STANDARD CHECKLIST (MECHANICAL) Ref: M / 17 / 2

Plant Item: Sheet : 1 of 2

Station: ESP-Collecting Electrodes Rapping Mechanism


System: Date of checking:
Manufacturer: Serial No.:
Location:

Plant Nomenclature: Unit:

S No. Activity (√ or X)
(Remarks)

1. General conditions satisfy the site Standing Instructions as


listed in the “Plant Item Commissioning Testing Essential Pre-
requisites (SCL MS 1/1)

2. The name plate legend agrees with the approved WBSEDCL


Plant Nomenclature, is clearly visible, securely fixed, is
durable and correlates with any remote labels.

3. Installation is correct and complete as per the latest approved


drawings.

4. Ensure that there is no foreign material inside the ESP and


check the cleanliness of hoppers and walls.

5. Check the disposition and tightness of inner arms on rapping


shaft set at proper phase angle.

6. Check the support bracket provided in the middle of two


hammers.

Any other observation:

WBSEDCL Contractor………………………..
Erection Commissioning Erection Commissioning
Signature
Name
Date
STANDARD CHECKLIST (MECHANICAL) Ref: M / 17 / 2
Plant Item: ESP- Collecting Electrodes Rapping mechanism Sheet : 2 of 2

Plant Nomenclature: Unit:

S No. Activity (√ or X)
(Remarks)

7. Check the distance between centre line of rapping shaft to


centre line of shock bar.

8. Ensure that the shock pad face and shaft axis are in the same
vertical plane.

9. Check the lateral shift to hammers with reference to shock


pad centre.

10. Check the proper sealing of the rapping shaft in the bearing.

Check the set rings position and their welding.


11.
Check the clearance between collecting electrode and gas
12. screen.

Check the radial & axial alignment of clutch & coupling.


13.
Check the direction of rotation of the hammers.
14.
Sealing of the opening for CE rapping shaft in the casing.
15

Any other observation:

WBSEDCL Contractor………………………..
Erection Commissioning Erection Commissioning
Signature