Agreement’ means 1.12 Subcontract Works: ‘Subcontract Works’ documents of a technical nature, if any, supplied by to the Authorized Representative of the
the Work Order placed on the Subcontractor or mean the work(s) to be executed, items and / or the Subcontractor under the Work Order / Company at the Project Site.
the Agreement signed with the Subcontractor by activities to be carried out and / or services to be Subcontract. b)Contractual correspondence or notice for claim
the Company for the execution of the specified performed in accordance with the Letter of Intent 1.19 Temporary Works: ‘Temporary Works’ which may involve financial implications either
portion of the scope of the Main Contract or the Work Order or the Subcontract or part(s) mean all temporary works of every kind (other now or at a later date shall be addressed to the
(hereinafter referred as ‘Subcontract Works’) and thereof as the case may be and shall include all than Subcontractor/ PRW’s Equipment) required Authorized Signatory of the Company at its
shall mean and include the Letter of Intent, the permanent and temporary works or extra or on Site for the execution and completion of the Registered Office at Mumbai at the following
Work Order, the Subcontract Agreement, the additional or altered or substituted works as Permanent Works and the remedying of defects address:
Special Conditions of Subcontract, these required for the performance of the Subcontract therein. Gammon India Limited,
General Conditions of Work Order, the and urgent measures which in the opinion of the 1.20 Permanent Works: ‘Permanent Works’ Gammon House,
Specifications of Subcontract, the Subcontract Company become necessary during the process mean the permanent works to be executed Veer Savarkar Marg, Prabhadevi,
Drawings, the Accepted Priced Bill of Quantities of work to obviate any risk of accident or failure (including without limitation, all permanent Mumbai 400 025.
of the Subcontract and the further documents, if and shall include completion of the Works fit for structures and all work intended to form a
any, which are listed in the Letter of Intent or the the purpose as per the Main Contract entered in continuing function after completion of the Further it is expressly agreed that no notice as
Work Order or the Subcontract. to between the Employer and the Company Works) in accordance with the Work Order / regards claims, if any, from the Subcontractor/
1.5 Engineer/ Consultant/ Architect: ‘Engineer/ including the remedying of defects therein. Subcontract. PRW which may involve financial implications
Consultant / Architect’ means the Client’s 1.13 Main Contractor’s Engineer: ‘Main 1.21 Applicable Laws: ‘Applicable Laws’ mean all either now or at a later date shall be treated as
Executive Officer or Client’s Consultant or Contractor’s Engineer’ means the ‘Project In laws, brought in to force and effect by Government valid unless the same is served within 14
Architect in charge of the Work. Charge’ of the Main Contractor and/or the of India or the State Government or the local bodies (Fourteen) days of occurrence of the event and
1.6 Company’s Authorized Representative: person specifically appointed and authorized by including rules, regulations and notifications made served to the Authorized Signatory of the
‘Company’s Authorized Representative’ means the Main Contractor to act as Main Contractor’s there under and judgments, decrees, injunctions, Company at its Registered Office in Mumbai and
the Company’s Project In- Charge. Engineer for the purposes of the Work Order / writs and orders of any court of record, applicable to that any notice not served within the above
1.7 Company’s Authorized Signatory: Subcontract or other person appointed from time to this Work Order / Subcontract and the exercise, specified time limit or not served to the
‘Company’s Authorized Signatory’ means the time by the Main Contractor and notified to the performance and discharge of the respective rights Authorized Signatory of the Company at its
Company’s Authorized Officer from its Subcontractor/ PRW. and obligations of the Parties hereunder, as may be Registered Office in Mumbai shall be treated as
Registered Office. 1.14 Specifications: ‘Specifications’ means the in force and effect during the subsistence of this invalid.
1.8 Piece Rate Worker (PRW): ‘Piece Rate document entitled Specifications (shall include Work Order / Subcontract and shall include its 4. LANGUAGE
Worker (PRW)’ means a person i.e. an Technical Specifications with respect to the statutory modifications, amendments, re- The ruling language of the Work Order /
individual, company, body corporate, HUF or a Subcontract Works), as included in the Letter of enactments, consolidations and substitutions as Subcontract including all documents thereof and
firm (proprietary or partnership) or an Association Intent or the Work Order or the Subcontract and may be in force from time to time for all further correspondence between the
of Persons (i.e. consortium, a joint venture, or by any additions or modifications to the Company and the Subcontractor/ PRW shall be
whatever nomenclature called) or like whose Specifications in accordance with the Main 2. INTERPRETATION English.
Offer has been accepted by the Company and Contract and shall include the directions, 2.1 In these Conditions, except where the context 5. GOVERNING LAWS
named as PRW in the Work Order and the legal requirements and provisions furnished or requires otherwise, words imparting the singular The Work Order / Subcontract shall be governed
successors in title to this (these) person(s), but approved in writing by the Main Contractor’s also include the plural and vice versa. by the Laws of India and courts in Mumbai shall
not (except with the prior written consent of the Engineer or the Consultant or the Employer as 2.2 The marginal words and other headings shall have exclusive jurisdiction over all matters
Company) any assignee of this (these) the case may be. Such document specifies the not be taken into consideration in the interpretation arising out of or relating to this Work Order /
person(s). Works. of these Conditions. Subcontract.
1.9 PRW Agreement: ‘PRW Agreement’ means 1.15 Time for Completion: Subcontractor/ 2.3 Any reference to a statutory provision shall Notwithstanding the place where the Work Order/
the Work Order or Agreement signed with the PRW’s ‘Time for Completion’ means the time for include such provision as is from time to time Subcontract is signed or the place where the work
PRW by the Company for the execution of the completing the Subcontract Works fit for the purpose modified or amended or re-enacted or under the Work Order/ Subcontract is to be
specified Scope Of Work as specified in the or a Section/Milestone thereof (as the case may be) consolidated or substituted so far as such executed , it is mutually understood and agreed by
Work Order (hereinafter referred as ‘PRW where Milestone completion dates are stipulated, modification or amendment or re-enactment or and between the Parties hereto, that this Work
Work(s)’) and shall mean and include the Work as stated in the Letter of Intent or the Work Order consolidation or substitution applies or is capable of Order/ Subcontract shall be deemed to have been
Order and/or the PRW Agreement, the Special or the Subcontract and shall always include the applying to any transactions entered into hereunder. entered into by the Parties concerned in the City of
Conditions, these General Conditions, the mobilisation period and monsoon period as well. 2.4 The rule of construction or interpretation, if any, Mumbai.
Specifications of Work Order for PRW, the 1.16 Accepted Subcontract Amount: that a contract should be interpreted against the 6. INDEMNITY
drawings and the further documents, if any, which ‘Accepted Subcontract Amount’ means either the Party/Parties responsible for drafting and preparing The Subcontractor/ PRW hereby indemnifies and
are listed in the Work Order. Lump Sum Amount or the total sum derived from the Contract shall not apply. keeps indemnified and hold harmless the
the multiplication of quantities of such item and Company against and from all claims, actions,
GAMMON
VER INDIA LIMITED VERSION 1 (SEPT 2014)
GENERAL CONDITIONS OF WORK ORDER

suits, demands, liabilities, charges, and any / all 9.7 there are no actions, suits, proceedings, or thereunder shall be entirely to the account of the Testing of equipment, tools, tackles, materials,
proceedings and any/ all losses or damages or investigations pending or, to the Subcontractor/ Subcontractor/ PRW. etc. or preparation of mock ups or trial patches
cost or expenses (including legal fees and PRW’s knowledge, threatened against it under 10 THE SCOPE OF WORK etc. shall be performed by the Subcontractor/
expenses) including third party claims that may the Applicable Laws or in equity before any court The Scope of Work shall be as more particularly PRW at its own costs as per instructions of and to
be suffered, incurred or expected to be so or before any other judicial, quasi-judicial or described in the Letter of Intent or the Work the satisfaction of Company’s Authorized
suffered or incurred by the Company on other authority, the outcome of which individually Order or the Subcontract and shall include all Representative.
account of anything done or omitted to be done by or in the aggregate may result in the breach of or ancillary, connected and incidental works 15. TAXES & DUTIES
the Subcontractor/PRW in connection with this constitute a default of the Subcontractor/ PRW whether explicitly stated or otherwise and shall 15.1 Unless otherwise specified the Accepted
Work Order / Subcontract or any part thereof, the under this Work Order / Subcontract or which mean during the Contract Period and Defect Work Order Amount / Subcontract Amount shall
Works and performance of its obligations, duties, individually or in the aggregate may result in any Liability Period: be inclusive of all taxes, duties, levies, royalties,
responsibilities or liabilities under this Work Order/ material impairment of its ability to perform any 10.1 Construction of all works set forth in the cess, octroi, service tax, etc. with breakup of all
Subcontract or otherwise. of its obligations, duties, responsibilities or Work Order / Subcontract in conformity with the taxes, duties, levies, royalties, cess, octroi,
7. EXCLUSIONS liabilities under this Work Order / Subcontract; Specifications and Standards set forth in the service tax etc. made available.
The Sub Contractor/ PRW has clearly 9.8 there are no actions, suits, proceedings, or Work Order / Subcontract fit for the purpose. 15.2 The Subcontractor shall register itself, as a
understood that the terms and conditions herein investigations pending or, to the Subcontractor/ 10.2 Performance and fulfillment of all other Registered Dealer under ST / Works Contract Tax
contained, has been negotiated by and entered PRW’s knowledge, threatened against it under obligations, duties, responsibilities and liabilities Act and with other relevant authorities in the State
into on behalf of the Company and the Sub the Applicable Laws or in equity before any court of the Subcontractor/ PRW in accordance with where work is to be executed, prior to qualifying
Contractor/ PRW understands and accepts that or before any other judicial, quasi-judicial or the provisions of the Work Order / Subcontract for bidding or within 30 (thirty) days of date of the
the Chairman and Managing Director of the other authority, the outcome of which individually and matters incidental thereto or necessary for Letter of Intent or the Work Order or the
Company or any Director(s) of the Company or or in the aggregate may result in any material the performance of any or all of the obligations, Subcontract and provide their registration
the Chief Operating Officer of the Company has adverse effect on its business, properties or duties, responsibilities and liabilities of the numbers to the Company. Such registration
no part to play in the negotiations and execution assets or its condition, financial or otherwise, or Subcontractor/ PRW under the Work Order / shall remain valid until the expiry of Defects
of these presents and accordingly is not liable at in any material impairment of its ability to perform Subcontract. Liability Period. The Subcontractor shall submit
all in contract, tort or crime in respect of this any of its obligations, duties, responsibilities or 10.3 Execution of all works required to remedy copies of Quarterly tax return, duly certified by a
Work Order / Subcontract or any acts pertaining liabilities under this Work Order / Subcontract; the defects or damage, as may be notified by the qualified, competent and independent Chartered
thereto including prior to its execution. The Sub 9.9 it has no knowledge of any violation or Company on or before the expiry date of the Accountant, showing certified amount billed by it
Contractor/ PRW accordingly undertakes that default with respect to any order, writ, injunction Defects Notification Period for the Works. to the Company during the Quarter under
under no circumstances shall he/it sue and/or or decree of any court or any legally binding consideration as his turnover. The Subcontractor
order of any Government or Government 11. SAFETY shall also submit other documents as necessary
prosecute the Chairman and Managing Director
of the Company, any Director(s) of the Company, Instrumentalities which may result in any material The Subcontractor/ PRW shall: to enable the Company to claim this Turnover as
the Chief Operating Officer of the Company in adverse effect on its ability to perform its (a) comply with all applicable safety regulations, allowable deduction. In case the Subcontractor/
respect of the breach of any terms and obligations, duties, responsibilities or liabilities (b) take care for the safety of all persons entitled PRW is unable to submit copies of Quarterly Tax
conditions herein or in respect of any acts, deeds under this Work Order / Subcontract and no fact to be on the Site, Return and other documents as stated above,
or statements that preceded this Contract and or circumstance exists which may give rise to (c) use reasonable efforts to keep the Site and indirect tax liability arising due to such failure on
pertaining to it. such proceedings that would adversely affect the Works clear of unnecessary obstruction so as the part of the Subcontractor including penalty
8. INSTRUCTIONS IN WRITING performance of its obligations, duties, to avoid danger to these persons, charges, if any, shall be paid by the Subcontractor
responsibilities or liabilities under this Work (d) provide fencing, lighting, guarding and watching to the Company or shall without prejudice to any
Instructions given by the Main Contractor’s
Order / Subcontract; of the Works until completion and taking over, other method of recovery, be deducted by the
Engineer shall be in writing, provided that, if for
9.10 it has complied with the Applicable Laws in (e) provide any Temporary Works (including roadways, Company from any amount due or which may
any reason, the Main Contractor’s Engineer
all material respects and has not been subject to footways, guards and fences) which may be necessary, become due to the Subcontractor or shall be
considers it necessary to give any such
any fines, penalties, injunctive relief or any other because of the execution of the Works, for the use and recovered as a debt. For this purpose, the
instruction orally, the Subcontractor/ PRW shall
civil or criminal liabilities which in the aggregate protection of the public and of owners and occupiers Company shall also have the right to invoke
comply with such instruction. Confirmation in
have or may have a material adverse effect on of adjacent land and Cross Fall Breach and Set Off provisions of
writing of such oral instruction given by the Main
its ability to perform its obligations, duties, (f) strictly comply with the Company’s manual and Clause 24.
