A technical traning report on

INDIAN RAILWAYS
TECHNICAL TRAINING CRNTRE
DIESEL LOCOMOTIVE WORKS
Varanasi 221004
GAUTAM BUDHA TECHNICAL UNIVERSITY, LUCKNOW, INDIA

2011-12

BACHELOR OF TECHNOLOGY
degree
In
MECHANICAL ENGINEERING
submitted
by
AMIT KUMAR CHAUHAN
to
Mr. Y.S.RAJPUT
(LECTURERE OF DEPARTMENT)

COLLEGE OF ENGINEERING
&
RURAL TECHNOLOGY
MEERUT
TABLE OF CONTENTS
1. Acknowledgment
2. Preface
3. Introduction
4. Brief History
5. Product
 EMD
 WDP4
6. Manufacturing Process
 Engine Division
 Vehicle Division
 Block Devision
7. Workshops
 LMS
 ET
 TMS
 LAS
8. Orginizational Strength
9. Our Quality Policy
10. Environmental/ Societal Orientation
ACKNOWLEDGEMENT

I owe a great many thanks to a great many people who helped and
supported me during making of this reporte.

My deepest thanks to Lecturer, Mr.Y.S.Rajput the Guide of the


reporte for guiding and correcting various documents of mine with
attention and care.

I express my thanks to the Lecturer Mr.D.P.Singh & HOD of


departement, Dr.B.K.Singh, for extending his support.

My deep sense of gratitude to Traning incharge Mr.S.K.Singh


support and guidance. Thanks and appreciation to the helpful people for
their support.

I would also thank my Institution and my faculty members without


whom this reporte would have been a distant reality. I also extend my
heartfelt thanks to my family and well wishers.
PREFACE
The objectives of the practical training are to learn
something about industries practically and to be familiar with
the working style of a technical person to adjust si mply
according to the industrial environment.

It is rightly said practical life is far away from theoretical


one We learn in class roo m can give the practical exposure or
real life experience no doubt they help in i mproving the
personality of the , b ut the practical exposure in the field will
help the st udent in long run of life and will be ab le to
imp lement the theoretical knowledge.

As, a part o f academic syllabus of four year degree


course in Mechanical Engineering every student is required to
undergo a practical training.

I am st udent of third year mechanical and this report is


written on the basis of practical knowled ge acquired by me d uring
the period on the basis of practical knowled ge acquired by me d
uring the period of practical training taken at Diesel Locomotive
Works, Varanasi.
INTRODUCTION
Diesel Locomotive Wo rks (DLW) is production unit under the
ministry of railways. This was setup in collaboration with American
locomo tive co mpany (ALCO) USA in 19 61 and the first locomotive
was rolled out in 196 4. This unit produces diesel electro nic locomotives
and DG sets for Indian railways and ot her customers in India and
Abroad.

Subseq uent ly a contract for transfer of techno lo gy of 4000 HP


Microprocessor Controlled AC/AC Freight (GT 46 MAC) / passenger
(GT 46 PAC) locomot ives and family of 71 0 engines has been signed
with electro motive divisio n of general mo tors of USA for manufacture
in DLW. the prod uction of these loco motives has now started and thus
DLW is the only manufacturers of Diesel Electric Locomo tives wit h
both ALCO and General motors technologies in the world.
Brief History

The Diesel Locomotive Works (DLW) in Varanasi, India, is a


production unit owned by Indian Railways, for which it manufactures
diesel-electriclocomotives and spare parts.

Founded in 1961, the DLW rolled out its first locomotive three
years later, on January 3, 1964. It manufactures locomotives which are
variants based on the original ALCO designs dating to 1960s and
the GM EMD designs of the 1990s. DLW has an annual production
capacity of 150 locomotives and plans to increase it to 200 based on the
current demand.

DLW locomotives have power outputs ranging from 2,600


horsepower (1,900 kW) to 4,000 horsepower (3,000 kW). Currently
DLW is producing EMD GT46MAC and EMD GT46PAC locomotives
under license from Electro-Motive Diesels (formerly GM-EMD) for
Indian Railways.

Varanasi, one of the oldest populated cities in the world and has a
promising place in the international ground both as a hub of traditions
and technology. One side the humming of divine and holy bells of the
temples brings the city to life; on other side Diesel Locomotive Works
(DLW) Varanasi is one of the largest industrial unit in eastern part of the
nation. DLW catch the attention of lot of foreign tourist students to
observer on going amazing locomotive manufacturing process in
Varanasi. Diesel Locomotive works Varanasi is located at the North end
of the city and about 8 Km away from the Holy River Ganges Ghats.
DLW is an ISO 9002, ISO 14001 & OHS 18001 Certified Organisation .

