SWEIHAN PROJECT

STATUS KRINNER SCREW/


FOUNDATION
27-05-2018
AGENDA
• SUPPLY STATUS
• ENTIRE PROJECT SEQUENCE PLAN
• TOTAL PROGRESS SUMMARY
• SCREW WORK BAR CHART
• DAILY REMEDIATION PROGRESS STATUS
• REMEDIATION PRIORITY PLAN FOR A WEEK
• PMV STATUS

2
SUPPLY STATUS

3
Entire project SEQUENCE plan

• Zone 1:- 16, 19, 35, 36, 34, 9, 6, 8, 3, 5, 7, 18, 20, 21, 10
• Zone 2:- 65, 66, 69, 70, 81, 83, 86, 87, 90, 91, 73, 72, 74, 75, 94, 95 76, 56,57,77,
37
• Zone 3A:- 113, 114, 117, 140, 100, 98, 79, 97
• Zone 3B:-133, 136, 137, 139, 138, 142, 141, 120, 99, 101
• Zone 4:- 181, 172, 175, 176, 179, 180, 159, 160, 161, 184, 185, 182, 183, 188,
189, 192, 193, 190, 191, 194, 195, 196, 198, 199, 201, 197, 200, 162
• Blue colour:- Topo Plan
• Red colour:- Topo Completed. Note - Height plan is awaiting from Krinner
(Germany).

4
TOTAL PROGRESS Summary

ZONE BLOCKS MARKING % INSTALLATION % REMEDIATION %

1 36 27 75% 25 69% 20 52%

2 51 32 62% 30 58% 25 49%

3A 30 26 86% 23 76% 22 73%

3B 33 25 75% 23 69% 19 57%

4 51 24 47% 23 45% 22 43%

Total 201 134 66% 124 61% 108 53%

5
ZONEs LEVEL SCREW WORK BAR CHART for MAY- 2018

51 51

36
32 33
31 30
28 28
25 26 25 26 25
23 23 24 24 23
21 22
18 18
16
14

Zon-1 Zon-2 Zon-3A Zon-3B Zon-4


Blocks Marking Installation Remediation MMS

Note:- Zone 3A and Zone-4 need more screws installation by Krinner.


6
DAILY REMEDIATION PROGRESS status

7
DAILY REMEDIATION PROGRESS status

8
DAILY REMEDIATION PROGRESS status

9
remediation Priority PLAN for NEXT week
PLAN SEQUENCE FOR DAY & NIGHT WORKS OF SCREWS REMEDIATION WORKS:-
BLOCKS DETAILS
SR. NO. DATE
ZONES DAY SHIFT ZONES NIGHT SHIFT
1 26.05.18 Z1 17 Z3B 132
2 27.05.18 Z1 15 Z2 68
3 28.05.18 Z1 & Z3A 15 & 119 Z2 68 &71
4 29.05.18 Z3A 119 Z2 71
5 30.04.18 Z4 178 Z3B 134
6 31.05.18 Z4 178 & 181 Z3B 134 & 135
7 01-06-2018 Z4 181 Z3B 135
8 02-06-2018 Z1 16 Z2 62
9 03-06-2018 Z1 16 &19 Z2 62 &65
10 04-06-2018 Z1 19 Z2 65
10
PMV STATUS

11