Contractor’s Engineer, whether before or after
responsibilities or liabilities under this Work instructions for ‘Safety, Health and Environment’ more 15.3 The Subcontractor/ PRW shall obtain
the carrying out of the instruction, shall be
Order / Subcontract; particularly as stipulated in the relevant Appendix . Service Tax registration as required under section
deemed to be an instruction within the meaning
9.11 no representation or warranty by the 69 of the Finance Act 1994 and also get himself
of this Clause.
Subcontractor/PRW contained herein or in any 12. ENVIRONMENTAL PROTECTION registered with other relevant authorities in the
9. REPRESENTATIONS AND WARRANTIES other document furnished by it to the Company In addition to the strict compliance of all the State where work is to be executed, prior to
The Subcontractor/ PRW represents, warrants or to any Government or Government Applicable Laws and the Company’s Manual and qualifying for bidding or within 30 (thirty) days of
Instrumentalities in relation to applicable permits, instructions for ‘Safety, Health and Environment’; the Letter of Intent or the Work Order or the
and confirms to the Company that:
licenses or approvals contains or will contain any more particularly as stipulated in the relevant Subcontract and provide their registration
9.1 it is duly organised and validly existing under
untrue statement of material fact or omits or will Appendix, the Subcontractor/ PRW shall ensure numbers to the Company. Such registration shall
the Laws of India and has full power and
omit to state a material fact necessary to make and take all required steps to protect the remain valid until the expiry of Defects Liability
authority to execute and perform its obligations
such representation or warranty not misleading; environment (both on and off the Site) and to limit Period.
under this Work Order / Subcontract and to carry
9.12 the Subcontractor/ PRW acknowledges that damage and nuisance to people and property 15.4 If the Subcontractor/ PRW does not have
out the transactions contemplated hereby;
prior to entering in to this Work Order / resulting from pollution, noise and other results of Service Tax number because of his / her taxable
9.2 it has taken all necessary corporate and
Subcontract, the Subcontractor/PRW has, after a its operations. turnover being lower than threshold limits as
other action under the Applicable Laws and its
complete and careful examination, made an The Subcontractor/ PRW shall ensure that specified in Service Tax Rule, 2005 (Registration
constitutional documents to authorize the
independent evaluation of the Work Order / emissions, surface discharges and effluent from of Special Category of Person), the same shall be
execution, delivery and performance of this
Subcontract, the Scope of the Work, the the Subcontractor/ PRW’s activities shall not mentioned on every invoice raised by the
Work Order / Subcontract;
Specifications and the Standards, the drawings, exceed the values stated in the Specification or Subcontractor/ PRW along with aggregate value
9.3 it has the financial standing and capacity to
the Site, local conditions, physical properties/ prescribed by the Applicable Laws. of taxable service till the date of last invoice
undertake the execution of Works
characteristics of ground, subsoil and geology; issued in a Financial Year.
subcontracted to it under this Work Order /
traffic volumes and all information provided by 13. HOUSEKEEPING 15.5 The Subcontractor/ PRW shall submit copies
Subcontract;
9.4 this Work Order / Subcontract constitutes its the Company and has determined to its At all times during the execution of Works, the of quarterly / semiannual returns, ledger accounts
satisfaction the accuracy or otherwise thereof Sub contractor/ PRW shall, at its costs, keep the and other documents required by the Company
legal, valid and binding obligation enforceable
and the nature and extent of difficulties, risks and site reasonably free from all unnecessary from time to time. In case the Subcontractor/
against it in accordance with the terms hereof;
hazards as are likely to arise or may be faced by obstruction and shall arrange storage of materials PRW fails to submit documents as stated above,
and its obligations under this Work Order /
it in the course of performance of its obligations, at site in orderly manner or dispose of any indirect tax liability arising due to such failure on
Subcontract shall be legally valid, binding and
duties, responsibilities or liabilities hereunder. unwanted materials. On substantial completion of the part of the Subcontractor/ PRW including
enforceable obligations against it in accordance
The Subcontractor/ PRW acknowledges and works and upon completion of works or earlier interest & penalty charges, if any, shall be paid by
with the terms hereof;
hereby accepts the risk of inadequacy, mistake determination, the Subcontractor/ PRW shall, at the Subcontractor/ PRW to the Company or shall
9.5 it is subject to the Laws of India, and hereby
or error in or relating to any of the matters set its costs, clear away and remove from site all without prejudice to any other method of recovery,
expressly and irrevocably waives any immunity
forth above and hereby acknowledges and surplus materials, rubbish, debris etc. and leave be deducted by the Company from any amount
in any jurisdiction in respect of this Work Order /
agrees that the Company shall not be liable for the whole of the site and works clean to the due or which may become due to the
Subcontract or matters arising there under
the same in any manner whatsoever to the complete satisfaction of the Company. If the Subcontractor/ PRW or shall be recovered as a
including any obligation, duty, responsibility or
Subcontractor/ PRW or any person claiming Subcontractor/ PRW fails to remove the surplus debt. For this purpose, the Company shall also
liability hereunder;
through or under any of them . materials, rubbish, debris etc., the Company shall have the right to invoke Cross Fall Breach and
9.6 the execution, delivery and performance of
In the event that any of the representations or engage additional manpower to clean the same Set Off provisions of Clause 24.
this Work Order / Subcontract will not conflict
warranties made/given by the Subcontractor/ and the amount so incurred shall, without 15.6 All invoices of the Subcontractor/ PRW shall
with, result in the breach of, constitute a default
PRW ceases to be true or stands changed, it prejudice to any other method of recovery, be be in the form of Tax Invoices and shall be raised
under or accelerate performance required by any
shall be the responsibility of the Subcontractor/ deducted by the Company from any amount due from the State in which the Site is located and
of the terms of the constitutional documents of
PRW to promptly notify the Company of the or which may become due to the Subcontractor/ taxes prevailing shall apply and following them
the Subcontractor/ PRW or any Applicable Laws
same. The Subcontractor/ PRW shall indemnify PRW or shall be recovered as a debt. For this shall be the responsibility and liability of the
or any covenant, contract agreement,
and hold the Company harmless against and purpose, the Company shall also have the right Subcontractor/ PRW. The Subcontractor/ PRW
understanding, decree or order to which it is a
from the consequences of any such failure to to invoke Cross Fall Breach and Set Off shall issue serially numbered Tax Invoice as
party or by which it or any of its properties or
notify the Company and any such failure shall provisions of Clause 24. required under the rule 4A of the Service Tax
assets is bound or affected;
constitute an event of default by the Rules 1994 within prescribed time indicating the
Subcontractor/ PRW and the consequences 14. TESTING : name and address of Service Provider and
GAMMON
VER INDIA LIMITED VERSION 1 (SEPT 2014)
GENERAL CONDITIONS OF WORK ORDER

Service Recipient, the Registration no. (PAN in the areas in which this Work Order/ measurements. All measurements shall be corresponding payment has been received by
based STC No.) of the Subcontractor/ PRW, Subcontract is to be executed. entered in a Measurement Book maintained by the Company from the Employer.
Description of Services, Category under which 17.4 Where neither the Minimum Wages nor fair the Company at site and signed both by the Any Payment by the Company to the
services are provided and details of service tax, wages have been fixed, the Subcontractor/ PRW Company’s Authorized Representative and the Subcontractor/ PRW shall be ‘on Account’
Primary Education Cess & Secondary & Higher shall pay to every employee/ workman wages not Subcontractor/ PRW as a token of acceptance. payment and no payment made by the
Education Cess separately. less than those prevailing in the area for the Company hereunder shall be deemed to
15.7 The Subcontractor/ PRW is fully respective category of employee/ workman, Measurements jointly taken and recorded as constitute acceptance by the Company of the
aware that the activity based service provided by where this Work Order/ Subcontract is to be above shall be the sole, conclusive and final Works or any part thereof.
him/her is pure service contract and the executed. record for payments and payments shall be The Company reserves its right to withhold
Company will have supervision right only for the 17.5 The Company shall not in any manner have made accordingly in full and final settlement of payments due to the Subcontractor/ PRW, if the
quality control purpose and ultimate control over any obligations, responsibilities or liabilities, the dues arising out of this Subcontract/ Work Subcontractor/ PRW has failed to perform in
the work force/ Labours deployed for providing whatsoever, towards any of the Subcontractor Order, inclusive of any interim payments which accordance with this Work Order / Subcontract
the service will always rest with Subcontractor/ /PRW’s Personnel, staff, employees or labour nor may be made to the Subcontractor/ PRW. and/or has failed to remedy the defects to the
PRW. The Subcontractor/ PRW is fully aware that the Company shall entertain any claim from 22. BILLING satisfaction of the Company.
Company is not liable to deposit service tax under Subcontractor/ PRW in this regard. The Subcontractor/ PRW shall submit monthly The Final Payment shall be subject to the Taking
Reverse charge Mechanism as provided under tax invoices to the Company on 5th of every Over Certificate for the Subcontract Works.
section 68(2) of The Finance Act, 1994, as 18. SUBCONTRACTOR / PRW ’S month in triplicate together with detailed joint 26. CLAIMS
services provided by the Subcontractor/ PRW SUPERINTENDENCE measurements, supporting documents and Notice for Claims, if any, shall be served by the
are not Manpower Supply Service. Throughout the execution of the Works, and as Reconciliation statement of materials, if any. Subcontractor/ PRW to Authorized Signatory of
15.8 The Subcontractor/ PRW undertakes to long thereafter as is necessary to fulfill the 23. CASH RETENTION the Company at it’s Registered office in Mumbai
comply with all applicable Tax Laws as in force Subcontractor/ PRW’s obligations, the within 14 (Fourteen) days of the occurrence of
Unless otherwise specified in the Letter of
from time to time and Company shall not be held Subcontractor/ PRW shall provide all necessary the event in accordance with Clause 3. Claims, if
Intent or Work Order or Subcontract, an amount
responsible in any manner whatsoever for the Superintendence to plan, arrange, direct, execute, any, shall be substantiated with supporting
equivalent to 10% (ten percentage) of the gross
Subcontractor/ PRW ’s non-compliance of manage, inspect and test the work. documents along with the statement which shall
value (including escalation payable, if any) of all
various Tax Laws & Rules , being framed from Superintendence shall be given by sufficient state the amount due and payable to the
invoices, running account bill / interim progress
time to time. number of persons having adequate knowledge of Subcontractor/ PRW under this Work Order /
bill shall be deducted from all invoices / running
15.9 In case any statutory levies like labour cess, the operations to be carried out (including the Subcontract.
account / interim progress bills towards Cash
royalties, Works Contract Tax etc. are recovered methods and techniques required, the hazards If the Subcontractor/ PRW do not submit its
Retention.
by the Employer from Company’s Bills on whole likely to be encountered and methods of claim(s) for whatsoever reason within the
The retention money so withheld shall be
of the Contract Value of the Main Contract or in preventing accidents) for the satisfactory and safe stipulated time as above to the Authorized
returned without interest to the Subcontractor/
case such levies are paid by the Company on execution of the Works. Signatory at Registered Office, the same shall be
PRW after completion of Defect Liability Period
whole of the Contract Value of the Main Contract, deemed to be waived.
and Subcontractor/ PRW’s fulfilling all its
proportionate recoveries shall be made by the 19. SUBCONTRACTOR/PRW’S PERSONNEL Notwithstanding any other provision contained
obligations, duties, responsibilities and liabilities
Company from the Subcontractor/ PRW’s The Subcontractor/PRW’s Personnel shall be herein to the contrary or otherwise, no claims of
under this Work Order / Subcontract and signing
invoices. appropriately qualified, skilled, competent, the Subcontractor/ PRW shall be admitted (nor
of ‘No Claim Certificate’ as per the format of the
15.10 Income Tax shall be deducted as experienced and trained in their respective trades deemed to be payable) unless the Employer
Company. In case of failure on the part of the
per the provisions of Income Tax Act, 1961 as or occupations. Prior to posting Key Personnel, admits and pays the corresponding claims of the
Subcontractor/ PRW to remedy the defects, the
applicable from time to time. the Subcontractor/ PRW shall obtain approval or Company.
