Professional Documents
Culture Documents
Electrical installation design is the subject that to introduce the student about
the real situation on electrical engineering field. On this subject, student can be shows
the connection and combination of the socket outlet, lighting, fan, air condition and
other to create electrical system. From this electrical installation project, student will
be trained to organize the whole project area from the main switch board (MSB) until
final circuit.
An electrical system can be divided into two type, low voltage and high
voltage system. On this subject, student is preferred to learn and understand about the
medium and low voltage system. On the low voltage system, student will covered to
determine the cable sizing and protection device, design the switchboard, design the
power factor, correction board, design the generator set with the automatic main
failure system, design the lightning for indoor uses, the socket outlet and protection
for the system.
In electrical installation design project, student should to follow the requirement and
understanding the governing rule and regulation. It is important to make sure the
project is safe and equipment used. Student should to follow the guideline on the IEE
Regulation Edition 17th and Jabatan Kerja Raya (JKR). By follow the guideline,
student does not improve their skill for design the electrical system, but it also help
student to improve their knowledge about the equipment used.
Objective
The main objective are to achieve this project was done completely. The objective is
preferred to design the medium and low voltage system. The objective that we apply
on this project is:
Lighting is the uses of various light sources, both artificial and natural, to
achieve some aesthetic or practical effect while illuminating a scene. Lighting is also
mainly either incandescent lamps or fluorescent lamps and often depends heavily on
movable fixtures plugged into outlets. This lighting is typically found in kitchens,
bathrooms, and corridors and in the form of hanging pendants in dining rooms and
aluminium placed inside fluorescent fixture, which can more divert light directed
toward the ceiling down toward the work area. Proper lighting is needed to provide
full illumination in an area. Without proper design, energy can be wasted by using too
much light. The idea is based on a view of theoretical applied to visual design and
A socket outlet is the familiar item mounted on the wall into which a plug can
be inserted. It is available in single and double types. A few manufacturers also make
A single socket outlet is rated at 13 amps. A double socket outlet is not rated at
26A .It 13A shared between the two outlets. Therefore if you intend to have two high
power appliances in the same place, two single sockets are better than one double.
The main advantages of the 13A socket with fused plug are that any appliance with a
loading not exceeding 3.12kW (13A at 240V) may be connected with perfect safety to
any 13A socket, and under certain conditions an unlimited number of socket may be
connected to any one circuit.13A socket outlets circuits can be fed by either radial or
ring circuits. Figure shows a radial circuit arrangement and the socket outlets in the
ring circuit are fed by two parallel conductors. Table shows the information of the
installation aspect of wiring and cabling is available in Malaysia Practices for 13A
socket outlet.
Types of 13A Socket Area Size of Wires Fuse/Circuit
Breaker Rating
Outlet
3. ELECTRICAL CABLE
For each of these conditions there is a correction factor which derates cable current
carrying capacity or conversely increases cable size. In this project, the correction
factor was assumed as: Ca = correction factor for ambient temperature
Cr = 0.725 when the semi enclosed fuses (BS 3036)used to protect the circuit
the IEE Regulations for the use of proper materials. There were several types of
cables installation such as cable in trunking, cable tray and power cable. For this our
projects, we just only use conduit installation. We must refer the IEE Regulation 17
edition to know list of the cable sizes, current carrying capacities and voltage drops of
The cable trunking was complying with IEC 61084. They were fabricated
form galvanized sheet steel and finished with two coats of standard orange enamel. A
square or rectangular in cross section, having one removable side. All trunking
elbows, offset and combination elbows, adaptors and tees were same thickness as the
straight trunking and the type manufactured and supplied by the same trunking
manufacture. The trunking was supported by fixing brackets so that the trunking will
not be in contact with the walls or floor slabs. Trunking was supplied 3m length and
are insulated conductors are obtained. Several general requirements apply to all types
of conduit installation. All runs must be installed as a complete system before any
conductors are pulled into them. In other words, a run of conduit (to include conduit,
fittings and supports) must be complete before the conductors are installed. A run of
conduit should be as straight and direct as possible. The minimum size raceway that
can be installed is generally ½-inch electrical trade size. There are exceptions to this
rule depending on specific locations. The expectations’ for each type are outlined in
the NEC.
