SWEIHAN PROJECT

STATUS KRINNER SCREW/


FOUNDATION
30-08-2018
AGENDA
• SUPPLY STATUS
• ENTIRE PROJECT SEQUENCE PLAN
• TOTAL PROGRESS SUMMARY
• SCREW WORK BAR CHART
• DAILY REMEDIATION PROGRESS STATUS
• REMEDIATION PRIORITY PLAN FOR A WEEK
• PMV STATUS

2
SUPPLY STATUS
KRINNER - SCREW AND CLAMPS SUMMARY - ZONE 2/3/4 Date-16.08.2018
Krinner Screws S235
Sr.no Item Description Recd.Qty
1 KSF S 60X2330 CQ+N8-S235 Ground Screw 24,857
2 KSF S 60X2582 CQ+N8-S235 Ground Screw 25,051
3 KSK S 60X2834 CQ+N8-S235 Ground Screw 25,036
Total (A) 74,944
Krinner Screws S355
Sr.no Item Description Recd.Qty
1 KSF S 60X2079 CQ+N8-S355 Ground Screw 21,094
2 KSF S 60X2582 CQ+N8-S355 Ground Screw 30,360
3 KSK S 60X2834 CQ+N8-S355 Ground Screw 30,276
4 KSF S 60X2330 CQ+N8-S355 Ground Screw 36,263
6 KSF S 60X2260 CQ+N8-S355 Ground Screw 137,936
7 KSF S 60X2530 CQ+N8-S355 Ground Screw 130,555
8 KSF S 60X2800 CQ+N8-S355 Ground Screw 133,770
9 KSF S 60X3085 CQ+N8-S355 Ground Screw 20,754
10 KSF S 60X1990 CQ+N8-S355 Ground Screw 19,470
11 KSF S 60X3340 CQ+N8-S355 Ground Screw 1,509
12 KSF S 60X3070 CQ+N8-S355 Ground Screw 5,134
Total (B) 567,121
  Grand totol (A+B) 642,065
Sr.no Item Description Recd.Qty
1 Clamp Collar Flex V Pre -Assembled 1,251,000

3
Entire project SEQUENCE plan
• Zone 1:- 10, 35, 21 (3 No.s)
• Zone 2:- WORK COMPLETED
• Zone 3A:- 97 (1 No.s)
• Zone 3B:- 99 (1 No.s)
• Zone 4:- WORK COMPLETED

4
Entire project SEQUENCE plan
PLAN SEQUENCE FOR KRINNER INSTALLATION SCREWS WORKS:-
Direct screwing Direct Screwing DRILLING ROBOT SCREWS MISSING SCREWS
SR. NO. WEEK DATE 1 ST TEAM (4 KRD) 2 ND TEAM (4 KRD) 3RD TEAM (2KRD) 4th Team (5 KRD) 5th Team (1 KRD) TOTAL TO GO
ZONES BLOCK N0 MODULE TYPE (W) ZONES BLOCK N0 MODULE TYPE (W) ZONES BLOCK N0 Blcok No Road Blcok No Road
1 29/07/2018                          
2 30/07/2018                          
3 1 31/07/2018       Z3 141 370              
4 01/08/2018                          
5 02/08/2018                          
    03/08/2019                          
6 04/08/2018 Z4 182 370       38 370          
7 05/08/2018       Z4 162 355              
8 06/08/2018                          
2
9 07/08/2018                          
10 08/08/2018                          
11 09/08/2018 Z4 183 370                    
    8/10/2018                          
12 11/08/2018       Z3 100 365              
13 12/08/2018                          
14 13/08/2018 Z4 195 370                    
3
15 14/08/2018                          
16 15/08/2018       Z3 101 scrweing 370 98 370          
17 16/08/2018 Z4 196 370                    
    8/17/2018                          
18 18/08/2018                          
19 19/08/2018 Z2 95 370                    
20 20/08/2018       Z3 79 365              
4
21 21/08/2018                          
22 22/08/2018                          
23 23/08/2018                          
    8/24/2018                          
25 25/08/2018                          
26 26/08/2018                          
27 27/08/2018 Z2 76 370                    
5
28 28/08/2018                          
29 29/08/2018 Z4 196 370 Z1 10 360              
30 30/08/2018             97 355          
31   8/31/2018                          
5
Entire project SEQUENCE plan
32 9/1/2018                 MARKING 10/11/12      
33 9/2/2018                 INSTALLATION 10/11/12      
34 9/3/2018 Z4 198 365 Z1 20 365     INSTALLATION 10/11/12      
6 9/4/2018                 MARKING 7/8/9 113, 114, 119 7
35  
36 9/5/2018                 INSTALLATION 7/8/9 117, 140, 139 7  
9/6/2018                 INSTALLATION 7/8/9 142, 158, 169, 9
37 178  
38   9/7/2018                          
39 9/8/2018       Z1 21 370     MARKING 4/5/6 89, 91, 92, 94 6  
40 9/9/2018                 INSTALLATION 4/5/6 162, 188 10  
41 9/10/2018 Z4 199 365 Z1 36 370     INSTALLATION 4/5/6 175,176, 181 10  
7
42 9/11/2018             99 370 MARKING 1/2/3 162 11  
43 9/12/2018                 INSTALLATION 1/2/3 78 6  
44 9/13/2018                 INSTALLATION 1/2/3 80, 86 6  
45   9/14/2018                          
46 9/15/2018       Z2 35 365 101 370     66, 62, 65 5  
47 9/16/2018 Z4 197 370               68 5  
48 9/17/2018                     69, 70 5  
8
49 9/18/2018 Z4 201 365               71,72 5  
50 9/19/2018                     48 4  
51 9/20/2018 Z4 200 360               49 4  
  0     4   1           5
TOTAL BLOCKS TO GO
                         