Company reserves its right to utilize this
15.11 The Subcontractor/ PRW shall have its consent of the Main Contractor’s Engineer. Notwithstanding any other provision contained
retention amount for carrying out the rectification
books of accounts audited by a qualified, However, notwithstanding any such approval or herein to the contrary or otherwise, the
works or discharging obligations, duties,
competent and independent Chartered consent by the Main Contractor’s Engineer or Subcontractor/ PRW shall not be paid any idling
responsibilities or liabilities of the Subcontractor/
Accountant and submit certificate of audit from failure to give approval or consent, the charges whatsoever under whatever
PRW and for this purpose the Company shall
such independent Chartered Accountant. In Subcontractor/ PRW shall remain solely nomenclature called.
also have the right to invoke Cross Fall Breach
addition the Company shall have the right to audit responsible for and shall not be relieved or 27. TAKING OVER OF THE WORKS
and Set Off provisions of Clause 24.
the books of accounts of the Subcontractor/ PRW. absolved in any manner whatsoever of its Until the issuance of Taking Over Certificate for
24. CROSS FALL BREACH AND SET OFF
obligations duties, responsibilities or liabilities the entire Project or in part by the Employer, no
16. LABOUR LAWS under the Work Order / Subcontract and that the The Subcontractor/ PRW shall be bound by the
sections or part thereof done by the
The Subcontractor/ PRW shall comply with all the Company shall not be liable for the same in any terms of this Work Order/ Subcontract as also
Subcontractor/ PRW shall be deemed to be
relevant labour Laws applicable to the manner whatsoever. any and all other Work Orders / Subcontract/
completed or deemed to be accepted or deemed
Subcontractor/ PRW’s personnel, staff, The Main Contractor’s Engineer may require the Agreements / Contracts with the Company. The
to be taken over by the Company.
employees and labour including Laws relating to Subcontractor/PRW to remove (or cause to be breach or default by the Subcontractor/ PRW
28. DEFECT LIABILITY PERIOD
their on-site as well as off-site employment, removed) any person employed on the Site or under any of the Work Orders / Subcontract/
28.1 Unless otherwise specified in the Letter of
health, safety, welfare, immigration and Works, including the Subcontractor/ PRW’s Agreements / Contracts shall be a default under
Intent / Work Order/ Subcontract, Defects
emigration, and shall allow them all their legal Representative, if applicable, who: all the Work Orders / Subcontract/ Agreements /
Liability Period shall be 12 (twelve) months from
rights. The Subcontractor/ PRW shall require its (a) persists in any misconduct or lack of care Contracts and the Company shall have the right
the Date of Completion of Subcontract Works.
employees to obey all Applicable Laws, including (b) carries out duties incompetently or negligently to exercise all rights that it may be entitled to in
The Subcontractor/ PRW, during such period,
those concerning safety at work. The (c) fails to conform with any provisions of the the event of breach or default by the
shall be liable for any defects in the material,
Subcontractor/ PRW shall in relation to the labour Work Order / Subcontract, or Subcontractor/ PRW under any and all the Work
equipment or workmanship and the removal,
employed by him, adhere to the provisions of the (d) persists in any conduct which is prejudicial to Orders / Subcontract/ Agreements / Contracts..
proper rectification / repair and replacement of
Industrial Disputes Act and rules and regulations safety, health, or the protection of the The Subcontractor/ PRW further agrees and
the same as shall be necessary, notwithstanding
made there under and such other Acts, as may be environment. confirms that, the Company shall at all times
any previous tests thereof, if in the opinion of the
applicable. If appropriate, the Subcontractor/ PRW shall; then have the right to deduct or adjust or set off all or
Company the same is not in accordance with
The Subcontractor /PRW shall be liable for appoint (or cause to be appointed) a suitable any monies from any due (s) payable to the
the Work Order / Subcontract. The
paying compensation for any claims arising out of replacement person. Subcontractor/ PRW under this Work Order /
Subcontractor/ PRW shall carry out all the
accidents to his labour under the Indian 20. DELAY DAMAGES Subcontract and/or under any other Work Orders
removal, repairs, rectification and replacement
Workmen’s Compensation Act. The Company / Subcontract/ Agreements / Contracts with the
The Subcontractor/ PRW shall complete the on this account at no extra cost to the Company
shall not be liable for reimbursement of medical Subcontractor/ PRW or any of the account of the
whole of the Works fit for the purpose and each whatsoever.
expenses of the Subcontractor / PRW and / or his Subcontractor/ PRW or any of the Bank
Section/Milestone thereof within the stipulated 28.2 In the event the Subcontractor/ PRW does
labour. Guarantees (i.e. Performance or Advance or
Time for Completion of Works. If the not remedy the defects within a reasonable time,
Retention or Security Deposit) of the
Subcontractor/ PRW fails to complete the Works the Company reserves its right to carry out such
17. RATES OF WAGES AND CONDITIONS OF Subcontractor/ PRW.
or each Section/Milestone thereof within the rectification either on its own or through any
LABOUR AND STAFF 25. PAYMENT
stipulated Time for Completion, the other party at the risk, cost and consequences of
17.1 The Subcontractor / PRW shall be liable and Subcontractor/PRW shall pay Delay Damages to Eligible payment will be released to the the Subcontractor/ PRW as well as recover all
responsible for payment of wages and observing the Company for this default at 0.75% of Subcontractor/ PRW by the Company within 15 costs and losses from the Subcontractor/ PRW
conditions of labour and staff as per the Accepted Subcontract Amount per week beyond (Fifteen) days after receiving corresponding utilizing the retention money and/or invoking any
Applicable Laws and Rules. stipulated Time for Completion subject to payment from the Employer subject to any or all Bank Guarantee (ies), (i.e. Performance or
17.2 The Subcontractor/ PRW shall in maximum of 10% of Accepted Subcontract statutory and other deductions and monies owed Advance or Retention or Security Deposit) and/or
the manner provided by Law, pay to every Amount. by the Subcontractor/ PRW to the Company adjusting against any payments due to the
employee/ workman employed by him in Delay Damages, without prejudice to any other including recoveries against mobilization or plant Subcontractor/ PRW and/or by any other means
connection with this Work Order/ Subcontract, method of recovery, be deducted by the Company advance, if any; interest on mobilization or plant as deemed fit and for this purpose the
wages at rate not less than the minimum rate of from any amount due or which may become due advance, if any; cash retention, security deposit, Company shall also have right to invoke Cross
wages fixed by the appropriate Government, to the Subcontractor/ PRW or shall be recovered deduction of monies due to the Company Fall Breach and Set Off provisions of Clause 24.
under the Minimum Wages Act, for the class of as a debt. For this purpose, the Company shall towards any plant, machinery, materials or 29. NON-PERFORMANCE
employees engaged in the works of similar to the also have the right to invoke Cross Fall Breach services arranged by the Company on behalf of
In case the Subcontractor/ PRW does not
one under the Work Order/ Subcontract. and Set Off provisions of Clause 24. the Subcontractor/ PRW and damages/costs
commence the work or does not mobilize
17.3 Where the Minimum Wages are not fixed, levied by the Company / the Employer, if any.
adequate resources, or does not progress
the Subcontractor/ PRW shall pay to every 21. JOINT MEASUREMENTS: Notwithstanding any other provision contained
satisfactorily, or does not make good shortfall in
employee/ workman wages at a rate not less than The Company’s Authorized Representative in the herein to the contrary or otherwise, no payment
achievement of required progress or does not
the fair wages, prescribed by the authorities presence of the Subcontractor/ PRW or his shall be made to the Subcontractor/ PRW unless
follow safe practices or does not protect the
concerned for this work or works of similar nature Authorized Representative shall take environment or does not maintain quality of work
GAMMON
VER INDIA LIMITED VERSION 1 (SEPT 2014)
GENERAL CONDITIONS OF WORK ORDER

or neglects or does not comply with instructions, Employer or in case of breach of any of the Notwithstanding any other provision contained The work under the Work Order / Subcontract
or do not make payments to their workmen and Representation or Warranties or undertakings or herein to the contrary or otherwise and without shall, if reasonably possible, continue during the
other creditors, or do not comply and observe obligations by the Subcontractor/ PRW or in the prejudice to any other rights and remedies arbitration proceedings.
statutory Laws of the place of work or in case of event of any default by the Subcontractor/ PRW. available to the Company under the Work Order The Arbitrator shall be deemed to have entered
any other form or non-performance by the Upon Termination the Subcontractor/ PRW shall: / Subcontract and the Applicable Laws, no on the reference on the date he issues notice to
Subcontractor/ PRW, then the Company (a) cease all further work, except for such work amount shall be due and payable to the both the Parties fixing the date of the first
reserves its rights to take any or all of the as the Company may specify for the sole Subcontractor/ PRW in case any of hearing. The Arbitrator shall give a separate
following remedial measures (not necessarily in purpose of protecting that part of the Works Subcontractor/ PRW’s breach or default results award in respect of each difference or dispute
the same order) by serving 7 (Seven) day already executed, except those to be in the termination of this Work Order / referred to it.
Notice; at the risk, cost and consequences of assigned to the Company Subcontract and /or the Main Contract. The venue of arbitration shall be Mumbai.
the Subcontractor/ PRW: (b) deliver to the Company, the parts of the The Subcontractor/ PRW undertakes that in the The award of the arbitrator shall be final,
a) Curtail or reduce the Scope Of Work Works executed by the Subcontractor/PRW event of Termination of the Work Order / conclusive and binding on all Parties to this Work
b) Retain the Subcontractor/ PRW’s Equipment up to the date of Termination. Subcontract, the Performance Security shall be Order / Subcontract.
and carry out the balance work in full or in (c) assign to the Company, all right, title and kept valid and subsisting until the expiry of 60 The cost of arbitration shall be borne by the
part (including any rectification in work benefit of the Subcontractor/PRW to the (Sixty) days beyond the Defect Liability Period parties to the dispute, as may be decided by the
already executed by the Subcontractor/ Works as at the date of Termination, and, as from the completion of the entire Works. arbitrator.
PRW) either on its own or through any other may be required by the Company; For this purpose, the Company shall also have Subject as aforesaid, the provisions of the
party at the risk, cost and consequences of (d) deliver to the Company, all Subcontractor/ right to invoke Cross Fall Breach and Set Off Arbitration and Conciliation Act, 1996, or any
the Subcontractor/ PRW as well as recover PRW’s Documents including drawings, provisions of Clause 24. statutory modification or re-enactment thereof
all costs and losses from the Subcontractor/ specifications and standards and other 32. ESCALATION and the rules made thereunder and for the time
PRW documents prepared by the Subcontractor/ Unless otherwise specified in the Letter of Intent being in force shall apply to the arbitration
c) Confiscate Cash Retention money/ Security PRW, if any as at the date of Termination; or the Work Order or the Subcontract’ the proceeding under this Clause.
Deposit No amount shall be due and payable to the Accepted Subcontract Amount shall be firm till
d) Invoke any or all Bank Guarantee (ies) (i.e.
Performance or Advance or Retention or
Subcontractor/ PRW in the event of termination
of the Work Order / Subcontract unless and until
the completion of the Subcontract Works and
shall not be subject to escalation of any kind
********************
Security Deposit).
e) Terminate the Work Order / Subcontract in
the Works as contemplated herein are completed
in entirety, Taking Over Certificate for the entire
whatsoever.
33. DISPUTE RESOLUTION
S E CT I O N I I
accordance with Clause 31. Works have been issued and all payments finally Amicable Settlement
f) Any other method as appropriate for due due on any account to the Company and / or In case of any difference or dispute, both Parties
performance other contractor(s) engaged in respect of the shall attempt to settle the difference or dispute
These General Conditions of Work Order
For this purpose, the Company shall also have outstanding Works have been finally paid and amicably before the commencement of shall be read in conjunction with the
the right to invoke Cross Fall Breach and Set Off settled and the Company has been discharged Arbitration. Special Conditions, if any and shall form
provisions of Clause 24. from all liabilities in respect thereof. On Arbitration Except where otherwise provided for an integral and binding part of the Work
30. STEP IN RIGHTS OF THE COMPANY completion of the outstanding Works by the in the Work Order / Subcontract, all questions Order placed on the Subcontractor or
Notwithstanding any other provision contained Company and / or other contractor(s), the cost, and disputes relating to the meaning of the Subcontract Agreement signed with the
herein to the contrary or otherwise, the expenses, charges (including damages paid to specifications, designs, drawings and ‘Subcontractor’ by Gammon India Limited
Company and the Subcontractor/ PRW agree the Employer) incurred for completing such instructions herein before mentioned and as to
outstanding Works either itself or through other the quality of workmanship or materials used on
(hereinafter referred to as the Main
that, the Company has the right and shall be
entitled to step-in with respect to this Work Order contractor(s), shall be determined and if the the work or as to any other question, claim, right, Contractor or the Company) and
/ Subcontract, in its sole discretion, in aggregate of: matter or thing whatsoever in any way arising out collectively referred as Parties for the
substitution/ replacement of the Subcontractor/ i. The sum which is already paid to the of or relating to the Contract, designs drawings, execution of the ‘Subcontract Works’.
