METHOD STATEMENT

OF
CONCRETE CASTING IN-SITU 
 
1. Cut of Pile Head
After finished of driving pile down to design level accordance with the specifications
and drawings, cutting of pile will be execute.

2. Form Works and Concreting Works


2.1. Form Work
The construction of form work will be made by timber structure and it could be
support the load of pile cap concrete, beam concrete and slab concrete.
The form work installation of wood and plywood must be support by tie rod to
maintain the verticality of the surface beam.

Form Work Material :

• Steel Bracket
• Wood & Plywood 9 mm
• Tie Rod
• Tools Set

2.2. Concreting Work

Concreting Tools :

• Pot Mixer
• Concrete bucket
• Pouring tools & support
• Concrete Vibrator
• Curing compound sprayer

3. Concreting Work
Pile cap, beam and slab will be cast in situ concrete, concrete grade as per
specification. Concreting works will be execute on 2 (two) stage, low level and
high level (as shown on attached drawing). Bracket structure will be fixing on steel
pile as a base of form work.
After installation of bracket done, laying of timber installation will be execute as a
frame for form work for pile cap, beam and slab. Scheme of bracket, timber staging
installation and form work as shown on attached drawing.
The pouring work will be done ect.:
• Stage 1 : Concrete pouring of Pile Cap & Beam
• Stage 2 : Concrete pouring of Slab
A. Concreting Scheme for Pile Cap & Beam
B. Bracket and Timber Staging Installation
C. Flowchart for Formwork
Marking Dimension of Drawing

Cleaning for Pile cap & Column Fix of Standar for Erection Drawing Process

Cleaning for Tie Beam & Plat  Formwork for Column & Tie Beam  Process


Slab That will Be Erected

Formwork for Plat Slab

Checking & Approval

Concrete Casting

Inspection