ADITYA ENGINEERS

SATTI BAZZAR

REF- STEEL ESTIMATE


DATE 9/6/04

DETAIL ESTIMATE OF PROPOSED SHED FOR


FOR M/S ASHOK ISPAT SIZE OF SHED 20.8MX45.73M (10231.2 sft
DETAILS OF TRUSS1 IN NO.
SR.N
O. PARTICULERS OF ITEMS SPECIFICATION NO. UNIT WT. L(M.) B(M) WT(KG) FOR 9 TRUSS
1 Top Chord 75X75X5 4 5.7 10.9 247.4 2226.4
2 Bottom Chord 75X75X5 4 5.7 10.5 239.4 2154.6
3 Central vertical bracing 50x50x5 2 3.8 3.1 23.6 212.0

1]
ADITYA ENGINEERS
SATTI BAZZAR

REF- STEEL ESTIMATE


DATE 9/6/04

6 J-Hook Ls 2400 200.0


7 Topi & Pitch Washer Ls 2400 20.0
8 Nut-Bolt Ls 2400 60.0
TOTAL 280.0
DETAILS OF COLUMN 1 IN NO.
SR.N
O. GENRAL BRACING
1 PARTICULERS OF ITEMS SPECIFICATION NO. UNIT WT. L(M.) B(M) WT(KG)
2 Top truss To Truss TOP CHORD BRACING 40x40x6 8 3.5 7.8 218.7
3 BOTTOM TRUSS CHORD BRACING 40X40X6 16 3.5 7.8 436.8
4 Column to column bracing 50X50X5 16 3.8 7.0 425.6
5 5MM GUSSET PLATE 5MM 50 39.3 0.2 0.2 392.5
7 Beam truss support ISMC200 2 22.1 1.2 53.0
7 Truss support beam bracing 50X50X5 16 3.8 2.1 128.9
9 TOTAL 1655.5
10 #REF!
GRAND
TOTAL KG #REF!

2]
ADITYA ENGINEERS
SATTI BAZZAR

REF- STEEL ESTIMATE


DATE 9/6/04

SR.N
O.
1
2
3
4
5
7
7
9
10

SR.N
O.
1

3
4

3]

You might also like