Diesel Locomotive Works, Varanasi (DLW) is one of the main


manufacturing units run by the Indian Railways. This manufacturing
unit came into existence in year 1961, as a “Green Field Project” in
industrial association with ALCO, USA. This unit generate all the Diesel
Electric Locomotives. In year 1964, the first locomotive was
manufactured and it was devoted to the country. Diesel Locomotive
Works, Varanasi produces only Electric Diesel locomotives and
auxiliary parts of locomotives. However it is an Indian corporation but it
has supplied locomotives to some foreign countries also, includes
Angola, Bangladesh, Malaysia, Myanmar, Sri Lanka, Vietnam and
Tanzania.Engine section manufacture more than 2000 machinery, which
comprise ALCO turbo superchargers, cylinder heads, connecting rods,
camshafts, lubricating oil pumps, chrome plated cylinder liners and
Vehicle section of DLW unit works on different fields that include
Currently, Diesel Locomotive Works, Varanasi constructs locomotives
and DG sets. In locomotives section, again it manufactures two different
types of products, one is EMD and another is ALCO.
MILE STONES

August 1961 DLW set up as a green field project in technical collaboration with ALCO, USA for
manufacture of Diesel Electric Locomotives
January 1964 First Locomotive rolled out and dedicated to the Nation
January 1976 Entered Export market, first locomotive exported to Tanzania
December 1977 First Diesel Generating Set commissioned
October 1995 The Transfer of Technology agreement was signed

March 2002 The first indigenous EMD WDG4 freight loco manufactured
November 2002 3600 HP Engine produced
March 2003 The first indigenous passenger version of EMD loco WDP4 manufactured
September 2003 Development of 16 cylinder 3300 HP Power upgraded DLW engine, WDM3D locomotive
2006 5000th locomotive produced
November 2006 DLW manufactured first WDG4 locomotive equipped with IGBT based converter
March 2007 First WDP4 locomotive equipped with IGBT based converter
DLW has successfully switched over to use of microprocessor based control system on all its
April 2007
locomotives.
March 2009 257 locomotives manufactured in 2008-09, highest ever locomotive production
November 2009 5690 locomotives upto 30th Nov’2009(including 348 EMD locos)
PRODUCT
 EMD
 WDG4 - 4000 HP GOODS LOCOMOTIVE

Broad Gauge freight traffic Co-Co diesel electric locomotive


with 16 Cylinder 4000 HP engine, AC-AC transmission,
microprocessor controlled propulsion and braking with high traction
First turned out in 1999 with transfer of technology from General
Motor (USA), this locomotive has exceptional fuel efficiency and
very low maintenance requirements. It is specifically designed for
heavy haul freight traffic requirements of Indian Railways for the 21st
Century.
The heart of loco Traction Control Converter uses the GTO
devices (obsolete technology). Now the IGBT devices, has been
introduced from Oct?2006. It is the latest technology and will be cost
effective. .
The locomotive power has been upgraded to 4500 BCV and the
first Loco (Loco No 12114) was manufactured in May?07
Diesel Engine Transmission
 16 Cylinder 710 G3B, 2  Electrical AC-AC
stroke, turbocharged ? after cooled  6 Traction motor ( 3 in
 Fuel Efficient Engine parallel per bogie)

 Injection System ? Direct  Suspension ? Axle hung /


Unit Injector taper roller bearing

 Governor ? Woodward  Gear Ratio ? 90:17

 Compression Ratio- 16:1

 Lube Oil Sump Capacity ?


950 Lts

Truck Brakes
 High adhesion  Electronic Air Brake
HTSC ( High Tensile Steel Cast) System ( KNORR-NYAB-
truck of bogie Computer Controlled Braking)

 Adhesion ? 0.42  Air , hand , dynamic


brake

 Pure air brake


General Characteristic
 Installed Power  4000 HP

 Axle Load  21 T

 Gauge  1676 mm

 Wheel arrangement  Co-Co

 Wheel diameter  1092 mm

 Height  4201 mm

 Width  3127 mm

 Overall Length (Over  19964 mm


Buffer Beam)  126 T
 Weight  54 T
 Max tractive effort  100 Kmph
 Maximum speed  6000 lts
 Fuel tank capacity  EM 2000 with SIBAS-
 Locomotive Control 16 Traction Control
WDG4-4000 HP GOODS TRACTIVE EFFORT &
LOCOMOTIVE POWER CHART

 WDP4
 4000 HP PASSENGER LOCOMOTIVE

State-of-Art, Microprocessor controlled AC-AC, Passenger


Locomotive Powered with 16-710G3B 4000HP Turbo charged Two
stroke engine.

