Principal Contractor : Petrofac Engineering & Construction

Subcontractor: Al Musairie National
Sub‐Contract Title : Offplot Civil Works (Pipelines & Cables) for Effluent Water Injection NK‐Ph I/ Central Seawater Injection NK‐Ph II, Kuwait
Project No : JI 2004
MANPOWER MOBILIZATION PLAN

PROJECT DURATION
MONTHS
Sl No. Manpower Description
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Oct‐11 Nov‐11 Dec‐11 Jan‐12 Feb‐12 Mar‐12 Apr‐12 May‐12 Jun‐12 Jul‐12 Aug‐12 Sep‐12 Oct‐12 Nov‐12 Dec‐12

I INDIRECT MANPOWER
1 Project Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 Construction Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Project Engineer 1 2 2 2 2 2 2 2 2 2 2 1 1 1 1
4 Planning Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
5 Safety Personnel 2 4 6 7 8 8 8 8 8 8 5 4 1 1 1
6 QC Personnel 2 2 3 3 3 3 3 3 3 3 3 2 2 2 2
7 Site Supervisor 2 2 4 4 4 4 4 4 4 4 4 2 2 2 2
Subtotal ‐ Indirect 10 13 18 19 20 20 20 20 20 20 17 12 9 9 9

II DIRECT MANPOWER
1 Foreman 3 8 12 26 28 30 30 30 30 30 20 16 4 2 2
2 Surveyor 2 3 3 3 3 3 3 3 3 3 3 3 1 1 0
3 Skilled Labour 16 42 60 66 73 79 79 79 79 78 51 40 12 5 5
4 Semi skilled Labour 24 63 92 100 111 121 121 121 121 119 77 61 18 7 8
5 Unskilled Labour 32 85 124 121 135 148 148 148 148 145 93 75 22 9 9
Subtotal ‐ Direct 77 201 291 316 350 381 381 381 381 375 244 195 57 24 24

TOTAL INDIRECT & DIRECT MANPOWER 87 214 309 335 370 401 401 401 401 395 261 207 66 33 33