ID WBS Task Name Duration Start Finish Predecessors % Complete June 01 July 01 August 01 Septe 01 October 01 Novem 01 Decem

h Predecessors % Complete June 01 July 01 August 01 Septe 01 October 01 Novem 01 Decem 01 January 01 Febru 01 M
1/0 5/0 9/0 3/0 6/0 0/0 3/0 7/0 1/1 5/1 9/1 2/1 6/1 0/1 4/1 7/0 1/0 4/0 8/0 4/0
1 1 MANAGED PRESSURE DRILLING & RISER GAS HANDLING CO 153 days? Wed 18/07/12 Fri 22/02/13 66%

2 1.1 212377 SURFACE EQUIPMENT & AIR RECEIVER 124 days Wed 18/07/12 Mon 14/01/13 87%

28 1.2 212378 HYDRAULIC POWER UNIT 148 days? Wed 18/07/12 Fri 15/02/13 75%

67 1.3 212379 FLOWSPOOL CONTROLS & MONITORING 142.5 days? Wed 18/07/12 Fri 08/02/13 57%

94 1.4 212380 SOFTWARE DEVELOPMENT 100 days Tue 14/08/12 Mon 07/01/13 0%

95 1.4.1 SCADA Code development 60 days Tue 14/08/12 Mon 05/11/12 0%

96 1.4.2 PLC Code Development 60 days Tue 14/08/12 Mon 05/11/12 0%

97 1.4.3 TCD Software Integration with RGH 10 days Tue 06/11/12 Mon 19/11/12 0%

98 1.4.4 Safety Software Development 10 days Tue 06/11/12 Mon 19/11/12 0%

99 1.4.5 System Partition 5 days Tue 20/11/12 Mon 26/11/12 0%

100 1.4.6 Level 3 Check 5 days Mon 26/11/12 Fri 30/11/12 0%

101 1.4.7 Peer Review Independent 3 days Fri 30/11/12 Tue 04/12/12 0%

102 1.4.8 Software Reviews & updates 4 days Tue 04/12/12 Fri 07/12/12 0%

103 1.4.9 Static Dynamic Testing 7 days Fri 07/12/12 Mon 17/12/12 0%

104 1.4.10 Black / White / Grey Box Testing 10 days Tue 18/12/12 Mon 07/01/13 0%

105 1.5 212459 UMBILICAL JUMPER & SURFACE TERMINATIONS 110 days Wed 01/08/12 Tue 08/01/13 68%

120 1.6 GENERAL DOCUMENTATION 50 days Mon 10/12/12 Fri 22/02/13 0%

Task Progress Summary External Tasks Deadline


Project: Draft Project Schedule
Date: Wed 21/11/12
Split Milestone Project Summary External Milestone