All types conduit must be rearmed after they have been cut. Conduit threaded
in the field must be threaded with a die that has a ¾-inch taper per foot. A conduit
installation can be rewired easily or altered at any time and this flexibility, coupled
with mechanical protection, makes conduit installations popular for commercial and
industrial applications.
to avoid or to control damage due to abnormal currents and voltages. All equipment
normally used in power system installation has standardized short-time with stand
ratings for overcurrent and overvoltage. The role of protective scheme is to ensure
that this withstand limits can never be exceeded. In general, this means that fault
Besides that, protective devices see the fault at the same time but only one must act.
protect an electrical circuit from damage caused by overload or short circuit. Its basic
discontinue electrical flow. Circuit breakers are made in varying sizes, from small
A short circuit current is a fault that occurs when a low resistance path exists
between the hot lead and some grounded points. When an electrical short circuit
occurs, heavy current will flow in the circuit for as long as it takes for the circuit
breaker to trip to OFF or for the fuse to blow. Because a properly-working circuit
breaker or fuse cuts off the current flow quickly, the circuit wiring will not have time
describe any electrical malfunction, regardless of the actual problem. A short circuit is
(overcurrent) limited only by the Thevenin equivalent resistance of the rest of the
generation of heat and the risk of fire or damage to equipment. Possible causes for
overcurrent include short circuits, excessive load and incorrect design. Fuses, circuit
breakers, temperature sensors and current limiters are commonly used protection
the ampacity of a conductor. Overcurrent may result from an overload, a short circuit,
or a ground fault. Overcurrent does not always cause a fire. The magnitude and
direction of the overcurrent must be sufficient to heat the wire to a temperature that
fire (called overload) should trip the fuse or breaker, opening the circuit and stopping
the flow and heating. However, items such as an extension cord can reduce the
conductor size between the load and the circuit protection and can overheat the wire
Flow chart 1.1 shows the steps that we have used to design the distribution
system
determine
calculated
calculated cable sizing calculate design the design the
the load
the load and the voltage Main Switch capacitive
socket
lighting protection drop Board bank
outlet
device
Lighting design is the most important aspect that should be doing when
designing the electrical system for building. To make the best design lighting, we
have to ascertain our design provides adequate lighting.
Flow chart 1.2 shows the steps that we apply for design lighting system.
To find the area of room and space building, we must determine the length and
width the space building using AutoCAD software. We have used the dimension
command in AutoCAD software. After finish takes the dimension of room, we have
inserted the data and calculate the dimension to determine the area and insert the data
into the Microsoft Excel.
Room index is related to the room dimensions and used when calculating the
utilization factor and other characteristics of lighting installation. To find the room
index, we must determine the mounting height (Hm) by assume it. Mounting height
was the height of luminaries above the working plane. Mounting refers to situation of
room and area. Refers to Appendix B, on table of JKR.
𝐿𝑥𝑊
Room Index, K=
𝐻𝑚 (𝐿+𝑊)
Where:
L = Length
W = width
Luminance (lux) is one of parameter has been considered during designing the
lighting system for this building. The luminance is depends on the general building
area. Because of that, we used the Appendix B as a reference to find the luminance of
the building area.
Figure 1.4 shows the result that we have done to determine the quantity of the lamps
5. Calculation of the quantity of lamps
In lighting design, calculate the quantity of lamps is the final steps. This is
because the data of dimension, coefficient, lamp lumen and other should be
determining to perform this calculation. However, the maintenance factor of lamps
should be applied to get the specific quantity of the lamps. In this project, we assume
that the maintenance factor is 1.
