Professional Documents
Culture Documents
S No. Activity (√ or X)
(Remarks)
WBSEDCL Contractor………………………..
Erection Commissioning Erection Commissioning
Signature
Name
Date
STANDARD CHECKLIST (MECHANICAL) Ref: M / 17 / 2
Plant Item: ESP- Collecting Electrodes Rapping mechanism Sheet : 2 of 2
S No. Activity (√ or X)
(Remarks)
8. Ensure that the shock pad face and shaft axis are in the same
vertical plane.
10. Check the proper sealing of the rapping shaft in the bearing.
WBSEDCL Contractor………………………..
Erection Commissioning Erection Commissioning
Signature
Name
Date