SWEIHAN PROJECT

STATUS KRINNER SCREW/


FOUNDATION
16-07-2018
AGENDA
• SUPPLY STATUS
• ENTIRE PROJECT SEQUENCE PLAN
• TOTAL PROGRESS SUMMARY
• SCREW WORK BAR CHART
• DAILY REMEDIATION PROGRESS STATUS
• REMEDIATION PRIORITY PLAN FOR A WEEK
• PMV STATUS

2
SUPPLY STATUS

BALANCE QUANTITY – 43,137 NO.S


3
Balance quantity is tentatively supplied by 4nd Week of July 2018
Entire project SEQUENCE plan
• Zone 1:- 20, 21, 35, 10 (4 No.s)
• Zone 2:-
• 75, 95, 76 North Sequence (4 No.s)
• 56, 55, 38 South Sequence (4 No.s)
• Zone 3A:- 100, 98, 79, 97 (4 No.s)
• Zone 3B:- 120, 142, 99, 101, 141(5 No.s)
• Zone 4:-
• 190, 191, 194, 182, 183, 180, 196, 198, 199, 201, 197, 200 One Sequence (14 No.s)
• 184, 185, 162, 195 Parallel Sequence (4 No.s)

• Red colour :- Height plan is awaiting from Krinner (Germany).


• Blue colour :- Hold by Zone
4
TOTAL PROGRESS Summary

ZONE BLOCKS MARKING % INSTALLATION % REMEDIATION %

1 36 32 89% 31 86% 31 86%

2 51 49 96% 45 88% 43 84%

3A 30 26 87% 26 87% 26 87%

3B 33 30 91% 29 88% 29 88%

4 51 44 86% 36 71% 35 69%

Total 201 181 90% 167 83% 164 82%

5
ZONEs LEVEL SCREW WORK BAR CHART for JULY- 2018

51 51
49
45 44
43

36 36 35
32 33 33
31 31 30 30 29 29
26 26 26 26 27
25
22

Zon-1 Zon-2 Zon-3A Zon-3B Zon-4


Blocks Marking Installation Remediation MMS

Note:- Zone 3A and Zone-4 need more screws installation by Krinner


6
DAILY REMEDIATION PROGRESS status

7
remediation Priority PLAN for NEXT week
PLAN SEQUENCE FOR DAY & NIGHT WORKS OF SCREWS REMEDIATION WORKS:-
BLOCKS DETAILS
SR. NO. DATE
ZONES DAY SHIFT ZONES NIGHT SHIFT
1 08-07-2018 Z4 193 - -
2 09-07-2018 Z2 73 - -
3 10-07-2018 Z3B 120 - -
4 11-07-2018 Z2 57 - -
5 12-07-2018 Z4 182 - -
6 14-07-2018 Z3B 142 - -
7 15-07-2018 Z4 183 - -

NOTE:- Plan effective from Monday 09.07.18, there will be a S&W remediation team in each Zone taking direction
from each Zone CM/Co-Ordinator/S&W Remediation Manager for reporting purpose.

8
PMV STATUS