AUH - QA&QC - MS - 01 Receiving Inspection PDF
AUH - QA&QC - MS - 01 Receiving Inspection PDF
Rev: 00
RECEIVING INSPECTION
Page: 1 of 5
METHOD STATEMENT
FOR
RECEIVING INSPECTION
1. OBJECTIVE
2. SCOPE
This method statement covers all incoming material & equipment received from
customer or purchased by AUH Office or Projects.
3. REFERENCES
− Project specifications
− PO/Packing list
− Vendor supplied drawings/documents
− All applicable codes and standards
− MTCs
− Indent
− Delivery Chalan
4. ABBREVIATIONS/DEFINATIONS
SM Site Manager
QIP Quality Inspection Plan
I/C Incharge
QA&QC Quality Assurance & Quality Control
E&P Equipment and Plant
MS Method Statement
PO Purchase Order
MIR Material Inspection Report
HSE Health, Safety & Environment
MTC Material Test Certificate
IMTE Inspection, Measuring & Test Equipment
BA Business Area
FRM Form
5. RESPONSIBILITIES
6. PROCEDURE
− Standard Items
− Project Specific Items
− E&P Items
− Tools
− Fixed Assets
− Manufactured Items
a) Standard Items
c) E&P Items
d) Tools
e) Fixed Assets
The user and QA&QC shall inspect fixed asset items at receiving
stores.
f) Manufactured Items
− Specifications
− Packing condition
− Inspection report of the manufacturer (If applicable)
− Physical condition
− MTC (if required)
6.2.7 Materials, such as crush, sand, bricks, loose earth, POL and
cement etc., are usually procured through Rate Running Contract
(RRC) arrangement. Their samples/sources shall be approved by
BA/Project QA&QC at the beginning of the project. Subsequent
deliveries shall in any case be inspected by site QA&QC regularly.
6.2.9 Inspection of the imported material shall be carried out by the I/C
QA&QC/User at the receiving stores.
6.2.10 Procurement shall ensure that all the materials, if rejected, shall be
returned to suppliers at the latter’s own risk and cost.
− Vernier Caliper
− Meter Tape
− Micrometer
− Battery Torch
− Welding Gauge
− Elcometer
8. HSE INSTRUCTIONS
- HSE instructions will be carried out under responsibility of I/C HSE for
safe and sound receipt of material / equipment.
- Keep your environment clean.
- No smoking is permitted in the restricted areas.
9. RELATED DOCUMENTS