MAY MONTH -2018

Grade of
S.No. Qty.(m3)
Concrete
1 M15PCC 18
2 M35Pile 32.5
Total Qty(m3) 50.5

JUNE MONTH -2018


Grade of
S.No. Qty.(m3)
Concrete
1 M15PCC 110.5
2 M25RCC 127.5
3 M35Pile 74.5
Total Qty(m ) 312.5
3

JULY MONTH -2018


Grade of
S.No. Qty.(m3)
Concrete
1 M15PCC 135
2 M25RCC 148.5
3 M35RCC 53
4 M35PUMP 543.5
5 M35PILE 35
Total Qty(m )
3
915

AUGUST MONTH -2018


Grade of
S.No. Qty.(m3)
Concrete
1 M15PCC 36.5
2 M25RCC 147.5
3 M35RCC 185.5
4 M35PUMP 71.5
5 M35PILE 170.5
Total Qty(m3) 611.5

SEPTEMBER MONTH -2018


Grade of
S.No. Qty.(m3)
Concrete
1 M15PCC 38.5
2 M25RCC 157
3 M35RCC 100
4 M35PUMP 50.5
5 M35PILE 230.5
Total Qty(m3) 576.5

OCTOBER MONTH -2018


Grade of
S.No. Qty.(m3)
Concrete
1 M15PCC 103
2 M25RCC 99
3 M35RCC 105
4 M35PUMP 170.5
5 M35PILE 290
Total Qty(m3) 767.5

NOVEMBER MONTH -2018


Grade of
S.No. Qty.(m3)
Concrete
1 M15PCC 62.5
2 M25RCC 61.5
3 M35RCC 60
4 M35PUMP 725.5
5 M35PILE 194.5
Total Qty(m3) 1104

DECEMBER MONTH -2018


Grade of
S.No. Qty.(m3)
Concrete
1 M15PCC 108.5
2 M25RCC 342
3 M35RCC 101.5
4 M35PUMP 814
5 M35PILE 295
6 M45RCC 124.5
Total Qty(m3) 1785.5

JANUARY MONTH-2019
Grade of
S.No. Qty.(m3)
Concrete
1 M15PCC 79.5
2 M25RCC 163
3 M35RCC 83
4 M35PUMP 976.5
5 M35PILE 47
6 M45RCC 247
Total Qty(m3) 1596

FEBURARY MONTH -2019


Grade of
S.No. Qty.(m3)
Concrete
1 M15PCC 47.5
2 M25RCC 56.5
3 M35RCC 42
4 M35PUMP 481
5 M35PILE 254.5
6 M45RCC 228
Total Qty(m3) 1109.5

MARCH MONTH -2019


Grade of
S.No. Qty.(m3)
Concrete
1 M15PCC 40
2 M25RCC 0
3 M35RCC 0
4 M35PUMP 672
5 M35PILE 140
6 M45RCC 269.5
Total Qty(m3) 1121.5

APRIL MONTH -2019


Grade of
S.No. Qty.(m3)
Concrete
1 M25RCC 52.00
2 M35PUMP 583.50
3 M35PILE 22.50
4 M45PSC 129.50
Total Qty(m3) 787.50

MAY MONTH -2019


Grade of
S.No. Qty.(m3)
Concrete
1 M15PCC 14
2 M25RCC 154
3 M35PILE 98.5
4 M35PUMP 405
5 M45RCC 257.5
Total Qty(m3) 929

JUNE MONTH -2019


Grade of
S.No. Qty.(m3)
Concrete
1 M15PCC 19.5
2 M25RCC 214
3 M35PUMP 175.5
4 M45RCC 108
Total Qty(m3) 517

JULY MONTH -2019


Grade of
S.No. Qty.(m3)
Concrete
1 M15PCC 28
2 M25RCC 253.5
3 M35PUMP 472
4 M20KERB 161.5
5 M45RCC 84.5
6 M30RCC 26
Total Qty(m3) 1029.5
Pinalur- Sethiyathopu Section of NH45C with Four
Lane from Km 0.000 to Km 60.250 (Design Chainage
Km 0.000 to 65.960
Client km) under
: National NHDP-IV
Highways Authorityinofthe State of
India
Authority Engineer : Theme Engineering Services Private Limited
EPC Contractor : Reliance Infrastructure Limited
ARY OF SITE CONCRETE PROGRESS FOR THE MONTH OF AUGUST 201
e
Date Part Strength(N/
of Locat Struc of Grad Qty at at
S.No. Side
Casti ion ture Struc e (m ) 7day 28da
3

ng ture s ys
1 ### 19+400 LHS MJB IG-71 M45RCC 21 37.78
2 ### 18+721 LHS MNB A2-RETAM25RCC 2 20.00
3 ### 18+721 LHS MNB A2-RETAM25RCC 2 19.41
4 02.08.2019
12+284 BHS BC SLAB M25RCC 27.5 19.56
5 ### 19+400 LHS MJB MEDIANM25RCC 4.5 19.56
6 ### 12+589 LHS MNB A1-PCC M15PCC 1.5 12.00
7 ### 18+721 LHS MNB A1-RET
M25RCC 3.5
8 ### 12+589 LHS MNB A1-RET
M25RCC 5.5
9 08.08.2019
18+721 LHS BC A1&A2M25RCC 1.5
10 09.08.2019
18+677 LHS BC PARAPE
M25RCC 2.5
11 09.08.2019
12+589 LHS MNB A2-RET
M15PCC 2.5
12 ### 16+847 LHS BC PARAPE
M25RCC 2.5
1312.08.2019
12+589 LHS MNB A2-REM25RC 5.5 at 7days
14
Concrete Production Quantity Details
Grade M35 M45 RCC
/ M15 PCC
M25 RCC
M35 RCC
M35 PilePump M20KERB
M30RCCTOTAL
Month

May - 18 18 0 0 32.5 0 0 0 0 50.5


Jun - 18 110.5 127.5 0 74.5 0 0 0 0 312.5
July - 18 135 148.5 53 35 543.5 0 0 0 915
Aug - 18 36.5 147.5 185.5 170.5 71.5 0 0 0 611.5
Sep - 18 38.5 157 100 230.5 50.5 0 0 0 576.5
Oct - 18 103 99 105 290 170.5 0 0 0 767.5
Nov - 18 62.5 61.5 60 194.5 725.5 0 0 0 1104
Dec - 18 108.5 342 101.5 295 814 124.5 0 0 1785.5
JAN-19 79.5 163 83 47 976.5 247 0 0 1596
FEB-19 47.5 56.5 42 254.5 481 228 0 0 1109.5
MAR-19 40 0 0 140 672 269.5 0 0 1121.5
APR-19 0 52 0 22.5 583.5 129.5 0 0 787.5
MAY - 19 14 154 0 98.5 405 257.5 0 0 929.0
JUN-19 19.5 214 0 0 175.5 108 0 0 517.0
JULY-19 28 253.5 0 0 472 84.5 161.5 26 1025.5
TOTAL 841.0 1976.0 730.0 1885.0 6141.0 1448.5 161.5 26.0 ###
INTERNAL 221 54.5 - - - - - -
SBE - PIPL37.5 48.5 2 250 -72 1.5 0 0
TOTAL 1099.5 2079.0 732.0 2135.0 6069.0 1450.0 161.5 26.0
###