Professional Documents
Culture Documents
General
This method of statement particularly focused on construction of Work Shop Building in Water
Treatment Plant Area of Polgahawela, Pothuhara, Alawwa Integrated Water Supply Project. This
is basically two storied building with the floor area approximately 1800 sqft. This covers the
sequencing of the construction, Formwork Arrangement, Health, Safety and Environment plan and
other supplementary documents to obtain approval from the Engineer.
2. Applicable Drawings and Specifications as per the Contract
5.7 Formwork
All formworks will be erected in accordance with the drawings and specifications.
Scaffolding for working and access platform where necessary will be erected by skilled labours in compliance
with safety requirements and it will be checked again for compliance.
Formwork system will be in compliance with the specifications, proposed paneling arrangements,
The formworks will be braced adequately to withstand the resulting lateral forces during casting of
concrete.
Form ties will be designed to resist and withstand the lateral pressure during concrete placing;
Appropriate and recommended construction joints will be provided at right locations according to the approved
Construction joints should be clean and free from dust & grout and approved bonding agent should be apply
Contact surfaces of the formworks will be treated with nontoxic mold oil/form-release agent before fixing
the formWORK in their final position.
Removal of formworks will be performed in accordance with the specifications and vertical fortnworks
will generally be removed after 24hrs where it is practicable
• 2”x2” cut to shape timber rafters with 2400x1200x12 mm plywood will be used
for the preparation of formwork panels. 2”x2” timber section will be used to brace
where necessary as per requirement. In general, largest practicable sizes will be used
° 50mm dia. GI pipes, form ties, threaded bars and P-cones will be used to tie & brace the
form work. In addition to that U jacks, T Jacks, Pipe supports and scaffolding frames
with 50mm dia. GI pipe bracing will be used for supporting the form work as
applicable. The Acro Jacks, turn buckle arrangements and tendon wires will also be
opted if necessary.
* All fabricated Formwork panels will be stacked and stored in separate location carefully
without causing any damage or warping under covered roof or otherwise covered
with tarpaulin. All forms will be cleaned and mold oil will be applied before
stacking as required.
Column Section C - C
5.7.3 Formwork for Beam & Slab
formwork arrangement for beam and slab illustrated below.
1 ,
Figure 05: Typical Formwork Arrangement for Beams and Slabs