𝐸𝑎𝑣 𝑥 𝐿𝑥𝑊
Number of luminaries, N =
𝐿𝐷𝐿𝑥𝐶𝑜𝑈𝑥𝑀𝐹
Where:
MF = Maintenance factor
L = Length of room
W = Width of room
In electrical installation design, switch socket outlet circuit can be installed into two
types like radial and ring circuit. Both of the circuit has their own advantage and
disadvantage. For radial circuit, it suitable to be installed on the small area and used
the largest cable size. This is because radial circuit connection can be define as the
main switch or fuses is transmitted from one point to point by a single length of cable
linking each point to the next. The example of radial circuit arrangement is shows on
Figure 2.1.
However, ring circuit connection can be perform as a ring where cable leaves the
consumer unit and travels to each socket on the main and when it reaches the last
socket it then turns back to the consumer unit. From that, the power can reach in the
circuit from the both direction, which reduces power load on the cable. So that, it
suitable to be installed on large area and used a small cable size. The example of ring
circuit arrangement is shows on Figure 2.2 and the different characteristic of ring and
radial circuit is shows on Table 2.1.
Cable sizing
Cable sizing are the important steps before selected the protection device in electrical
system. Basically, most engineer design system will be selecting the higher then
actual value of cable sizing. This is because the method is one of the JKR procedure
and rule in design a project. From that, it can help a consumer to do some renovation
for a future.
To select the best cable size, we have highlighted some steps that should be applied to
find it. First, we must determine the design current (Ib) of the circuit. Then, choose
the type and nominal current rating (In) of the associated overcurrent protective
device. To choose nominal current rating, we used IEE Regulation Edition 17th by
refer to figure 13.1-13.3. To make sure the value of In is suitable, we have choose the
greater than or equal to Ib value.
Diagram 3.1 shows the real installation system
Current carrying
capacity of cable (Iz)
MCB LOAD
I z I n Ib
I 2 1.45I z
Where
Iz = the current carrying capacity of a cable for continuous service, under the
particular installation condition concerned
I2 = the operating current of the device protecting the circuit against overload
To find the maximum demand value, we had decided the value of diversity factor
first. When choose diversity factor we had know the situation of area for lighting and
socket outlet. When change situation of place, change value of diversity factor.
The design current of the system should be calculate to analyse either the result for
the socket and lighting system is acceptable or not. If there are any error in
calculation, we describe either our design is cause the more circuit overload and
frequent breaker tripping. Each design current can be determine by the following
equation:
iv) Determine the current setting of protection device, In for the MCCB
Current setting of protection device is important to determine for design the suitable
MCCB of the building. It also used to determine and select the best protection device
of the project. After finish determine MCCB rating, we have to design the main
switchboard (MSB) for connect all the MCCB.
The size of a cable to be used for an installation depends upon the current rating of the
cable under defined installation conditions and the maximum permitted drop in
voltage as defined by Regulation 525-01.
Voltage drop calculation
The voltage drop calculation is used to ensure that voltage applied to the
electrical appliances is maintained within proper limits. Most electrical appliances are
designed to operate within a voltage tolerance of ± 10%. In Malaysia, the utility
supply regulations normally ensure the voltage variations at the supply are kept within
-10% to +5%. When the cable is too long but the cross-sectional of the cable is small
will produce the voltage drop. So, the load at the end point will not reach the actual
voltage. The IEE Wiring Regulation 17th Edition state the maximum voltage drop is
not exceeded 4% of the nominal voltage at the origin. So, for the three phases that
using in this building that uses 415V.The calculated voltage drop should include any
effects due to harmonic currents.
Diagram 4.1 shows the voltage drop of the system based on JKR requirement:
MS SS DB End
2h 1.5 0.5
3.5
4%
Diagram 4.1
To calculate the voltage drop of the system, we must have some important information to
apply it. The only information needed is analysis the type of cable, determine the conductor
cross section and type circuit connection identify the method of installation and also calculate
the load of the circuit. All these information is used to apply to the following equation:
For dc circuit and for ac circuit using conductor of ≤16mm² cross sectional area:
tabulated mV / A / m x I b x l
Voltage drop (volts)
1000
tabulated ( mV / A / m) z x I b x l
Voltage drop (volts)
1000
For dc circuit and for ac circuit using conductor of ≤16mm² cross sectional area:
tabulated mV / A / m x I b x lx cos
Voltage drop (volts)
1000
sin 1 cos 2
Ib = Design Current
𝑙 = Length of cable
Design Main Switchboard
The incoming switchgear for the MSB is located in the substation room with the
switchgears. MSB was the point at which the incoming power supply divides into separates
circuit, each of the circuit controlled and protected by the fuse or switchgear of the board.