Fabricated rigid design Under frame, two stage suspension, High


Traction High Speed 3 axle (HTSC) light weight cast truck frame
attribute to high adhesion performance.

First turned out in 2003, this locomotive has exceptional fuel


efficiency and very low maintenance requirements. It is specifically
designed for heavy haul passenger traffic requirements for Indian
Railways.

The WDP4 fleet is being upgraded by provision of hotel load


feature along with power upgradation to 4500 HP. The prototype will
be manufactured in the year 2007.
Diesel Engine Transmission
 16 Cylinder 710 G3B, 2  Electrical AC-AC
stroke, turbocharged ? after cooled
 4 Traction motor ( 3 in
 Fuel Efficient Engine parallel per bogie)

 Injection System ?  Suspension ? Axle hung


Direct Unit Injector / taper roller bearing

 Governor ? Woodward  Gear Ratio ? 77:17

 Compression Ratio- 16:1

 Lube Oil Sump Capacity


? 1073 Lts

Truck Brakes
 High adhesion HTSC (  Electronic Air Brake
High Tensile Steel Cast) truck or bogie System ( KNORR-NYAB-Computer

 Adhesion ? 0.42 Controlled Braking)

 Air , hand , dynamic


brake with fully blended with
automatic brakes

 Pure air brake


General Characteristic
 Installed Power  4000 HP

 Axle Load  19.5 T

 Gauge  1676 mm

 Wheel arrangement  A-A-I I-A-A

 Wheel diameter  1092 mm

 Height  4201mm

 Width  3127 mm

 Overall Length  19964 mm


(Over Buffer Beam)
 117 T
 Weight
 27 T
 Max tractive effort
 160 Kmph
 Maximum speed
 4000 lts
 Fuel tank capacity
 EM 2000 with
 Locomotive SIBAS-16 Traction Control
Control

WDP4-4000 HP GOODS TRACTIVE EFFORT


LOCOMOTIVE & POWER CHART
1. ALCO
1350 HP CAPE GAUGE LOCOMOTIVE
VDM 4

TECHNICAL INFORMATION

1350 HP Locomotive having fabricated cape gauge Co-Co


bogie. hese locomotives have been supplied to Angola and Sudan.

Wheel Co – Co
Arrangement

Track Gauge 1067 mm Cape gauge

Weight 72 t

Overall 15600 mm
Length

Wheel 921 mm
Diameter

Gear Ratio 18: 93

Maximum 90 Kmph
Speed
Diesel Engine Type : ALCO 251 D 6
Cyl. in line.

HP 1350

Transmission Electrical AC/DC

Brake 28LAV-1 system

Loco Air, dynamic, parking

Train Air & Vacuum

Fuel Tank 3000 Litres


Capacity
 2300 HP CAPE GAUGE LOCOMOTIVE

TECHNICAL INFORMATION

2300 HP Main Line Locomotive, having fabricated cape gauge


Co-Co bogies. These are provided with two drivers cabs, one at each
end. These locomotives have been supplied to Angola and Sudan.

Wheel Co-Co
Arrangement

Track Gauge 1067 mm Cape Gauge

Weight 102 t

Overall Length 17620 mm

Wheel Diameter 921 mm

Gear Ratio 18 : 93

Maximum 100 Kmph


Speed

Diesel Engine Type : ALCO 251-B 12


Cyl. V- Engine

HP 2300

Transmission Electrical AC/DC


Brake IRAB-1

Loco Air, Dynamic, parking

Train Air

 2300 HP METER GAUGE LOCOMOTIVE

TECHNICAL INFORMATION

2300 HP Main Line Locomotive, having fabricated meter gauge


Co-Co bogies. These are provided with two drivers cabs, one at each
end. These locos have been supplied to Malaysia, Senegal and Mali.

Wheel Co-Co
Arrangement

Track Gauge 1000 mm Meter Gauge

Weight 102 t

Overall 17620 mm
Length

Wheel 921 mm
Diameter

Gear Ratio 18 : 93

Maximum 100 Kmph


Speed

Diesel Engine Type : ALCO 251-B 12 Cyl.