PRW upon the occurrence or non-occurrence of Subcontractor/ PRW under this Work Order / specifications, estimates, instructions, orders or
an event, which in the opinion of the Company, Subcontract; plus the costs, expenses, charges these conditions of otherwise concerning the 1. PRIORITY OF DOCUMENTS
would require such step-in, or in the event of any (including damages paid to the Employer) works, or the execution or failure to execute the The documents forming the Subcontract, listed in
default by the Subcontractor/ PRW or breach of subsequently incurred by the Company in same whether arising during the progress of the the Letter of Intent or the Work Order or the
Representation and Warranties or Suspension or completing the outstanding Works, either itself or work or after the completion or abandonment Subcontract are to be taken as mutually
Termination of this Work Order / Subcontract. through other contractor(s), exceeds the thereof; after written notice by either Party to the explanatory of one another unless otherwise
Furthermore, the Company shall have lien Subcontract Amount (corresponding to the Contract, shall be referred to the sole arbitration provided in the Work Order or the Subcontract.
rights over the Subcontractor/ PRW’s certified work executed by the Subcontractor/ of a person bearing the designation of General For the purposes of interpretation, the priority of
Documents, Equipment and materials. PRW till the date of termination as duly audited Manager or equivalent (or higher designation) of the documents shall be in accordance with the
Notwithstanding any other provision contained by the Auditor of the Company), then the Gammon India Limited to be appointed by the following sequence:
herein to the contrary or otherwise, the Subcontractor/ PRW shall be liable for paying Chairman and Managing Director, Gammon 1.1 The Subcontract Agreement / The Work
Company may enter upon the Site and complete such excess amounts, which is over and above India Limited. Order
the outstanding Works either on its own or the Subcontract Amount (corresponding to the If the person so appointed is unable or unwilling 1.2 The Letter of Intent issued by the
through any other party at the risk, cost and certified work executed by the to act, as the sole arbitrator, some other person Company , if any
consequences of the Subcontractor/ PRW as Subcontractor/PRW till the date of termination as wiling to act as such arbitrator shall be appointed 1.3 The Special Conditions of Work Order /
well as recover all costs and losses from the duly audited by the Auditor of the Company), to by the Chairman and Managing Director, Subcontract, if any
Subcontractor/ PRW. The Company may, to the the Company. The Subcontractor/ PRW Gammon India Limited. 1.4 These General Conditions of Work Order.
exclusion of any right of the Subcontractor/PRW undertakes to pay such amounts within 30 (thirty) There will be no objection if the arbitrator so 1.5 The Specifications of Subcontract (shall
over the same, take over and use without any days of receipt of the demand notice issued by appointed is an employee of Gammon India include Technical Specifications with respect to
payment to the Subcontractor/ PRW any of the the Company. Limited and that he had to deal with the matters the Subcontract Works)
Subcontractor/ PRW’s Equipment as may be ii.the sum which is already paid to the to which the Work Order / Subcontract relates 1.6 The Subcontract Drawings
available on the Site in connection with the Subcontractor/ PRW under this Work Order / and that in the course of his duties with the 1.7 The Priced Bill of Quantities
Works for such period as the Company Subcontract plus the costs, expenses, charges matters as such he had expressed views on all 1.8 Any other document forming part of the
considers expedient for the execution and (including damages paid to the Employer) or any of the matters in dispute or difference. Work Order / Subcontract
completion of the Works. Upon completion of the subsequently incurred by the Company in The arbitrator to whom the matter is originally 1.9 The Request for Qualification cum Proposal
Works or at such earlier date as the Company completing the outstanding Works, either itself or referred being transferred or vacating his office 1.10 The Letter of Proposal / Offer letter of the
deems appropriate, the Company shall inform through other contractor(s), equals the or being unable to act for any reason as Subcontractor
the Subcontractor/ PRW that such Subcontract Amount (corresponding to the aforesaid at the time of such transfer, vacation of If an ambiguity or discrepancy is found in the
Subcontractor/ PRW’s Equipment will be certified work executed by the Subcontractor/ office or inability to act, Chairman and Managing documents, the Main Contractor’s Engineer shall
returned to the Subcontractor/ PRW at the Site. PRW till the date of termination as duly audited Director, Gammon India Limited shall appoint issue any necessary clarification or instruction which
In the event that, Subcontractor/ PRW’s by the Auditor of the Company), then no another person to act as arbitrator in accordance shall prevail.
Equipment is hypothecated or under a lien of any payment shall be due and payable by either with the terms of the Contract. It is also a term of
kind, the Subcontractor/PRW confirms and Party to the other. this Contract that no person other than a person 2. ASSIGNMENT BY THE COMPANY
undertakes to inform and get the prior approvals iii. the sum which is already paid to the appointed by Chairman and Managing Director, The Company may, at any time, assign or transfer;
from its lender(s) with respect to the above Subcontractor/ PRW under this Work Order / Gammon India Limited as aforesaid should act or enter into an agreement to assign or transfer this
provision. Subcontract; plus the costs, expenses, charges as arbitrator and if for any reason, that is not Work Order / Subcontract (in full or in part) or any /
For this purpose, the Company shall also have (including damages paid to the Employer) possible, the matter is not be referred to all of the obligations, duties, responsibilities,
the right to invoke Cross Fall Breach and Set Off subsequently incurred by the Company in arbitration at all. liabilities, rights and benefits in or under the
provisions of Clause 24. completing the outstanding Works, either itself or It is a term of the Work Order / Subcontract that Subcontract to any person without obtaining prior
through other contractor(s), is less than the the Party invoking arbitration shall specify the consent of and/or without any prior intimation to the
31. TERMINATION Subcontract Amount (corresponding to the dispute or disputes to be referred to arbitration Subcontractor. It is hereby clarified that the
Notwithstanding any other provision contained certified work executed by the Subcontractor/ under this Clause together with the amount or Company may, as security in favour of bank or
herein to the contrary or otherwise and without PRW till the date of termination as duly audited amounts claimed in respect of each such financial institution, assign its rights to any money
prejudice to any other rights and remedies by the Auditor of the Company), then the dispute. due or to become due under the Subcontract. The
available to the Company under the Work Order / Company shall pay such amount to the The arbitrator may from time to time with consent Subcontractor hereby agrees and confirms to any
Subcontract and the Applicable Laws, the Subcontractor/ PRW within 30 (thirty) days of of the Parties enlarge the time, for making and Assignment of the Company of its rights and
Company shall be entitled to terminate the Work receipt of the demand notice issued by the publishing the award. obligations to any third party(ies). The
Order / Subcontract, if the Main Contract is Subcontractor/ PRW. Subcontractor concurs and confirms and remains
terminated for any reason whatsoever by the bound by any such Assignment by the Company.
GAMMON
VER INDIA LIMITED VERSION 1 (SEPT 2014)
GENERAL CONDITIONS OF WORK ORDER

period during the subsistence of this Work Order maintain, dismantle, reassemble, adjust and (i) provision of workmen/labour,
3. CONFIDENTIAL DETAILS / Subcontract. repair this part of the Works. Such part shall not (ii) purchase of materials and
All matters related to this Work Order / Subcontract, 6.3 The Subcontractor shall be solely be considered to be completed for the purposes (iii) Transportation of Materials.
the Works and all other documents shall be responsible and undertakes the obligation to of taking-over until these documents and Provided that, appointment of any such
regarded by the Subcontractor as being highly ensure all statutory and legal compliances manuals have been submitted to the Main subcontractor or supplier shall be only with the
confidential and shall not be disclosed to any party, (including but not limited to obligations under all Contractor’s Engineer. However, prior written consent of the Main Contractor’s
person or entity. The Subcontractor shall at no time the labour and industrial Laws). Notwithstanding notwithstanding submission of the above Engineer. The Subcontractor shall submit to the
hereinafter use any technical information or any other provision contained herein to the documents by the Subcontractor or any review Company particulars of its subcontractors or
intellectual property, in relation to this Subcontract contrary or otherwise, all statutory and legal and comments/observations by the Main suppliers it proposes to employ and the extent
and the Main Contract. The Subcontractor shall not compliances shall be sole responsibility and Contractor’s Engineer or failure of the Main of each subcontractor/supplier’s gross order
have the right to advertise or otherwise permit the obligation as well as liability of the Subcontractor. Contractor’s Engineer to review or provide value to enable the Main Contractor’s Engineer
dissemination of publicity concerning this 6.4 In the event of any failure of the comments/observations thereon; the to provide his approval or consent or otherwise.
Subcontract. This Confidentiality obligation shall Subcontractor as regards any of the statutory or Subcontractor shall remain solely responsible Subcontracting of Works in excess of the above
survive expiry or termination of this Work Order / legal compliances, the Subcontractor shall for and shall not be relieved or absolved in any specified limit at any stage of the Project or
Subcontract. indemnify and hold the Company harmless manner whatsoever of its obligations, duties, not obtaining prior written approval or consent
4. NO PRIVITY OF CONTRACT OF THE against and from the consequences of any such responsibilities or liabilities under the Work Order from the Main Contractor’s Engineer shall
SUBCONTRACTOR WITH THE failure and any such failure shall constitute an / Subcontract and that the Company shall not be constitute breach of the Agreement by the
event of default by the Subcontractor and the liable for the same in any manner whatsoever. Subcontractor under the provisions of this Work
EMPLOYER 6.9 The Subcontract shall prepare and submit (in Order / Subcontract. However, notwithstanding
consequences thereunder shall be entirely to the
Nothing herein shall be construed as creating any
account of the Subcontractor. editable soft copies and required number of hard any such submission of the above particulars by
privity of contract between the Subcontractor and
6.5 The Subcontractor after receiving possession copies) resource based Network Program the Subcontractor or any approval or consent or
the Employer. If the Subcontractor commits any (Primavera) together with Resource Schedules for disapproval by the Main Contractor’s Engineer or
of the site or part thereof, ensure that such site
breach of the Work Order / Subcontract, he shall procurement and delivery of Subcontractor’s failure of the Main Contractor’s Engineer to
remains free from all encroachments and take all
indemnify the Company against any damages for Documents, Subcontractor’s Equipment, approve or give consent or otherwise, the
steps necessary to remove encroachments, if
which the Company may become liable under the materials and Subcontractor’s Personnel in Subcontractor shall remain solely responsible
any.
Main Contract as a result of such breaches. In such conformity with the Work Order / Subcontract for and shall not be relieved or absolved in any
an event, the Company shall, without prejudice to 6.6 The Subcontractor shall be fully responsible
for the security and presence on or around or together with other documents including manner whatsoever of its obligations, duties,
any other method of recovery, recover such
entry in or around the project site or any other construction methodology for construction and responsibilities or liabilities under the Subcontract
damages from any amount due or which may commissioning of the Project within the Contract and that the Company shall not be liable for the
become due to the Subcontractor or shall be interference with or affecting the project site or
the execution of the Works by or caused by any Period. same in any manner whatsoever. Further the
recovered as a debt. For this purpose the
protestor or trespasser or for the act, omission, 6.10 The Subcontractor shall submit (in editable Subcontractor shall be responsible for the acts,
Company shall also have the right to invoke defaults, omissions, and neglects of any of its
or default of any such person during the contract soft copies and required number of hard copies)
Cross Fall Breach and Set Off provisions of subcontractor or supplier, their agents, or
period for the land handed over to the details of the arrangements and methods which the
Clause 24 of Section I.
Subcontractor. Any such interference shall not Subcontractor proposes to adopt for the execution of workmen, fully and to the extent as if they were
be a breach of the obligations of the Company to the Works. No significant alteration to these the acts, defaults, omissions, or neglects of
5. PRINCIPAL TO PRINCIPAL provide access to the Project Site. arrangements and methods shall be made without the Subcontractor itself.
It is agreed and understood that, as between the this having previously been notified to the Main 6.14 The Subcontractor shall provide all
6.7 The Subcontractor shall give prompt prior
Main Contractor and the Subcontractor, the legal Contractor’s Engineer. However, notwithstanding Superintendence, Subcontractor’s Documents,
notice to the Company of any error, omission,
relationship is strictly on a principal to principal submission or notification of such details of the Subcontractor’s Equipment, Subcontractor’s
fault or other defect in the design of or the
basis. Nothing is deemed to constitute or imply Specification for the Subcontract Works which it arrangements and methods by the Subcontractor Personnel, materials, goods, consumables and
any other legal relationship such as principal- or any review and comments/observations by the other things and services, whether of a temporary or
may discover when reviewing the Work Order /
agent, master-servant or otherwise. It is Main Contractor’s Engineer or failure of the permanent nature, required in and for this design (to
Subcontract and/or the Main Contract or
expressly agreed that there shall be no principal- Main Contractor’s Engineer to review or provide the extent specified in the Subcontract),
executing the Subcontract Works.
agent, master-servant or any other relationship comments/observations thereon; the execution, completion fit for the purpose and the
6.8 If the Work Order / Subcontract specify that
between the Main Contractor and the the Subcontractor shall design whole or any part Subcontractor shall remain solely responsible remedying of any defects.
