SUPPLY STATUS
3
Entire project SEQUENCE plan
• Zone 1:- 16, 19, 35, 36, 34, 9, 6, 8, 3, 5, 7, 18, 20, 21, 10
• Zone 2:- 65, 66, 69, 70, 81, 83, 86, 87, 90, 91, 73, 72, 74, 75, 94, 95 76, 56,57,77,
37
• Zone 3A:- 113, 114, 117, 140, 100, 98, 79, 97
• Zone 3B:-133, 136, 137, 139, 138, 142, 141, 120, 99, 101
• Zone 4:- 181, 172, 175, 176, 179, 180, 159, 160, 161, 184, 185, 182, 183, 188,
189, 192, 193, 190, 191, 194, 195, 196, 198, 199, 201, 197, 200, 162
• Blue colour:- Topo Plan
• Red colour:- Topo Completed. Note - Height plan is awaiting from Krinner
(Germany).
4
TOTAL PROGRESS Summary
5
ZONEs LEVEL SCREW WORK BAR CHART for MAY- 2018
51 51
36
32 33
31 30
28 28
25 26 25 26 25
23 23 24 24 23
21 22
18 18
16
14
7
DAILY REMEDIATION PROGRESS status
8
DAILY REMEDIATION PROGRESS status
9
remediation Priority PLAN for NEXT week
PLAN SEQUENCE FOR DAY & NIGHT WORKS OF SCREWS REMEDIATION WORKS:-
BLOCKS DETAILS
SR. NO. DATE
ZONES DAY SHIFT ZONES NIGHT SHIFT
1 26.05.18 Z1 17 Z3B 132
2 27.05.18 Z1 15 Z2 68
3 28.05.18 Z1 & Z3A 15 & 119 Z2 68 &71
4 29.05.18 Z3A 119 Z2 71
5 30.04.18 Z4 178 Z3B 134
6 31.05.18 Z4 178 & 181 Z3B 134 & 135
7 01-06-2018 Z4 181 Z3B 135
8 02-06-2018 Z1 16 Z2 62
9 03-06-2018 Z1 16 &19 Z2 62 &65
10 04-06-2018 Z1 19 Z2 65
10
PMV STATUS
11