Professional Documents
Culture Documents
Instructional Manual
Version: 1.00
Date: 24 July 09
Reference
PMBPK (2008) A Guide to the Project Management Body of Knowledge,
Version 4, Project Management Institute.
License
The MS Project template and this Manual forms part of the People Rich Pty Ltd
(Australia) licensed Project Management Methodology that has been customised for
FSMed. It cannot be distributed beyond the exclusive use of FSMed unless it is in
compliance with the license agreement.
Acronym Description
FSMed Fiji School of Medicine
HR Human Resources
PM Project Management
PMBOK A Guide to the Project Management Body of Knowledge
PMM Project Management Methodology
PRC Project Resource Centre
PMP Project Management Plan
WBS Work Breakdown Structure
This instruction does not explain the more advanced resource management
functionality, and is not designed as an instruction guide for staff who have not used
MS Project before. Rather it shows the meaning of customised columns set up as
part of the People Rich template.
On the MS Project template, text in blue signifies automated fields, and text in
maroon is used during tracking project progress in the implementation phase of the
project.
This MS Project file allows for the calculation of the Project Budget and Schedule for
planning purposes, as well as the Savings/Overspends, % Complete, and Estimated
Actual Expenditure calculation during the implementation phase.
2 WBS No.
This is an automatically inserted reference number that allows tasks to be linked to
Activities. For example, task 1.2.1 belongs to activity 1.2 etc.
3 Information
This information column uses symbols that indicate certain information types, for
example:
4 Activity/Task Description
An activity is a grouping or heading for a number of tasks, and a task is the actual
piece of work to be undertaken. An activity is normally stated as a deliverable or a
noun, whereas a task is a verb (i.e., written as a doing thing). Grouping tasks is
simply a mechanism to ease the management of the work to be done. For example,
if a number of tasks were to be outsourced to a business, then they may be grouped
together to be more easily provided to the outsource firm.
The and symbols in front of existing activities/tasks indicate that there is more
information relating to these, and by mouse clicking on the symbol all the related
next level of information will be shown as seen below.
The figure below shows a simple generic WBS comprised of Phase and
deliverables sections.
1. Select the tasks that you want to make subtasks of the summary task.
2. Select the Indent button on the Formatting toolbar.
After clicking the Indent button on the Formatting toolbar, MS Project makes
the selected tasks subtasks of the summary task immediately preceding the,
and makes the preceding task a summary task. See the following figure.
FSMed’s WBS template is designed to separate the activity tasks for Internal FSmed
resources, External Resource (i.e. Consultants) if required and Material Resources.
The template has included a Project Team and Project Status Reporting as ‘recurring
tasks’. Recurring tasks are simply an easy way to set recurring events. Simply
double click on the template task and a window will pop up (or select ‘Insert-
Recurring Task’ to enter a new one).
From this window you can set the frequency and dates of the recurring event.
From the ‘Select HR Resource Type’ column, select ‘FSMED Staff’ for FSMED
resources. Otherwise, select ‘External Contractor’ for external resources.
To enter a new resource simply use the ‘Insert – New Resource’ function.
For any labour or human resource select the type = WORK.
Adjust the ‘Std. Rate’ column to the relevant rate per hour for a WORK (Labour)
related resource.
Return to the GANT CHART view by selecting the GANT CHART from the VIEW
Menu.
Another example is within the ‘Selected Key FSMed Staff Resource’ column a
‘Consultant’ is selected and the amount of effort for the task is 2 person day, then
enter ‘7.4’ (i.e., 2 x 14.8 hrs per day) or enter 2 days in the Schedule Duration (Days)
column.
Please note that this is ‘available time’. For example, the person effort may be 3
days, but there may be 5 days scheduled, allowing a two day float flexibility in the
schedule. If the scheduled time was only 3 days, then there is no float, and the task
may be on the critical path.
This means that the template allows for the showing of actual effort and schedule
duration allocation.
Where possible, dependencies should be set before dates are finalised, as they
automatically change the dates according to the ‘Schedule Duration’ column
information.
The ‘Depend’ column requires information from the left-most column that shows a
sequential number. By entering the number of a task into that field it makes an
automatic dependency link. For example, the screen shot above shows:
You will notice that the dates also now follow the WBS dependencies set: WBS task
1.2 starts after task 1.1 is finished; and task 1.3 starts after task 1.2 finishes.
Effectively you would only have to change the dates on task 1.1 (and any schedule
duration) and the dates will start automatically updating.
In the above example, it shows that the total project budget is calculated as
$2349.75.
If you need to change the rate, simply right click on the header (Administration Fee)
in that column and select ‘customised field’. The following window will appear:
If you over spent $100.00 you enter ‘-100’ into this column and it records a over
spent, which increases the Project Budget summary amount by $100.
The total of this column allows the Project Manager to keep track of any budget
overrun or savings they have.
In the example above, the ‘-$50’ indicates that the Project Manager has a total $50
over spent on the original budget allocation.
For example, if I had a 50 day task that started on the 4 January and finishes on the
30 march, and my progress report period end date is the 1 February, I would report
only 50% of the job is done. This would show that I have spent half the allocated
budget to this task.
18 Further Help
MS Project has a build in help guide. You can write a question in the help window in
the top right corner of the screen.
For further assistance, contact the Project Resources Centre by visiting the Project
Resources Centre Intranet or send an email to prc@fsm.ac.fj.
-End of Document-