Subcontractor under this Work Order/ of the Permanent Works or Temporary Works, for and shall not be relieved or absolved in any 6.15 Notwithstanding the submission of list of
Subcontract and no representation to any such then unless otherwise stated in the Subcontract: manner whatsoever of its obligations, duties, resources proposed to be deployed by the
effect would be made by the Subcontractor to (a) the Subcontractor shall carry out such responsibilities or liabilities under the Work Order Subcontractor, the Subcontractor shall from time
anyone. design himself or through an outsourced agency / Subcontract and that the Company shall not be to time, bring additional resources as required at
The Subcontractor shall indemnify the Main in which case such outsourced agency shall be liable for the same in any manner whatsoever. site to achieve desired rate of progress as also
Contractor against any claims, expenses, from out of the Panel of Agencies approved by 6.11 The Subcontractor shall be responsible for the augment resources, from time to time, to make
liabilities and losses and for any third party adequacy, stability and safety of design (to the good shortfall in progress, if any without any
the Company . However, notwithstanding
claims regarding and/or arising under or in extent specified), all methods of construction and additional costs to the Company .
selection of the outsourced agency from out of
connection with the relationship and/or all Site operations. The Subcontractor shall be 6.16 Any and all materials issued by the
the above Panel, the Subcontractor shall remain
misrepresentation thereby by the Subcontractor. responsible for all Subcontractor’s Documents, Company , if any, to the Subcontractor shall be
solely responsible for and shall not be relieved or
absolved in any manner whatsoever of Subcontractor’s Equipment, Temporary Works, deemed to be in the possession and custody of
6. SUBCONTRACTOR’S GENERAL its obligations, duties, responsibilities or liabilities and such design of each item as is required for the the Subcontractor upon presentation of Material
OBLIGATIONS under the Work Order/ Subcontract and that the item to be in accordance with the Work Order / Issue Note to the Subcontractor.
The Subcontractor’s general obligations, duties, Company shall not be liable for the same in any Subcontract. 6.17 The Subcontractor shall ensure that all
responsibilities and liabilities shall include, but manner whatsoever. Further the Subcontractor 6.12 The Subcontractor shall, with due care and materials issued by the Company, if any shall be
not limited to, the following: shall be responsible for the acts, defaults, diligence, design (to the extent specified in the secured and so stored as to ensure the
6.1 The Subcontractor shall comply with all omissions, and neglects of any of its outsourced Work Order / Subcontract), execute and preservation of the quality and fitness for the
Applicable Laws in the performance of its agencies fully and to the extent as if they were complete the Works fit for the purpose in Works. The Subcontractor shall confirm to all
obligations, duties, responsibilities and liabilities the acts, defaults, omissions, or neglects of accordance with the Work Order / Subcontract applicable national and local safety and other
under this Work Order / Subcontract. the Subcontractor itself. and with the Main Contractor’s Engineer’s codes.
6.2 The Subcontractor shall comply with all (b) the Subcontractor shall submit (in editable instructions and shall remedy any defects in the 6.18 Any and all materials issued by the
applicable permits, licenses and approvals in soft copies and required number of hard copies) Works. The Subcontractor shall execute the Company, if any to the Subcontractor shall be
accordance with Applicable Laws in the the Subcontractor’s Documents, to the Main Subcontract Works as per the terms and used by the Subcontractor only for the purpose
performance of its obligations, duties, Contractor’s Engineer, in accordance with the conditions of the Work Order/ Subcontract, the of and with respect to the Works for which they
responsibilities or liabilities under this Work procedures specified in the Work Order / Drawings, the Bill of Quantities, the are intended and for no other purpose.
Order / Subcontract. The Subcontractor shall Subcontract; Specifications and workmanship as per 6.19 The Subcontractor shall ensure that Plant or
make or cause to be made, necessary (c) these Subcontractor’s Documents shall be in requirements of the Work Order/ Subcontract. Equipment issued by the Company , if any shall
applications to the relevant Government and accordance with the Specification and Drawings, Any modifications / additions/ changes be used with due care and after such use
other Government Instrumentalities with such and shall include additional information required necessary as per the opinion of the Main promptly returned to the Company in working
particulars and details, as may be required for by the Main Contractor’s Engineer to add to the Contractor’s Engineer and/or the Specifications condition.
obtaining all applicable permits, licenses or Drawings for co-ordination of each Party’s shall be conveyed to the Subcontractor in writing 6.20 The Subcontractor shall disclose all
approvals under this Work Order / Subcontract designs; and the same shall be adhered to by the information including confidential information as
and obtain and keep in force and effect all such (d) the Subcontractor shall be fully and solely Subcontractor. The Subcontractor shall not may be reasonably required in order to verify
applicable permits, licenses or approvals in responsible for this design and it shall, when the make any changes, whatsoever, unless compliance with the Work Order / Subcontract
conformity with the Applicable Laws. The Works are completed, be fit for such purposes instructed/ permitted in writing by the Company and allow its proper implementation.
Subcontractor shall, not later than 30 (thirty) for which the same is intended as are specified save and except changes necessary to correct 6.21 The Subcontractor shall not be entitled to
days from the date of the Work Order or date of in the Work Order / Subcontract; and errors or omissions. assign this Work Order / Subcontract or the
execution of the Subcontract, obtain all such (e) prior to the commencement of the Tests on 6.13 The Subcontractor may take up the rights, benefits and obligations hereunder save
applicable permits, licenses or approvals of this Completion, the Subcontractor shall submit (in execution of the Works itself or be entitled, in and except with prior written consent of the
Work Order / Subcontract unconditionally or if editable soft copies and required number of hard turn, to engage its subcontractors to undertake Company.
subject to conditions then all such conditions copies) the ‘as-built’ documents to the Main the execution of the Works; subject to aggregate 6.22 The Subcontractor shall, in the event of
shall have been satisfied in full and such Contractor’s Engineer and, if applicable, sum of all such subcontracted works by it shall termination of the Work Order / Subcontract
applicable permits, licenses or approvals shall operation and maintenance manuals in not exceed 25% (Twenty Five Percent) of the during the Contract Period, handover the project
be kept in full force and effect for the relevant accordance with the Specification and in Accepted Subcontract Amount. For the purpose site in the form required by the Company and /or
sufficient detail for the Employer to operate, of this Clause subcontracting will not include the Employer.
GAMMON
VER INDIA LIMITED VERSION 1 (SEPT 2014)
GENERAL CONDITIONS OF WORK ORDER

If required under the Main Contract and/or the commenced. When any document of a technical Subcontractor’s Equipment, materials and omission, negligence, default, or breach of the
Tender document, the Subcontractor shall nature is issued to the Main Contractor’s Subcontractor’s Personnel in conformity with Subcontractor itself or any of its subcontractor or
ensure, provide and comply with any and all Engineer, evidence of the prior approval by the the Work Order /Subcontract supplier or any of their servants or agents
obligations, and additional warranties, Subcontractor itself shall be apparent on the (d) a Variation is instructed (provided such
guarantees and all other requirements document itself. However, notwithstanding (ii) Construction Methodology variation is not capable of execution as
thereunder. submission of the above documents by the simultaneous/parallel activity) except where
Subcontractor or any review and (iii) An ‘S’ curve illustrating anticipated monthly such Variation is necessitated as a
7. PERFORMANCE BANK GUARANTEE comments/observations by the Main Contractor’s and cumulative billing for achieving the consequence of any default or breach of the
7.1 The Subcontractor shall submit, within 7 Engineer or failure of the Main Contractor’s Completion of the Project and each Agreement by the Subcontractor.
(Seven) days from date of Letter of Intent (LOI), Engineer to review or provide Section/Milestone thereof as per Scheduled
a Contract Performance Bank Guarantee as comments/observations thereon; the Project Completion Date and on which the 13.4 Any extension of time shall be at the
‘Performance Security’ for the due performance of Subcontractor shall remain solely responsible for actual cumulative progress shall be superimposed discretion of the Company and subject to
the Subcontract for an amount equivalent to 10% and shall not be relieved or absolved in any invocation and continuation of any or all of the
(ten percent) of the Accepted Subcontract Amount, manner whatsoever of its obligations, duties, (iv) A Quality Assurance Plan (QAP) covering all contractual or legal rights of the Company.
with an initial validity up to sixty (60) days beyond responsibilities or liabilities under the Work Order aspects of the work to be adopted for this Works
the end of Defect Liability Period. In case of / Subcontract and that the Company shall not be for effective assurance, control and 13.5 Notwithstanding any other provision
delay in completion of Works, the validity of liable for the same in any manner whatsoever. management of Quality in conformity with the contained herein to the contrary or otherwise, no
Contract Performance Bank Guarantee shall be Specifications extension of time shall be granted (nor deemed
extended for such periods as may be required and 11. APPROVAL OF MAIN to be granted) unless the Main Contractor
notified by the Company. CONTRACTOR/ CONSULTANT/ THE (v) An Environmental Management Plan; receives corresponding extension of time from
7.2 The Contract Performance Bank Guarantee EMPLOYER the Employer.
shall be in the form of an unconditional and (vi) A Safety Management Programme 13.6 Time shall continue to be of the Essence
All Subcontractors’s Documents, Subcontractor’s
irrevocable Bank Guarantee in the format including an Emergency Response Protocol of the Subcontract also to any such extension
Equipment, materials and services to be
provided by the Company. The Contract granted by the Company.
incorporated in or required for the Works and all (vii) A Traffic Diversion & Management Plan, if
Performance Bank Guarantee shall be from a Subcontract Works executed by the
nationalized bank acceptable to the Company.
applicable 14. INSURANCE
Subcontractor and its workmanship shall be The Subcontractor shall insure the Works,
7.3 Without prejudice to any other rights and subject to the approval of the Main Contractor/ (viii) The sequence of all Tests on Completion
remedies available to the Company under the Subcontractor’s Equipment, Materials and
the Consultant/ the Employer. However, specified in the Subcontract. Subcontractor’s Documents for not less than
Work Order / Subcontract and the Applicable notwithstanding such approval by the Main
Laws, the Company shall have the rights to the full reinstatement cost including the costs
Contractor/ the Consultant/ the Employer; the The Main Contractor’s Engineer shall, within 14 of demolition, removal of debris and professional
encash the said Contract Performance Bank Subcontractor shall remain solely responsible (Fourteen) days of the receipt of the Work fees and profit. This insurance shall be effective from
Guarantee any time during the period of its for and shall not be relieved or absolved in any Programme, review the same and convey its the date on which work is proposed to be
validity on demand, without demur, manner whatsoever of its obligations, duties, comments/observations to the Subcontractor commenced at site until the date of issue of the
contestation or protest by the Subcontractor responsibilities or liabilities under the Work Order with a particular reference to the conformity or Performance Certificate for the Works to provide cover
and without assigning any reason. For this / Subcontract and that the Main Contractor shall otherwise with the requirements under the Work for loss or damage for which the Subcontractor is
purpose, the Company shall also have the right not be liable for the same in any manner Order /Subcontract. However, notwithstanding liable arising from a cause occurring prior to the issue
to invoke Cross Fall Breach and Set Off whatsoever. any review and comments/observations by the of the Performance Certificate and for loss or
provisions of Clause 24 of Section I.
