A. Busbar Conductors
2. Site Tests
2.4 Measurement of noise levels. The following noise levels shall not be exceeded at
the substation fence and / or 25 meters from the busbar, whichever is closer.
Measurement shall be made at 2 points on each side of the substation.
For 500 kV:
2.5 Measurement of electric field. Measurement shall be made at two points in each bay
and at the two points around the substation fence. The following values should not
be exceeded:
It is not permitted to use only one insulator string to separate two systems. Two insulator strings
have to be applied and the fittings between the two insulators strings have to be earthed.
1.1 Checking of level and alignment of installed station insulators and accessories
1.3 Checking of proper grounding of steel structure support for station post insulators