Design power factor correction is the final stage to determine the protection device of
the equipment. The purpose of the systems for power factor correction in networks is to
compensate the generated lagging reactive power by leading reactive power at defined nodes.
This is because much electrical equipment is producing a harmonic factor, so it has to design
to reduce and decrease the harmonic factor in the equipment. In this way impermissibly high
voltage drops and additional ohm losses are also avoided. The necessary leading power is
produced by capacitors parallel to the supply network, as close possible to the inductive load.
Static capacitive compensation devices reduce the lagging reactive power component
transmitted over the network. If network conditions alter, the required leading reactive power
can be matched in steps by adding and taking out single power capacitors (automatic PFC) to
compensate the lagging reactive power.
Design the capacitor bank
Capacitor bank is design protects the equipment, which is it can be used safely to consumer
and gives a long period of the equipment. A capacitor bank can be design into a number of
steps, typically either 6 or 12 steps. In this project, 6 steps are selected and each of the
capacitor banks is controlled by a contactor. The size of the capacitor could be increased or
decreased in steps, by controlling the contactor. The locations of the capacitor bank for this
project were connected at the bus bars of the main low voltage distribution board for the
installation and remain in service during normal loading. To calculate the capacitive rating for
the system, it can be divided into 2 methods in the different condition.
Method 1
For the first method, it normally applied to determine the normal required capacitor output of
the system. This result can be determined based on the leading or lagging power factor in the
system. The calculation to determine the rating can be using by equation following.
where
Second method to determine the capacitive rating for the system is normally used when the
system is producing a harmonics effect. The new value of the capacitor output should be
calculated to determine the new rating of the capacitor used. It is important when the
harmonics are mainly produced in the supply network, a detuning factor of 7% is
recommended due to JKR standard.
𝑉𝑛𝑒𝑤 2 𝑓 𝑛𝑒𝑤
𝑄𝑛𝑒𝑤 = ( ) ×( ) × 𝑄𝑐 × (1 − 𝑝)
𝑉𝑐𝑛 𝑓 𝑐𝑛
where
p = detuning factor
The size of the capacitor is depends on the number of the steps require on the system. The size
of the capacitor could be increased or decreased in steps, by controlling the contactor. The 6-
steps automatic power factor correction board is selected as ( 1 : 1 : 2 : 2 : 4 spare), the step
function is freely selectable and can be modified by changing the branch circuit rating. The
calculation to determine each step of the capacitive rating can be using by equation following.
𝑄 𝑛𝑒𝑤
1 𝑠𝑡𝑒𝑝 =
𝑡𝑜𝑡𝑎𝑙 𝑠𝑡𝑒𝑝𝑠
To making and breaking capacity of the circuit breaker is suitable to the short circuit level of
the installation. The Standard IEC 60831-1 and IEC 60931-1 prescribe that capacitor is able
to operate under steady-state conditions with an r.m.s current value up to 30% higher than
their rated current Ic.
𝑄𝑛𝑒𝑤
𝐼𝑐 𝑚𝑎𝑥 = 1.43 ×
√3 × 𝑉𝑟𝑎𝑡𝑒𝑑
𝑄𝑛𝑒𝑤
𝐼𝑐 𝑚𝑎𝑥 = 1.365 ×
√3 × 𝑉𝑟𝑎𝑡𝑒𝑑
Where
The Davis Lighting was chosen due to its low price and high quality.The type of lamp that
always use and suitable are flourescent lamp and considered as the best choice for energy
saving propose. The lighting types were used in the project was attached in Appendix B.