V- Engine

HP 2300

Transmission Electrical AC/DC

Brake IRAB-1

Loco Air, Dynamic, parking

Train Air

Fuel Tank 3000 Litres


Capacity

 3000 HP CAPE GAUGE LOCOMOTIVE

TECHNICAL INFORMATION
( Provisional Specifications)

3000 HP Micro Processor Controlled, Main Line, Cape Gauge


Locomotive with improved Cab, under development for Mozambique
Railway.

Wheel Co-Co
Arrangement

Track Gauge 1067 mm Cape Gauge

Weight 114 t

Overall 18632 mm
Length

Wheel 1000 mm
Diameter

Gear Ratio 19 : 92

Maximum 100 Kmph


Speed

Diesel Engine Type : ALCO 251-C 16 Cyl.


V- Engine

HP 3000

Transmission Electrical AC/DC

Brake IRAB-1

Loco Air, Dynamic

Train Air

Fuel Tank 6000 Litres


Capacity

 1350 HP METER GAUGE LOCOMOTIVE


YDM4

TECHNICAL INFORMATION

1350 HP Locomotive having cast / fabricated meter Gauge Co-


Co bogie. Such locomotives have been supplied to Vietnam and
Myanmar.
Wheel Co – Co
Arrangement

Track Gauge 1000 mm

Weight 72 t

Overall 15600 mm
Length

Wheel 965 mm
Diameter

Gear Ratio 18: 93

Maximum 96 Kmph
Speed

Diesel Engine ALCO 251 D 6 Cyl. in line.

HP 1350

Transmission Electrical AC/DC

Brake IRAB ? 1 system / 28LAV-1

Loco Air, dynamic, parking

Train Air / Dual (Air and Vacuum)

Fuel Tank 3000 Litres


Capacity
 BROAD GAUGE MAIN LINE FREIGHT LOCOMOTIVE
WDG 3A

TECHNICAL INFORMATION

Diesel Electric main line, heavy duty goods service locomotive,


with 16 cylinder ALCO engine and AC/DC traction with micro
processor controls.

Wheel Co-Co
Arrangement

Track Gauge 1676 mm

Weight 123 t

Length over 19132 mm


Buffers

Wheel Diameter 1092 mm

Gear Ratio 18 : 74

Min radius of 117 m


Curvature

Maximum Speed 105 Kmph


Diesel Engine Type : 251 B,16
Cyl.- V

HP 3100

Brake IRAB-1

Loco Air, Dynamic

Train Air

Fuel Tank Capacity 6000 litres

 BROAD GAUGE MAIN LINE MIXED SERVICE


LOCOMOTIVE
WDM 3D

TECHNICAL INFORMATION

Diesel Electric Locomotive with micro processor control


suitable for main line mixed Service train operation.

Wheel Co-Co
Arrangement

Track Gauge 1676 mm

Weight 117 t

Max. Axle 19.5 t


Load

Length over 18650 mm


Buffer

Wheel 1092 mm
Diameter

Gear Ratio 18 : 65

Maximum 120 Kmph


Speed

Diesel Engine Type : 251 B-16 Cyl. ?V?


type (uprated)

HP 3300 HP (standard UIC


condition)

Transmission Electric AC / DC

Brake IRAB-1 system

Loco Air, Dynamic, Hand

Train Air

Fuel Tank 5000 litres


Capacity
 BROAD GAUGE SHUNTING LOCOMOTIVE
WDS 6AD

TECHNICAL INFORMATION

A heavy duty shunting Diesel Electric Locomotive for main line


and branch line train operation. This locomotive is very popular with
Steel Plants and Port Trusts.

Wheel Co-Co
Arrangement

Track Gauge 1676 mm

Weight 113 t

Length over 17370 mm


Buffer

Wheel 1092 mm
Diameter

Gear Ratio 74 : 18

Maximum 50 Kmph
Speed
Diesel Engine Type : 251 D-6 Cyl. in-line

HP 1350 / 1120 HP (std.)

MANUFACTURING PROCESS
 Engine Division

 COMPONENT MACHINING

Over 2000 components are manufactured in-


house at DLW. These include ALCO turbo
superchargers, lubricating oil pumps, cam
shafts, cylinder heads, chrome plated cylinder
liners, connecting rods and various gears. Our
well-equipped Machine Shops have dedicated
lines for operations like turning, milling, gear
hobbling, drilling, grinding and planning etc.
In addition, DLW is equipped with a variety of
special purpose machines and a large number of
state-of-the-art CNC machines to ensure quality
and precision.