Main Contractor’s Engineer on the above damage caused by the Subcontractor in the
12. TIME FOR COMPLETION documents or failure of the Main Contractor’s course of any other operations including under
8 SUFFICIENCY OF THE Time shall be of the Essence of this Work Order Engineer to review or provide Defects Liability. The Subcontractor shall insure the
ACCEPTED SUBCONTRACT AMOUNT /Subcontract. comments/observations thereon, the Subcontractor’s Equipment for not less than the
The Accepted Subcontract Amount shall cover Subcontractor shall remain solely responsible full replacement value, including delivery to Site. For
all the obligations, duties, responsibilities or The Subcontractor shall commence the execution of for and shall not be relieved or absolved in any each item of the Subcontractor’s Equipment, the
liabilities of the Subcontractor under the Work the Works within 7 (Seven) days of date of Letter of manner whatsoever of its obligations, duties, insurance shall be effective while it is being
Order / Subcontract and all the things (including Intent or the Work Order or the Subcontract and responsibilities or liabilities under the Work Order transported to the Site and until it is no longer
all incidental and connected things whether shall proceed with the Works with due expedition /Subcontract and that the Main Contractor shall required as the Subcontractor’s Equipment.
explicitly mentioned or otherwise) necessary for and without any delay. not be liable for the same in any manner The Subcontractor shall effect and maintain
the proper execution and completion of the The Subcontractor shall complete the whole of the whatsoever. insurance against liability for claims, damages,
Works fit for the purpose and the remedying of Works fit for the purpose and each Section/Milestone losses and expenses (including legal fees and
any defects. thereof, if any, within the Time for Completion specified 13. EXTENSION OF TIME FOR expenses) arising from injury, sickness, disease or
The Subcontractor shall be deemed to have for the Works or Section/Milestone thereof, as the death of any person employed by the Subcontractor
satisfied itself as to the correctness and
COMPLETION
case may be, including: or any other of the Subcontractor’s Personnel.
sufficiency of the Accepted Subcontract Amount (a) Achieving the passing of the Tests on The insurance shall be maintained in full force and
and deemed to have based the Accepted 13.1 In the event of any delay, the Subcontractor
Completion, and shall at all times ensure that: effect during the whole time that these personnel
Subcontract Amount on the data, interpretations, are assisting in the execution of the Works.
necessary information, inspections, examinations (b) Completing all work which is stated a) it uses and continues to use all reasonable
and satisfaction as to all relevant matters. in the Work Order /Subcontract as being required endeavors to avoid or reduce the effect of any
for the Works or Section/Milestone thereof to be delay on the completion of the Works or a 15. FORCE MAJURE
considered to be completed for the purposes of Section/Milestone thereof (as the case may be) In this Clause, ‘Force Majeure’ means an exceptional
9. SUBCONTRACTOR’S EQUIPMENT
taking-over where Milestone completion dates are stipulated. event or circumstance:
The Subcontractor shall be responsible for all
The Subcontractor shall submit (in editable soft b) subcontractor or vendor appointed by it shall (a) which is beyond a Party’s control,
Subcontractor’s Equipment. When brought on to
copies and required number of hard copies) to re-programme or adjust their performance for
the Site, Subcontractor’s Equipment shall not be (b) which such Party could not reasonably have
the Main Contractor’s Engineer, within 14 (Fourteen) subcontracted works or services and take
more than (3) years in age, shall be complete in provided against before entering into the
days from the date of Letter of Intent, a detailed measures to avoid or reduce the effect of any
all respects with all accessories and necessary Contract,
Work Programme including Construction delay on the completion of Works or a
spares and shall be in good working condition. (c) which, having arisen, such Party could not
Methodology and other documents. The Section/Milestone thereof (as the case may be)
The Subcontractor shall maintain adequate reasonably have avoided or overcome, and
Subcontractor shall also submit a revised Work where Milestone completion dates are stipulated.
inventory of spares at site all the time. When (d) which is not substantially attributable to the other
Programme, whenever the previous Programme
brought on to the Site, Subcontractor’s Party.
is rendered inconsistent with actual progress or 13.2 The Subcontractor shall not be entitled to
Equipment shall be deemed to be exclusively
with the Subcontractor’s obligations. However, an extension of time in respect of any cause of
intended for the execution of the Subcontract Works. Force Majeure may include, but is not limited to,
submission of such revised Programme shall delay nor for any period of delay, which by the
The Subcontractor shall not remove from the Site any exceptional events or circumstances of the kind listed
not relieve or absolve the Subcontractor of any exercise of all reasonable endeavours could be
item of Subcontractor’s Equipment without the below, so long as conditions (a) to (d) above are
of its obligations, duties, responsibilities or avoided or reduced (to the extent that such could
written consent of the Main Contractor’s satisfied:
liabilities under the Work Order /Subcontract. have been reduced). The onus of proving that
Engineer. However, no such consent shall be
the Subcontractor has exercised all reasonable (i) war, hostilities (whether war be declared or not),
required for vehicles transporting Goods or
The Works Programme shall include: endeavours, and that despite such endeavours, invasion, act of foreign enemies,
Subcontractor’s Personnel off Site.
the delay could not be avoided or reduced, shall
in all cases rests with the Subcontractor in this (ii) rebellion, terrorism, sabotage by persons
10. QUALITY ASSURANCE (i) A resource based detailed CPM/PERT respect. other than the Subcontractor’s Personnel,
The Subcontractor shall institute a Quality Network Programme in Primavera; revolution, insurrection, military or usurped power,
Assurance System to demonstrate compliance (a) showing the Critical Path and quantities of 13.3 No extension of time shall be granted to the or civil war,
with the requirements of the Work Order / major work items to be performed each Subcontractor except in the following events:
Subcontract. The System shall be in accordance month/week (a) the Contractor is not being given possession (ii) riot, commotion, disorder, strike or lockout
with the details stated in the Work Order (b) the Programme shall not be unbalanced of the Project Site or any part thereof in by persons other than the Subcontractor’s
/Subcontract. The Main Contractor’s Engineer/ and shall be based on the achievement of accordance with requirement and necessity of such Personnel,
the Consultant/ the Employer shall be entitled to outputs calculated and demonstrated in the Project Site or any part thereof
audit any aspect of the System. Details of all method statement to be submitted by the (b) the delay has been caused for a
procedures and compliance documents shall be (iv) munitions of war, explosive materials, ionising
Subcontractor. reason attributable to the Employer
submitted to the Main Contractor’s Engineer radiation or contamination by radio-activity, except
(c) Resource Schedules for procurement and (c) conditions constituting Force Majeure Events;
before each design and execution stage is as may be attributable to the Subcontractor’s use
delivery of Subcontractor’s Documents, except where such delays are due to any act,
GAMMON
VER INDIA LIMITED VERSION 1 (SEPT 2014)
GENERAL CONDITIONS OF WORK ORDER

of such munitions, explosives, radiation or radio- PRW and the consequences thereunder shall be 2. WORKMANSHIP performance of its obligations, duties,
activity, and entirely to the account of the PRW. responsibilities or liabilities under this Work Order
All work shall be in accordance with the or otherwise.
1.5 The PRW after receiving possession of the requirements of the Company’s Authorized
(v) natural catastrophes such as earthquake, Representative and of Client’s Engineer/
hurricane, typhoon or volcanic activity. site or part thereof, ensure that such site remains
free from all encroachments and take all steps Consultant/ Architect and of first class 3. EXCLUSIONS
necessary to remove encroachments, if any. workmanship. No payment shall be made in The Hiring Agency has clearly understood that
If a Party is or will be prevented from performing its respect of work not accepted by the Company’s the terms and conditions herein contained, has
substantial obligations under the Work Order Authorized Representative in charge of the work been negotiated by and entered into on behalf of
/Subcontract by Force Majeure, then it shall give 1.6 The PRW shall be fully responsible for the
security and presence on or around or entry in or even if client has admitted the payment for such the Company and the Hiring Agency
notice to the other Party of the event or works. understands and accepts that the Chairman and
circumstances constituting the Force Majeure and around the project site or any other interference
with or affecting the project site or the execution the Managing Director of the Company, or any
shall specify the obligations, the performance of 3. TIME FOR COMPLETION Director(s) of the Company or the Chief
which is or will be prevented. The notice shall be of the Works by or caused by any protestor or
trespasser or for the act, omission, or default of Operating Officer of the Company has no part to
given within 14 (Fourteen) days after the Party The work shall be completed by the date
any such person during the contract period for play in the negotiations and execution of these
became aware, or should have become aware, of specified in the Work Order. Further at least 20
the land handed over to the PRW. Any such presents and accordingly is not liable at all in
the relevant event or circumstance constituting Force % of the Physical work must be completed in
interference shall not be a breach of the contract, tort or crime in respect of this Work
Majeure. 25% of the time allowed and at least 50 % of
obligations of the Company to provide access to Order or any acts pertaining thereto including
Each Party shall at all times use all reasonable physical work shall be completed within 50% of
the Project Site. prior to its execution. The Hiring Agency
endeavours to minimise any delay in the time allowed.
accordingly undertakes that under no
performance of the Contract as a result of Force The time shall be essence of this Work Order
1.7 The PRW shall, with due care and diligence, circumstances shall he/it sue and/or prosecute
Majeure. and PRW shall observe strict adherence of time
execute and complete the Works fit for the the Chairman and the Managing Director of the
A Party shall give notice to the other Party when it for completion of Works and each milestone
purpose in accordance with the Work Order and Company any Director(s) of the Company, the
ceases to be affected by the Force Majeure. thereof.
with the Main Contractor’s Engineer’s Chief Operating Officer of the Company in
*********************** instructions and shall remedy any defects in the 4. ESTIMATED QUANTITIES:
respect of the breach of any terms and
conditions herein or in respect of any acts, deeds
Works. The PRW shall execute the Subcontract
S E CT I O N I I I Works as per the terms and conditions of the
Work Order, the Drawings, the Bill of Quantities,
The quantities shown in the Work Order are
estimates only and are not guaranteed and may
or statements that preceded this Contract and
pertaining to it.
the Specifications and workmanship as per be increased or decreased by the Company and
These General Conditions of Work Order shall the PRW shall be entitled only to payment for the
requirements of the Work Order. Any 4. CONFIDENTIALITY
be read in conjunction with the Special amount of work actually executed by the PRW /
modifications / additions/ changes necessary as All matters related to this Agreement, the Project
Conditions, if any and shall form an integral and Certified by the Employer / the Company at the
per the opinion of the Main Contractor’s Engineer and all other documents given to the Hiring
binding part of the Work Order placed on the rates accepted in this Work Order and not to any
and/or the Specifications shall be conveyed to Agency shall be regarded by it as being highly
Piece Rate Worker (PRW) by Gammon India compensation or other payments in respect of
the PRW in writing and the same shall be confidential, and shall not be disclosed to any
Limited (hereinafter referred to as the Main such variation in quantities.
adhered to by the PRW. The PRW shall not party, person or entity. The Hiring Agency shall
Contractor or the Company) and collectively
make any changes, whatsoever, unless at no time hereinafter use any technical
referred as Parties for the execution of the Works 5. APPEAL TO COMPANY’S
instructed/ permitted in writing by the Company information or intellectual property, in relation to
awarded to the PRW.
save and except changes necessary to correct this Agreement and the Main Contract. It shall
AUTHORIZED SIGNATORY
errors or omissions. not have the right to advertise, or otherwise
permit, the dissemination of publicity concerning
1. PRW’S GENERAL OBLIGATIONS 1.8 Notwithstanding the submission of list of If the PRW is not satisfied with any instructions this Agreement. This Confidentiality obligation
resources proposed to be deployed by the PRW, or decisions on the part of the Company’s shall survive expiry or termination of this
The PRW’s general obligations, duties, the PRW shall from time to time, bring additional
responsibilities and liabilities shall include, but Authorized Representative in charge of the Agreement.
resources as required at site to achieve desired Work, he may appeal to the Company’s
not limited to, the following: rate of progress as also augment resources, 5. REPRESENTATIONS AND
Authorized Signatory at Registered Office whose
from time to time, to make good shortfall in decision shall be final and binding. WARRANTIES
1.1 The PRW shall comply with all Applicable progress, if any without any additional costs to
Laws in the performance of its obligations, The Hiring Agency represents, warrants and
the Company. confirms to the Company that:
duties, responsibilities and liabilities under this
Work Order. 1.9 Any and all materials issued by the ******************** 5.1 it has understood the requirements
Company, if any, to the PRW shall be deemed to
1.2 The PRW shall comply with all applicable
permits, licenses and approvals in accordance
be in the possession and custody of the PRW
upon presentation of Material Issue Note to the
S E CT I O N I V and application of the Company and accordingly
offering a suitable Equipment on hire for
with Applicable Laws in the performance of its PRW. These General Conditions of Equipment Hire specified and intended purpose and confirms
obligations, duties, responsibilities or liabilities shall be read in conjunction with the Special that it is fit for the purpose specified and
under this Work Order. The PRW shall make or 1.10 The PRW shall ensure that all materials Conditions, if any and shall form an integral and intended by the Company and it confirms that in
cause to be made, necessary applications to the issued by the Company, if any shall be secured binding part of the Work Order placed on the case the Hired Equipment is not up to the
relevant Government and other Government and so stored as to ensure the preservation of Hiring Agency by Gammon India Limited standard required by the Company or not fit for
Instrumentalities with such particulars and the quality and fitness for the Works. The PRW (hereinafter referred to as the Main Contractor or the purpose specified and intended by the
details, as may be required for obtaining all shall confirm to all applicable national and local the Company) and collectively referred as Company, the same shall be replaced forthwith
applicable permits, licenses or approvals under safety and other codes. Parties for providing Equipment on hire (the without any additional costs to the Company.