Calculation Method:
𝐿×𝑊
𝑅𝑜𝑜𝑚𝐼𝑛𝑑𝑒𝑥, 𝐾 =
𝐻𝑚(𝐿 + 𝑊 )
2.85 × 1.85
=
3(2.85 × 1.85)
= 0.37
The value of room index that calculated can obtain a value of maintenance factor, CoU
that is 0.48 refer to Appendix B. The initial lumens of each lamp (LDL) obtained from
manufacturer’s data, for LDL table refer to Appendix B. Then, the number of luminaires, N
can be calculated if all the data are complete. The number of luminaires can determine the
number of required lamps.
𝐸𝑎𝑣 × 𝐿 × 𝑊
𝑁=
𝐿𝐷𝐿 × 𝐶𝑜𝑈 × 𝑀𝐹
= 1.569 ≈ 2 𝑢𝑛𝑖𝑡
Besides by using calculation method, an alternative way used software for design
which knows as Calculux. The software that use is Microsoft Excel, Speed and easy . The
result between use calculation and software method are same. As can see at Appendix C
shows the result for the luminance design using software (Calculux) method.
When the electrical loads in this building were determined, then estimation power loads for
the mechanical loads was required such as air conditioning. For estimation load need to
calculated connected load first. Load estimation must be declared power demand which
determines the contract for the supply of energy. The rating of the MV/LV transformer,were
applicable (depend on loads).
Lighting System
The example below shows the step to determine the cable size for DB-BULL which
required to maximum demand. Use lower voltage,fordetemine the value of current Ib.
√3 , because used for three phase cable. Size cable was already selected from table at
Appendix B. Since the cable was already installed in cable riser, the non-armoured
single core PVC insulated cable was selected to be used in DB-BULL.
TCL MD cos𝜃
9.68kW 9.68kW 0.75
𝑀𝐷(𝑘𝑊)
𝐼𝑏 =
√3 × 240 × 𝑐𝑜𝑠𝜃
9.68𝑘
=
√3 × 415 × 0.75
≈ 17.96 𝐴
In condition IEE Regulation Edition 17th , the rating of MCCB must be equal to or
large than Ib. So,MCCB at rated 30 A TPN (In = 30A) was chosen for the DBB1. Since the
cable was installed in conduit in thermally insulating wall, refer to the condition in the IEE
Wiring Regulation which the 𝐼𝑧 ≥ 𝐼𝑛 that the cable selected was6𝑚𝑚2 .
4.3 Voltage drop
In voltage drop calculation, there are two condition that use two formula. First, in
which using conductor of 16𝑚𝑚2 or less cross-sectional area and secondly using conductor
of 25𝑚𝑚2 or greater cross-sectional area. The voltage drop through the conductor for DB and
SSB was not exceeding 4% of the nominal voltage of supply. The calculated voltage drop
should include any effects due to harmonic current.
From SSB B1 to DBB2 (L) , the cable used is 4𝑚𝑚2 PVC Cable+E conduit.
From main switch board (MSB) to SSB A1,the cable use is 35𝑚𝑚2 PVC Cable+E conduit .
Current of Circuit Breaker Length Cable Voltage Drop, r Cable Voltage Drop, x
107.68 A 10 m 1.10 mV/A/m 0.27 mV/A/m
Current Transformer always was provided by contractor. The incoming supply was
controlled by a circuit breaker in MSB; the metering CTs were installed before the circuit
breakers. The CTs size up by using equation below and for selecting the CTs.
The equation for Current Transformer (CT) will use the power line equation that will derived
the formula to be as below:
𝑃 = √3 × 𝑉 × 𝐼 × 𝑐𝑜𝑠𝜃
𝑃(𝑘𝑊) 88.59𝑘
𝐼= =
√3 × 𝑉 × 𝑐𝑜𝑠𝜃 √3 × 415 × 0.75
= 164.329 𝐴 ≈ 200 𝐴
Ratio : 200/5 A where 200 A is the primary ratio of the metering CT. choose from table at
Appendix B.