Note : 1- Robot Screws installation subjected to PO finalization 2- Missing screws subjected to clear availability of work front

 
  Work Completed  
  Work in Progress  

6
TOTAL PROGRESS Summary

ZONE BLOCKS MARKING % INSTALLATION % REMEDIATION %

1 36 33 92% 32 89% 32 89%

2 51 51 100% 51 100% 50 98%

3A 30 30 100% 30 100% 29 97%

3B 33 32 97% 32 97% 32 97%

4 51 51 100% 51 100% 51 100%

Total 201 197 98% 196 98% 194 97%

7
ZONEs LEVEL SCREW WORK BAR CHART for AUGUST- 2018

51 51 51 50 51 51 51 51

39
36
33 32 32 33 32 32 32 32
30 30 30 30 29 28
26

Zon-1 Zon-2 Zon-3A Zon-3B Zon-4


Blocks Marking Installation Remediation MMS

Note:- Zone 3A and Zone-4 need more screws installation by Krinner


8
DAILY REMEDIATION PROGRESS status
SCREWS REMEDIATION PROGRESS IN AUGUST 2018

8/12/2018
REMEDIATED TOUCH UP PAINT REMEDIATION
SI NO DATE ZONES BLOCK NOS SHIFT REMARKS
SCREWS QTY STATUS STATUS
1 8/1/2018 3B 141 Day 1100 WIP WIP  
2 8/2/2018 2 56 Day 1230 Completed Completed  
3 8/3/2018 2 57 Day 1270 Completed Completed  
4 8/4/2018 4 182/141 Day 990 WIP WIP 141 Completed

1 Tractor + crew given to zone 1 for missing


screws remediation
5 8/5/2018 4 182 Day 290 Completed Completed
1 Tractor + crew given to zone 4 for
remediation SCB

6 8/6/2018 3 142 Day 900 Completed Completed  


1 Tractor + crew given to zone 4 for
7 8/7/2018 3 120 Day 250 Completed Completed
remediation SCB
8 8/8/2018 4 162 Day 1220 Completed Completed  
1 Tractor + crew given to zone 1 for missing
9 8/9/2018 4 183 Day 900 WIP WIP screws remediation
10 8/10/2018 4 183/195 Day 280 Completed Completed  
1 Tractor + crew given to zone 4 for
11 8/11/2018 4 195 Day 900 WIP WIP
remediation SCB

9
remediation Priority PLAN for NEXT week

PLAN SEQUENCE FOR DAY WORKS OF SCREWS REMEDIATION WORKS:-


BLOCKS DETAILS
SR. NO. DATE
ZONES DAY SHIFT
1 11-08-2018 Z4 195
2 12-08-2018 Z4 195/100
3 13-08-2018 Z4 100
4 14-08-2018 Z4 98
5 15-08-2018 Z2 98/101
6 16-08-2018 Z4 101