this Work Order and obtain and keep in force Equipment).
and effect all such applicable permits, licenses or .11 Any and all materials issued by the 5.2 it has the adequate technical
approvals in conformity with the Applicable Laws. Company, if any to the PRW shall be used by the 1. GOVERNING LAWS knowledge and skill, financial capability and
The PRW shall, not later than 30 (thirty) days PRW only for the purpose of and with respect to The Work Order shall be governed by the Laws organizational strength, skilled manpower and
from the date of the Work Order, obtain all such the Works for which they are intended and for no of India and courts in Mumbai shall have ability to perform the agreed Scope of Work
applicable permits, licenses or approvals of this other purpose. exclusive jurisdiction over all matters arising out within the time frame duly meeting quality, safety
Work Order unconditionally or if subject to of or relating to this Work Order. and environment norms stipulated by the
conditions then all such conditions shall have 1.12 The PRW shall ensure that Plant or Notwithstanding the place where the Work Order is Company.
been satisfied in full and such applicable permits, Equipment issued by the Company, if any shall signed or where the work under the Work Order is
licenses or approvals shall be kept in full force be used with due care and after such use to be executed, it is mutually understood and 5.3 it shall adhere to all the statutory
and effect for the relevant period during the promptly returned to the Company in working agreed by and between the Parties hereto, that requirements including laws and rules relating to
subsistence of this Work Order. condition. this Work Order shall be deemed to have been safety and environment applicable while
entered into by the Parties concerned in the City of performing its Scope of Work and agrees that
1.3 The PRW shall be solely responsible and 1.13 The PRW shall disclose all information Mumbai failure or default in compliance with the aforesaid
undertakes the obligation to ensure all statutory including confidential information as may be requirements, if any, shall be treated as breach
and legal compliances (including but not limited reasonably required in order to verify compliance 2. INDEMNITY of the Agreement.
to obligations under all the labour and industrial with the Work Order and allow its proper
Laws). Notwithstanding any other provision The Hiring Agency hereby indemnifies and keeps
implementation. 5.4 it hereby indemnifies the Company
contained herein to the contrary or otherwise, all indemnified and hold harmless the Company
statutory and legal compliances shall be sole against and from all claims, actions, suits, of any matter related to non-compliance of
1.14 The PRW shall, in the event of termination statutory requirements and that the onus shall
responsibility and obligation as well as liability of demands, liabilities, charges, and any / all
of the Work Order during the Contract Period, solely rest with it to resolve any such issues
the PRW. proceedings and any/ all losses or damages or
handover the project site in the form required by directly with the regulatory authorities without
cost or expenses (including legal fees and
the Company and /or the Employer. any recourse to the Company.
1.4 In the event of any failure of the PRW as expenses) including third party claims that may
If required under the Main Contract and/or the
regards any of the statutory or legal be suffered, incurred or expected to be so
Tender document, the PRW shall ensure,
compliances, the PRW shall indemnify and hold suffered or incurred by the Company on 5.5 it shall conduct the periodic testing
provide and comply with any and all obligations,
the Company harmless against and from the account of anything done or omitted to be done by and recalibration of the Equipment as per the
and additional warranties, guarantees and all
consequences of any such failure and any such the Hiring Agency in connection with this Work original Equipment Manufacturer’s instructions.
other requirements thereunder.
failure shall constitute an event of default by the Order or any part thereof, the Works and
GAMMON
VER INDIA LIMITED VERSION 1 (SEPT 2014)
GENERAL CONDITIONS OF WORK ORDER

5.6 it is agreed and understood that, as 12. OPERATION HOURS case, the Equipment consumes more fuel than fronts as per the requirements of the project site
between the Company and the Hiring Agency the The Equipment shall be available for at least 260 the agreed limit, then the excess amount with or as and when required.
legal relationship is strictly on a principal to hours/26 days per month for operation. The 15% of charges shall be deducted from the
principal basis. Nothing is deemed to constitute hours shall be flexible i.e. the Equipment shall be monthly bills raised by the Hiring Agency. If the 25. FORCE MAJEURE
or imply any other legal relationship such as available for work round the clock i.e. 24 hours in Hired Equipment consumes excess fuel regularly
The term “Force Majeure” in this Agreement
principal-agent, master-servant, or otherwise. It a day. Increase in the operation hours beyond for a prolonged period, the Company reserves
would mean and include acts of God, fire,
is expressly agreed that there shall be no 260 hrs., if any, shall be chargeable at the right to terminate the Contract at any point of
casualty, flood, earthquake, strikes or lockouts,
principal-agent, master-servant or any other negotiated rates or rates worked out on pro-rata time.
riots, militancy, insurrections or civil disorder,
relationship between the Company and the basis whichever is lower. During monsoons embargoes or war. If either Party’s performance
Hiring Agency under this Work Order and no (typically June to September), hire charges shall 18. SPARE PARTS, OIL AND LUBRICANTS of obligations under this Agreement is prevented,
representation to any such effect would be made be paid at negotiated rates or for maximum 130 The Hiring Agency shall keep adequate stock of restricted, delayed or interfered with by reason of
by the Hiring Agency to anyone. hours whichever is lower. However, the spare parts & consumables required for repair & Force Majeure, the performance of obligations
Equipment shall be available for work round the maintenance of the Equipment. This shall shall be excused to the extent delayed or
In the event that any of the representations or clock. entirely be the responsibility of the Hiring Agency prevented by such Force Majeure.
warranties made/given by the Hiring Agency and the Company shall not be responsible for
ceases to be true or stands changed, it shall be 13. OPERATOR(S) OF EQUIPMENT AND O the same. However the Company may provide a
the responsibility of the Hiring Agency to 26. COMPETITIVENESS OF HIRE
& M CREW separate space for storing the spare parts.
promptly notify the Company of the same. The
The Hiring Agency shall provide qualified,
CHARGES
Hiring Agency shall indemnify and hold the The Hiring Agency undertakes that it has not
experienced and competent O & M Crew for 19. HAZARDS
Company harmless against and from the supplied/is not supplying the similar Equipment
operating and maintaining the Equipment for The Hiring Agency shall be solely responsible for
consequences of any such failure to notify the at a hire charge(s) which are lower than that
trouble free operation. The personnel employed any and all hazardous materials, hazardous
Company and any such failure shall constitute an offered in the present Agreement in respect of
shall have valid license to operate the Equipment processes, or hazardous procedure with respect
event of default by the Hiring Agency and the any other customer and if it is found at any stage
and shall be capable of carrying out regular to the work in this Work Order and hereby
consequences thereunder shall be entirely to the that the similar Equipment was supplied by the
maintenance and repairs at the site without any indemnifies and keeps indemnified and hold
account of the Hiring Agency. Hiring Agency to any other customer at a lower
delay or hindrances to the ongoing work. The harmless the Company against and from all
6. AGE OF HIRED EQUIPMENT Operator(s) of Equipment engaged by the Hiring hire charge(s), then that very charge(s), with due
claims, demands, liabilities, charges, and any /
The Hired Equipment shall be in excellent Agency shall have a valid Driving License and allowance for elapsed time, shall be applicable to
all proceedings and any/ all losses or damages
Working Condition and also under no shall have driving/ operating experience of not the present Agreement and the difference in the
or cost or expenses (including legal fees and
circumstances shall be more than 5 (Five) years less than 5 (five) years with respect to the same cost shall be refunded by the Hiring Agency to
expenses) including third party claims that may
old. class of the Vehicle/Equipment to drive and the Company.
be suffered, incurred or expected to be so
operate the Vehicle on road and at work site suffered or incurred by the Company on
7. THIRD PARTY INSPECTIONS AND safely and carefully. The notarized copy of the account of anything done or omitted to be done by 27. PAYMENT TERMS
TESTS driving license, the residential address proof, the the Hiring Agency in connection with this Work A monthly Tax Invoice shall be raised by the
signature proof, identification mark and blood Order or any part thereof Hiring Agency for the Hired Equipment and shall
The Hiring Agency shall carry out third party
group for each driver shall be given to the submit the same by the 5th (fifth) day of every
Inspection at its own cost through an approved
Company by the Hiring Agency before such month along with the relevant documents like
agency at the interval agreed between the Hiring
driver(s) / operator(s) is(are) assigned to the
20. REPAIR AND MAINTENANCE
Agency & the Company. Inspection reports / vouchers / log book copy signed by
Vehicle/ Equipment. The Hiring Agency agrees The Hiring Agency shall carry out necessary
Calibration reports for the same shall be representative of both the parties, confirming the
and undertakes to be responsible to ensure that preventive and periodic maintenance as per the
submitted to the Company site office within 5 period of utilization of the Equipment. The
such driver / operator provided for the Vehicle / manufacturer’s requirements. The Hiring Agency
(five) working days of the inspection. Required Company shall verify and settle these invoices
Equipment shall be physically fit for reporting to shall also provide a detailed schedule for
corrective actions, if any, on nonconformance as as per terms stated in the Work Order. No
duty. The driver / operator shall be sober (not carrying out the periodic and preventive
a consequence of the inspection shall be taken interest/penalties shall be paid on delayed
under the influence of any form of intoxication), maintenance to the Company for approval.
within a week failing which the Equipment shall payments, if any.
of a sane mind, aware of his responsibilities and Preventive Maintenance shall be carried out
be deemed to be under breakdown till such time during approved time slots only (e.g. during
shall not have any kind of bad habits. The Hiring
the same is made good by the Hiring Agency. lunch hours or during the night time) so as not to 28. TERMINATION
Agency agrees and undertakes to be responsible
to ensure all of the above and to ensure safety of affect operation schedule. The approval of
8. HOUR METER and be liable for all the persons, third parties, the Preventive Maintenance Schedule by the 28.1 Notwithstanding any other provision
The Hired Equipment shall have an hour meter driver/ operator and the Vehicle /Equipment and Company shall not absolve the Hiring Agency contained herein to the contrary or otherwise and
to accurately record hour meter reading on a of all third party property at all times. from their responsibilities to operate and without prejudice to any other rights and
day-to-day basis. effectively maintain the Equipment. remedies available to the Company under the
Work Order and the Applicable Laws, the
14. SITE ACCOMMODATION Company shall be entitled to terminate the Work
9. MOBILIZATION & DEMOBILIZATION Unless otherwise specified in the Special
21. BREAKDOWN
Order, if the Main Contract is terminated for any
CHARGES Conditions, accommodation of the crew shall be In event of breakdown of the Equipment, the
reason whatsoever by the Employer or in case
arranged by the Hiring Agency. If stated in the Company shall deduct the hire charges at
Unless otherwise specified in the Special of breach of any of the Representation or
Special Conditions, only accommodation may be negotiated rates or rates worked out on pro-rata
Conditions, mobilization and demobilization Warranties or undertakings or obligations by the
provided by the Company to the crew on basis whichever is higher. In case of minor
charges shall be to the account of the Hiring Hiring Agency or in the event of any default by
chargeable basis, if available. For avoidance of breakdown, Equipment shall be repaired within
Agency. Even in cases where mobilization and / the Hiring Agency.
doubt it is clarified that the salary wages, food 24 Hrs. In the event of failure to repair the
or demobilization charges are to the account of
and insurance etc. of the crew shall be provided Equipment without delay or otherwise, the
the Company, the Company shall not be liable
by the Hiring Agency. Company shall hire the Equipment from any
for any mobilization or de-mobilization if the 28.2 If due to reasons attributable to the Hiring
other source at the risk, cost and consequences
Hired Equipment doesn’t perform as per agreed Agency, it is not possible to complete the Work
capacity/terms or not fit for the purpose specified 15. MINIMUM WAGES of the Hiring Agency.
as per the specifications or as per schedule, then
and intended by the Company. The Hiring Agency shall ensure that it shall pay
the Company reserves the right to terminate the
wages not less than payable as per the Minimum 22. EQUIPMENT PERFORMANCE Agreement by serving a 3 (three) day notice. The
Wages Act and labor laws and submit the Overall availability of the Equipment shall not be
10. COMMENCEMENT DATE Hiring Agency shall additionally be liable for all
documentary evidence of payment to the less than 90% of planned hours as per the
This Contract shall be effective from the date cost, risk, expenses, penalties, charges, claims,
Company, periodically. Company schedule. In the event the Company is
when the Equipment reaches specified location delays, compensation, and all such costs that
of the opinion that the Hiring Agency is not might be burdened onto the Company with
of the Company site as also is ready for
operation duly installed, tested and 16. LOG BOOK meeting the required performance criteria, the respect to this Agreement as specified herein.
