1) A new geothermal well in Taupo, New Zealand needed to be brought online but conventional means of starting production had failed.
2) Western Energy Services used coil tubing to inject air into the wellbore to reduce hydrostatic pressure and start flow, gently warming the casing.
3) The operation was successful in starting production from the new well using coil tubing's controlled method to prevent temperature shocking the upper casing.
1) A new geothermal well in Taupo, New Zealand needed to be brought online but conventional means of starting production had failed.
2) Western Energy Services used coil tubing to inject air into the wellbore to reduce hydrostatic pressure and start flow, gently warming the casing.
3) The operation was successful in starting production from the new well using coil tubing's controlled method to prevent temperature shocking the upper casing.
1) A new geothermal well in Taupo, New Zealand needed to be brought online but conventional means of starting production had failed.
2) Western Energy Services used coil tubing to inject air into the wellbore to reduce hydrostatic pressure and start flow, gently warming the casing.
3) The operation was successful in starting production from the new well using coil tubing's controlled method to prevent temperature shocking the upper casing.
Well Profile CASE: Air Lift Geothermal well to start on
production Type: Geothermal Challenge: New well drill needing to be put on production to Location: station. Several attempts at starting well flowing by Taupo Geothermal District, conventional means proved unsuccessful. New Zealand Solution: Status: Lighten hydrostatic of well with air through coil New Drill tubing and start well flowing and gently bring casing up to temperature. Well Depth: 2850m MD Execution: Casing size: Western Energy Services mobilized its Coil Tubing 13 3/8” Production Unit and arranged air compression services on 7” Slotted Liner short notice to fulfil the client’s needs. Air lift operational experience was provided to assist with Coil Tubing: the program and build confidence in the client for 2500m – 2” HS-80 chances of a successful operation. Coil Tubing was BHA: run into the well to a total depth of 1200m MD Coil Connector and injecting air bringing the well online to test variable direction Jetting equipment. The controlled nature of using Coil nozzle Tubing to start new wells is rapidly making it a preferred option to prevent temperature shocking Operation Date: of the upper sections of casing when starting a new Q4 2014 well.