4.5 Design Power Factor Correction Board
Power factor correction board or capacitor banks are used to improve the quality of the
electrical system and the efficient operation of the power system. Basically there are two part
to design the capacitor bank. Part 1 is usually used for commercial code of practice and
roughly estimates the initial and required PF to size the capacitor bank. The part 2 was used
based on catalogue and regulation and more parameters are required for this method.
𝑄𝑐 = 𝑃(tan 𝜃1 − tan 𝜃2 )
= 61.2606 𝑘𝑉𝐴𝑅
𝑉𝑛𝑒𝑤 2 𝑓𝑛𝑒𝑤 𝑝
𝑄𝑛𝑒𝑤 = ( ) 𝑋( ) 𝑋 (1 − ) 𝑋 𝑄𝑐
𝑉𝑐 𝑓𝑐 100
525 2 50
𝑄𝑛𝑒𝑤 = ( ) × ( ) × (1 − 7%) 𝑋 61.2606 𝑘𝑉𝐴𝑅
415 50
In this project, the steps that we have choose is (1 : 1 : 2 : 2 : 4). The rating capacitive we
used ≈ 91.1558𝑘𝑉𝐴𝑅.
𝑄 𝑛𝑒𝑤 Qnew
1 step = =
𝑡𝑜𝑡𝑎𝑙 𝑠𝑡𝑒𝑝𝑠 10
91.1558 𝑘VAR
step =
10
Information;
P = installation loan in kW
nformation:
STEP 7 : Calculation Circuit Breaker Rating
The circuit breaker was considered for design power factor regulator.
𝑄𝑛𝑒𝑤 91.1558𝑘
𝐼= =
√3 × 415 √3 × 415
= 126.816 A
9𝑘
= × 1.43
√3 × 415
= 17.90𝐴 ≈ 25𝐴 𝑇𝑃𝑁 𝑀𝐶𝐶𝐵
18𝑘
= × 1.43
√3 × 415
= 35.81 𝐴 ≈ 40𝐴 𝑇𝑃𝑁 𝑀𝐶𝐶𝐵
36𝑘
= × 1.43
√3 × 415
= 50.08 𝐴 ≈ 63𝐴 𝑇𝑃𝑁 𝑀𝐶𝐶𝐵
CONCLUSION
SUMMARY
A couple of new proposal could be observed from various designs. For example,
certain cable were sized down, outgoing cable were change to bus duct system, luminaire
were repurposed to energy saving type, different type of compound light proposed, circuit
breaker were upgraded, power factor correction factor was improved, reliable lighting
protection device and the capacity of auxiliary and transformer were upgraded. The above
Design standard and regulation are the same for every project but design requirement
need to suit the architecture layout difference type for various type of project. Hence a lot a
coordinated works between architect, mechanical and civil engineering were to be worked out
in the initial stage. Engineers need to understand how to society in each all of the consultant
they worked with, so that by their activity they can create satisfying and sustainable jobs for
The education of engineering only provides them for involvement in the theory stage.
When expose to working environment, theory is one part of the design. For instant the design
has to refer to local authority and client requirement in order the project completion. Besides
that, engineer has to go for self improvement such as exploring into new technologies.
Engineer have to put a lot of efforts for planning and consideration for energy
management due to comparison for long and short term benefits such as purchasing more
expensive lighting which consist of low ballast and energy saving fluorescent light fitting
Professional engineers have to access the information from many sources. They must
achieve the standard and regulation that they are refer and they were informed by latest
distribution box (DB), sub-switch board (SSB) and main-switch board (MSB). The purpose of
spare if we need the new wiring in the future. If we don’t install the spare, we need to make
another DB for the wiring and make the cost is expensive. If we have the spare, we just need
to install the cable through the spare and it can save the cost initially. It will more efficient
Objective............................................................................................................................2
Design theory.....................................................................................................................3
Lighting
Socket outlet
Electrical cable
Correction factor
Low voltage distribution system
Installation design
Protection
Methodology......................................................................................................................14
Lighting system
Cable sizing
Voltage drop
Capacitive Bank
Result...................................................................................................................................28
Lighting system
Power factor correction
Summary.................................................................................................................40