The Equipment logbook contemporarily Company shall terminate the contract, at its The Hiring Agency shall then not be entitled to
commissioned in presence of authorized
maintained at the site shall be treated as a final discretion by serving 7 (Seven) day notice. The receive any payment and the cost of the
personnel from the Hiring Agency approved by
and conclusive document for time calculation, Company shall also recover damages to the tune substituting party doing / completing such Work
the Company to operate the Equipment. For
which shall be duly signed by operator of the of a sum equal to the amount levied, imposed or shall be reimbursed by the Hiring Agency to the
avoidance of doubt it is clarified that
Hiring Agency and Authorized Representative of recovered from the Company by its Employer Company
mobilization/demobilization period shall not be
the Company. under the Main Contract.
considered as part of hiring period.
29. CROSS FALL BREACH AND SET OFF
11. INSURANCE 17. FUEL 23. DAMAGES FOR DELAY The Hiring Agency shall be bound by the terms
The rates accepted by the Company are In case of any delay in completion of the project of this Work Order as also any and all other
The Hiring Agency shall obtain adequate cover
inclusive of fuel and oil/lubricant charges. Unless for reasons attributable to the Hiring Agency, the Work Orders / Agreements / Contracts with the
for Comprehensive Insurance for the Equipment
otherwise specified in the Special Conditions, Company shall recover damages from the Hiring Company. The breach or default by the Hiring
delivered at the Company site at its own cost
fuel shall be arranged by the Hiring Agency. If Agency of a sum equal to the amount levied, Agency under any of the Work Orders /
including third party insurance and submit
specified in the Special Conditions, Fuel may be imposed, or recovered from the Company by its Agreements / Contracts shall be a default under
documentary evidence thereof to the Company.
provided by the Company on chargeable basis Employer under the Main Contract. all the Work Orders/ Agreements/ Contracts and
The Company shall not be liable for any damage
to the Equipment and/or property, or personnel, upon written request from the Hiring Agency at the Company shall have the right to exercise all
etc. owned or employed by the Company/ its prevailing market rates plus charges of 5%. 24. TRANSFER OF LOCATION rights that it may be entitled to in the event of
Employer/ or any other agencies for whatsoever Upper Limit of Fuel consumption of the The Company shall have rights to change / breach or default by the Hiring Agency under any
reasons. Equipment shall be decided by the Company. In transfer location of the Equipment between work
GAMMON
VER INDIA LIMITED VERSION 1 (SEPT 2014)
GENERAL CONDITIONS OF WORK ORDER

and all the Work Orders / Agreements / Company, any Director(s) of the Company, the 7. MINIMUM WAGES Vehicle within one hour. Such replacement
Contracts. Chief Operating Officer of the Company in vehicle shall be at the cost of the Hiring Agency.
The Hiring Agency further agrees and confirms respect of the breach of any terms and The Hiring Agency shall ensure that it shall pay Charges towards the breakdown period shall be
that, the Company shall at all times have the conditions herein or in respect of any acts, deeds wages not less than payable as per the Minimum deducted at negotiated rates or rates worked out
right to deduct or adjust or set off all or any or statements that preceded this Contract and Wages Act and comply with all obligations under on pro-rata basis whichever is higher. If in the
monies from any due (s) payable to the Hiring pertaining to it. labour laws. The Hiring Agency shall periodically opinion of the Company’s Authorized Person, the
Agency under this Work Order / Subcontract submit the documentary evidence of payments to vehicle suffers frequent breakdown or is not
and/or under any other Work Order(s) or the Company. The Hiring Agency undertakes maintained as per these terms and conditions,
Agreement(s) with the Hiring Agency or any of 3. THE SCOPE and agrees that the relationship between the then the Company shall (at its option) forthwith
the account of the Hiring Agency or any of the Company and the Hiring Agency is on a principal terminate this Work Order.
Bank Guarantees (i.e. Performance or Advance The Hiring Agency shall provide a registered
to principal basis. The Hiring Agency undertakes
or Retention or Security Deposit) of the Hiring motor vehicle which has the necessary permit
and agrees that it is responsible for the full and
Agency. and is registered for use as a passenger contract
timely performance of all legal and statutory 13. LIABILITY IN CASE OF ACCIDENT
carriage/tourist vehicle (the “Vehicle”). The Hiring
compliances. Any non-payment by the Company
Agency shall also provide with the Vehicle a
30. ARBITRATION or dispute between the Hiring Agency and the In case of any accident resulting in loss or
Driver having an effective and valid driving
All and any disputes arising out of or in Company, if any, shall not be a cause or ground damage to property or life, the sole responsibility
license for the same class of Vehicle (the
connection with this Agreement, after written for non-compliance of these obligations by the for any legal or financial implication shall vest
Driver”). The Hiring Agency shall provide the
notice by either Party to the Contract, shall be Hiring Agency. with the Hiring Agency. The Hiring Agency
Vehicle with the Driver for use by the Company’s
referred to the Sole arbitration of a person Project at its Site / Office or location specified by agrees and undertakes that the Company shall
8. OPERATION HOURS
(bearing the designation of General Manager or it. have no liability whatsoever.
equivalent or higher designation) of the The Hiring Agency agrees that the Vehicle shall
Company appointed by the Chairman and 4. RTO CERTIFICATE & INSURANCE be available for at least 312 hours/26 days per
Managing Director of the Company. The place of month for operation. The hours of operation of
arbitration shall be Mumbai. The arbitration shall
14. TRANSFER OF LOCATION
The Vehicle shall have a valid R.T.O. the Vehicle shall be flexible i.e. the Vehicle shall
be conducted in English language. The Registration certificate, permits, fitness be available for work round the clock i.e. 24 The Company shall have rights to change /
arbitration award shall be final and binding. certificate, PUC certificate(s), certificate of hours in a day. Increase in the operation hours transfer location of Vehicle between work fronts
Subject as aforesaid, the provisions of the payment of vehicle/road taxes (as may be beyond 312 hours, if any, shall be chargeable at as per the requirement of the project site or as
Arbitration and Conciliation Act, 1996, or any applicable) and shall have a Comprehensive negotiated rates or rates worked out on pro-rata and when required. If the location of the Vehicle
statutory modification or re-enactment thereof Insurance Policy including third party. The risk basis whichever is lower. The Hiring Agency is changed beyond the permit limits / plying limits
and the rules made thereunder and for the time amount coverage for third party (ies) shall not be shall ensure that the replacement Driver for the it shall be the responsibility of the Hiring Agency
being in force shall apply to the arbitration less than Rs. 7,50,000/-(Rupees Seven Lacs Vehicle is provided for driving duty beyond the to ensure such taxes are paid and the permits
proceeding under this Clause. Fifty Thousand only) and the risk coverage for statutory working hours for Driver. obtained.
the Driver and all passengers shall not be less
than Rs. 2,00,000/- (Rupees Two Lacs only) per
Note: Nothing in this Agreement shall person for the entire period of the contract. The
constitute or deemed to constitute the Hiring Agency shall be responsible for all 9. ODOMETER 15. PAYMENT TERMS
Hiring Agency as an agent of Gammon certification, insurances, permits, approvals,
payment of taxes, and all such obligations and The Hired Vehicle shall have calibrated A monthly Tax Invoice shall be raised by the
India Limited. liabilities as required by the Applicable Law Odometer to accurately record Kilometer reading Hiring Agency for the hired Vehicle by the 5 th
including but not limited to those mentioned in on a day-to-day basis. The meter reading should (fifth) day of every month along with the relevant
this Clause. tally the actual distance of run at any instant and documents like vouchers / log book copy signed
‘Authorized Person’ of the Company shall have by representative of both the parties, confirming
authority to check the meter for its correctness. the period of utilization of the Vehicle and
******************* 5. AGE OF VEHICLE statement of recoveries, if any. The Company
shall verify and settle these invoices as per terms
S E CT I O N V The Vehicle shall be in excellent working
conditions and under no circumstances shall be
10. LOG BOOK stated in the Work Order. All taxes and duties
with respect to this Work Order or any payment
more than 3 (three) years old. The Hiring Agency shall be the sole responsibility of the Hiring
The Driver of the Vehicle shall maintain the Log
shall be responsible to ensure that the Vehicle Agency. No interest/penalties shall be paid on
These General Conditions of Vehicle Hire shall Book where date, time, kilometer reading and
has sufficient fuel, its lubricants, air and water delayed payments, if any.
be read in conjunction with the Special places visited are filled in and signed by the
and internally and externally, is always
Conditions, if any and shall form an integral and Company’s Authorized Representative (or users
maintained in a sterling condition by the Hiring
binding part of the Work Order placed on the so authorized in writing by the Company’s 16. TERMINATION
Agency.
Hiring Agency by Gammon India Limited Authorized Representative). The Vehicle Log
(hereinafter referred to as the Main Contractor or Book contemporarily maintained at the site shall The Work Order shall be terminated forthwith by
the Company) and collectively referred as 6. DRIVER be treated as a final and conclusive document the Company in case there is a breach of any of
Parties for providing Vehicle on hire (the Vehicle) for time calculation, which shall be duly signed the obligations, undertakings, representations
The Driver engaged by the Hiring Agency shall daily by the Driver of the Vehicle and Authorized and warranties made herein above by the Hiring
1. GOVERNING LAWS have a valid Driving License and shall have Person of the Company. The ‘Authorized Person’ Agency.
The Work Order shall be governed by the Laws driving experience of not less than 5 (five) years of the Company may be either the Project
of India and courts in Mumbai shall have with respect to the same class of Vehicle to drive Manager / Plant Manager for the respective site,
exclusive jurisdiction over all matters arising out the Vehicle on road safely and carefully. The the Administration in charge for the site, or an 17. ARBITRATION
of or relating to this Work Order. notarized copy of the driving license, the officer of the Company not below the rank of
Notwithstanding the place where the Work Order is residential address proof, the signature proof, Senior Manager. All and any disputes arising out of or in
signed or where the work under the Work Order is identification mark and blood group for each connection with this Agreement, after written
to be executed, it is mutually understood and Driver shall be given to the Company by the notice by either Party to the Contract, shall be
agreed by and between the Parties hereto, that Hiring Agency before such Driver(s) is(are) referred to the Sole arbitration of a person
assigned to the Vehicle. The Hiring Agency
11. FUEL (bearing the designation of General Manager or
this Work Order shall be deemed to have been
entered into by the Parties concerned in the City of agrees and undertakes to be responsible to Equivalent or higher designation) of the
The rates accepted by the Company are Company appointed by the Chairman and
Mumbai ensure that such Driver provided for the Vehicle
inclusive of fuel and oil/lubricant charges. Unless Managing Director of the Company. The place of
shall be physically fit for reporting to duty (and
otherwise specified in the Special Conditions, arbitration shall be Mumbai. The arbitration shall
shall not be suffering from any form of
2. EXCLUSIONS fuel shall be arranged by the Hiring Agency. If be conducted in English language. The
communicable infectious diseases including any
stated in the Special Conditions, Fuel may be arbitration award shall be final and binding.
form of communicable infectious respiratory and
The Hiring Agency has clearly understood that provided by the Company on chargeable basis Subject as aforesaid, the arbitration shall be
skin diseases). The Driver shall have polite
the terms and conditions herein contained, has upon written request from the Hiring Agency at governed under the laws of India.
behavior & shall be on duty with neat and clean
been negotiated by and entered into on behalf of prevailing market rates plus charges of 5%.
dress. The Driver shall be sober (not under the
the Company and the Hiring Agency Upper Limit of Fuel consumption of the Vehicle
influence of any form of intoxication), of a sane
understands and accepts that the Chairman and shall be decided by the Company. In case, the Note: Nothing in this Agreement shall
mind, aware of his responsibilities and shall not
the Managing Director of the Company, or any Vehicle consumes more fuel than the agreed
Director(s) of the Company or the Chief
have any kind of bad habits. He shall be
limit, then the excess amount with 15% of
constitute or deemed to constitute the
available and answer the mobile phone at all Hiring Agency as an agent of Gammon
Operating Officer of the Company has no part to charges shall be deducted from the monthly bills
times. In case of any misbehavior or misconduct
play in the negotiations and execution of these raised by the Hiring Agency. India Limited.
of the Driver, the Company may forthwith levy a
presents and accordingly is not liable at all in
charge of Rs. 500 (Rupees Five Hundred only)
contract, tort or crime in respect of this Work
and additionally the Company may (at its option)
Order or any acts pertaining thereto including
terminate this Work Order. The Hiring Agency 12. BREAKDOWN *******************
prior to its execution. The Hiring Agency
agrees and undertakes to be responsible to
accordingly undertakes that under no
ensure all of the above and to ensure safety of In the event of any mechanical failure/
circumstances shall he/it sue and/or prosecute
the passengers, third parties, the Driver and the breakdown of the Vehicle, the Hiring Agency
the Chairman and the Managing Director of the
Vehicle at all times. shall arrange for the replacement by another

You might also like