Valves - lot 2.

PCC date. Remarks.


Fuel gas TIE - IN. P1.12. 15-Aug-2019 Import metering, aux. boiler FG heater, KOD completed in lot
- 1 calibrations.
Fuel gas - auxiliary boiler FG system. P1.08. 15-Oct-2019 Start - up heater included for sub - system completeness.

Export gas (from export metering to pipeline). P1.11. 14-Oct-2019

Evaporation pond & headers. P1.06. 5-Sep-2019

Chemical injection systems (partial - for unit P1.05. 18-Sep-2019 (excluding scale inhibitors & de - emulsifier packages).
82).
Water treatment systems (partial). P1.07. 26-Oct-2019 Partial for 1st phase (with neutralisation tank).

Valves - lot 3.
Unit - 83 (boilers). P1.09. 26-Nov-2019

Firewater systems. P1.07. Pre - requisite for boiler start - up.

Chemical injection (for unit - 83). P1.05. 18-Sep-2019