Associated manufacturing processes like heat treatment and induction


hardening are also carried out in-house.
A completely new Chrome Plating Shop for Cylinder Liners has been
set up with modern infrastructure like fume extraction system and
Programmable Logic Controlled material movement system.
 Engine Assembly & Testing

Pre-inspected engine block, crankshaft, camshafts, cylinder liners,


pistons, connecting rods, cylinder heads,
exhaust manifold, turbo-supercharger and
all related piping is used in assembly of
engine. Electrical machines like traction
alternator, auxiliary generator and exciter
are thereafter coupled on the engine.
The complete power pack with electrics are tested on
Computerised Engine Test Beds to verify horsepower output.
Vital parameters of engine are checked to assure the quality of
product.

Only after the engine parameters are found perfect the power
packs are cleared for application on locomotives.

 Vehicle Division

 Component Fabrication
Precision cutting and forming of sheet metal
is utilised for manufacture of superstructures
including drivers cab, engine hoods, and
compartments for housing electrical
equipment. All activities connected with
pipes like pickling, bending, cutting,
forming and threading of pipes of various
sizes are undertaken in another well-equipped work area.
All electrical equipment is assembled in the fabricated control
compartments and driver?s control stands is done in another work
area.

 Under frame Fabrication


Under-frames are fabricated with due care to
ensure designed weld strength. Requisite
camber to the under-frame is provided
during fabrication itself. Critical Welds
areas are tested radio-graphically. Welder
training and their technical competence are
periodically reviewed. EMD under-frame is fabricated using
heavy fixtures, positioners to ensure down hand welding.

Fixtures are used to ensure proper fitting of components and


quality welding in subsequent stages.

 BOGIE MANUFACTURING
Special purpose machines are utilised for
machining cast and fabricated bogie frames.
Axle and wheel disc machining is
undertaken on sophisticated CNC machines.
Inner diameter of wheel discs are matched with the outer diameter
of axles and assembled on wheel press. The complete truck
(bogie), including bogie frames, wheels and axles, brake rigging
and traction motors are assembled which is ready for application
to locomotive.

 LOCOMOTIVE ASSEMBLY
Tested engines are received from Engine
Division. Similarly under-frames are received
from Loco frame Shop and Assembled trucks
from Truck Machine Shop. Superstructures and
contractor compartments are received from
respective manufacturing and assembly shops of Vehicle Division.
Important alignments like crank shaft deflection, compressor
alignment and Eddy Current clutch/radiator fan alignment are done
during assembly stage.
Electrical control equipments are fitted and control cable harnessing is
undertaken. The complete locomotive is thus assembled before being
sent onwards for final testing and painting.
all locomotive systems are rigorous tested as per laid down test
procedures before the locomotive is taken up for final painting and
dispatch.
 Block Division

 Flame Cutting of Components

Steel plates are ultrasonically tested before being


precision cut by numerically controlled flame
cutting machines, Plasma Cutting Machine.
Components are straightened and machined prior
to fitting & tacking on fixture designed specially
for engine block fabrication to ensure close tolerance on engine block.

 Fabrication of Engine Block


Components after flame cutting and various
machining operations are fit and tack
welded before taking on rollovers. Heavy
Argon-CO2 welding is done on these
rollovers. High quality of welding is done
by qualified welders. Weld joints are
subjected to various tests like ultrasonic, X-
rays, Visual etc.

Down-hand welding is ensured using specially designed


positioners.

Fabrication of engine block is completed by


submerged arc welding using semi-
automatic welding machines.
Special fixtures are used for making down-
hand welding possible in inaccessible areas. Critical welds are
subjected to radiographic examination. All welders are
periodically tested and re-qualified for the assigned.

After complete welding weldment is stress relieved and marking


is done for subsequent machining.

 Portal Milling Machine

Engine block machining is done on Portal


Milling Machine which is a 5 axis CNC
machine with SIEMENs 840-D state of art
system control with dedicated tool management
system. This machine performs milling, drilling,
tapping and boring operations in single setting.
The machine accuracy of 10 micron enables adhering to the tolerance
required on engine block.