10
PMV STATUS
WEEKLY PROGRESS REPORT 8/12/2018
TOPO MARKING SCREW INSTALLATION REMEDIATION
TOTAL KRINNE NUMBER NUMBER TOTAL
OF BLOCKS TOTAL NUMBER OF REMEDIATE
ZONES NUMBER TOTAL COMPLET
BALANCE
R
TOPO PLAN HEIGHT MARKING COMPLETED
OF BLOCK
SCREW COMPLETED INSTALLED
%
REMEDIATION
BLOCKS
%
S OF BLOCKS ED BLOCK NUMBERS MARKING %
BLOCK NUMBERS
SCREW
SCREWS IN
COMPLETED BLOCK
REMEDIATION
D SCREWS
SCREWS PLAN COMPLETE COMPLETE NUMBERS IN THE
D D THE ZONES COMPLETED ZONES
02, 04, 24, 26, 27, 28, 29, 02, 04, 24, 26, 27, 28, 02, 04, 24, 26, 27, 28,
30, 31, 32, 33, 25, 22, 23, 29, 30, 31, 32, 33, 25, 29, 30, 31, 32, 33, 25,
Zone 1 113,298 36 36 0 -   13, 1, 11, 12, 14, 17, 15, 32 89% 22, 23, 13, 1, 11, 12, 31 98,886 86% 11, 23, 1, 12, 13, 14, 31 97,182 86%
16, 19, 6, 8, 7, 5, 3, 9, 18, 14, 17, 15, 16, 19, 6, 8, 22, 17, 15, 16, 19, 3, 5,
34, 36 7, 5, 3, 34, 18, 9 8, 6, 7, 18, 34, 9
39, 40, 41, 42, 43, 44,
39, 40, 41, 42, 43, 44, 45, 45, 46, 47, 58, 59, 60, 39, 40, 41, 42, 43, 44,
46, 47, 58, 59, 60, 61, 78, 45, 46, 47, 58, 59, 60,
61, 78, 80, 50, 51,48,
80, 50, 51, 48, 49, 53, 54, 61, 78, 80, 50, 51, 48,
49, 52, 53, 54, 63, 64,
52, 63, 64, 67, 68, 71, 62, 49, 54, 52, 63, 53, 64,
Zone 2 156,140 51 51 0 -   65, 66, 69, 70, 81, 72, 37, 51 100% 67, 68, 71, 62, 65, 66, 50 153,464 98% 67, 68, 71, 62, 65, 66, 48 146,180 94%
83, 86, 87, 77, 90, 91, 94, 70, 69, 72, 81, 83, 86, 69, 70, 72, 81, 83, 37,
73, 74, 75, 57, 56, 95, 76, 37, 87, 77, 90, 91, 94,
86, 87, 90, 91, 77, 94,
55, 38 57, 73, 74, 75, 56, 95,
73, 95, 74, 55, 56, 75
55, 38
82, 84, 85, 88, 102, 82, 84, 85, 88, 102,
82, 84, 85, 88, 102, 103, 103, 104, 105, 106, 103, 104, 105, 106,
Zone 104, 105, 106, 107, 109, 107, 109, 110, 89, 92, 107, 109, 110, 89, 92,
3A 93,042 30 30 0 -   110, 89, 92, 108, 111, 112, 29 97% 108, 111,112, 93, 115, 28 86,602 93% 111, 108, 112, 93, 96, 27 80,406 90%
93, 96, 115, 116, 118, 113,
114, 119, 117, 79, 98, 100 96, 119, 118, 116, 113, 116, 118, 119, 113,
114, 117, 79, 100 114, 115, 117, 79
122, 123, 124, 125, 122, 123, 124, 125,
122, 123, 124, 125, 126, 126, 127, 128, 129 , 126, 128, 129, 144,
127, 128, 129 , 132, 130, 132, 130, 144, 145, 145, 148, 149, 121,
Zone 103,176 144, 145, 148, 149, 148, 149, 121, 152, 152, 153, 156, 157,
33 33 0 -   121,152, 153, 156, 157, 32 97% 31 98,968 94% 31 96,768 94%
3B 131, 134, 135, 133, 136, 153, 156, 157, 131, 127, 130, 131, 132,
137, 140, 139, 138, 142, 134, 135, 133, 136, 134, 135, 133, 136,
120, 141, 101 137, 140, 139, 138, 137, 140, 139, 138,
120, 142, 141 120, 142, 141

143, 146, 147, 163, 143, 146, 147, 163,


143, 146, 147, 163, 164, 164, 165, 166, 167, 164, 165, 166, 167,
165, 166, 167, 169, 186, 169, 186, 187, 170, 169, 186, 187, 170,
187, 170, 168, 171, 173, 168, 171, 173, 174, 171, 168, 150, 151,
174, 150, 151, 154, 155, 150, 151, 154, 155, 154, 155, 174, 158,
158, 177, 178, 181, 159,
Zone 4 157,550 51 51 0 -   160, 161, 172, 175, 176, 50 98% 158, 177, 178, 181, 45 140,556 88% 177, 178, 181, 173, 44 135,140 86%
179, 189, 192, 193, 182, 159, 160, 161, 175, 159, 160, 161, 175,
183, 188, 185, 190, 191, 172, 176, 179, 189, 172, 176, 179, 189,
194, 184, 196, 198, 199, 192, 193, 188, 190, 192, 193, 188, 190,
180, 162, 195, 197, 200 184, 191, 194, 185, 184, 191, 194, 185,
180, 182, 162, 183, 195 180, 182, 162, 183

Total 623,206 201 201 0       194 97%   185 578,476 92%   181 555,676 90%

11