 Angular Boring Machine


Angular boring "V" boring is done of special
purpose machine. This special purpose
machine has two high precision angular
boring bars.
WORKSHOP
 Light Machine Workshop(LMS)
 Engine Testing(ET)
 Truck Machine Shop(TMS)
 Loco Assembly Shop(LAS)

This shop deals with the matching of vario us small co mpo nents
required fo r the power pack unit such as, cam shaft, co nnecting rod,
liners, gears levers, F.P. Support, Piston pin, nuts and bo lts bushes,
various shafts etc.

The light machine shop divided into the following section:-


 Econometric section
 Grinding section
 Gear section
 Cam shaft sect ion
 A.T.L. section
 Belching section
 Connect ing rod section
.  Lathe section
 Liners section
 Drilling section
 Milling section
Organizational Strength

 A flagship production unit of Indian Railways offering complete


range of products in its area of operation with annual turnover of
over 2124 Crore.
 State of the art Design and Manufacturing facility to manufacture
200 locomotives per annum with wide range of related products
viz. DG Sets, Loco components and sub-assemblies.
 Supply of spares required to maintain Diesel Locomotives and DG
sets.
 Unbeatable trail-blazing track record in providing cost-effective,
eco-friendly and reliable solutions to ever increasing transportation
needs for over four decades.
 Fully geared to meet specific transportation needs by putting Price
- Value - Technology equation perfectly right.
 A large base of delighted customers among many countries viz.
Myanmar, Sri Lanka, Malaysia, Vietnam, Bangladesh, Tanzania,
Angola, to name a few, bearing testimony to product leadership in
its category.

Our Quality Policy

 Quality, Environment, Health & Safety Policy

Diesel Locomotive Works is a Production Unit of Indian Railways,


manufacturing Diesel-electric Locomotives, Diesel Generating sets
and their spares for Indian Railways, Non-Railway Customers and
exports.
 We are committed to achieve excellence by:

 Continual improvement of the Quality,


Environmental and Health & Safety - at- work -
place performance.
 Preventing pollution by all means including
minimizing resource consumption and waste
generation using cleaner technologies, material
substitution and process changes.
 Preventing all injuries and loss of property including
environmental performance through continuous
safety inspections.
 Striving for compliance with all applicable
Environmental and Health & Safety legislations.
 Striving for "Right first time" and safe working
practice through system improvement and training.
 Enhancing Customer Satisfaction through
improvement in reliability and performance of
products.
 Preventing all employees from occupational diseases
and health hazards.

 We shall:
 Set objectives & targets and periodically monitor
their progress through internal audit and
management review.
 Communicate Quality, Environment and Health &
Safety policy to the employees and to make it
available to the public on demand.
Environmental/Societal Orientation

 Environmental Management
A healthy and congenial environment alone can produce and promote
healthy citizens we firmly believe. In order to have a clean and green
DLW, we have a well defined integrated environmental policy. This
promotes an ever motivated work-force, giving rise to products of
International standard.

 Environmental Objectives:
 Reduction in Resourceconsumption
 Reduction in Fire Emergencies -10%
every year
 Improvement in Emergency
preparedness
 Monitoring of water & ambient air periodically
 Sewage Treatment Plant:
STP is mainly concerned with the treatment of domestic and industrial
sewage. The treated water is used for irrigation
purpose up to nearby Lohta farm and kitchen
gardening at DLW premises.The digested sludge
is sent to sludge drying beds, later to be used as
manure. Methane gas mainly produced from the
digester is collected in the gas holder and supplied to the canteen.

 Industrial Effluent Treatment Plant:


IETP does the job of treatment of industrial
effluent which mainly contains oil and
grease . The treated water is sent to nearby
villages for farming and kitchen gardening
at DLW.
 Chromium Treatment Plant:
CTP deals with the treatment of effluents from
CRP shop (Chrome Plating Shop). This has
varying concentration of hexavalent chromium.
This hexavalent chromium is converted into
trivalent chromium in acidic condition and is
precipitated. This sludge, after drying in the form of cakes, is stored
in a covered tank made of concrete. Water after treatment is used for
irrigation in nearby villages.

 Occupational Health & Safety Management:


DLW is OHSAS-18001 certified since September, 2005.
OHSAS formulates the work-procedures, defines hazards,
assesses the risks involved therein and
generates awareness regarding use of
personal protective equipments at
workplace. This enhances safety at work-
place, reduces chances of accidents and
makes workers more confident leading to
increase in productivity.

OHS Objectives:
 Reduction in HOD cases -10% every year
 Improvement in use of PPEs (100%)
 Recharging of Ground water