WATER TRUCK UTILIZATION

Water Truck 1 (9722) Water Truck 2(4155)


Date 06/06/2012 (7:15-17:30) Total Observation time = 300 min
1.0 Cycles / Filling 1 cyc 1 cyc

2.1 Curing 150 min 120 min


2.2 Backfill 30 min 105 min
Filling Up(including Waiting
2.3 time) 90 min 75 min

Watering of Form/Refill
2.4 Water Tanks 30 min 0 min
TOTAL 300 min 300

Date 07/06/2012 (7:15-17:30) Total Observation time = 555 min


1.0 Cycles / Filling 2 cyc 2 cyc

2.1 Curing 255 min 450 min


2.2 Backfill 210 min 45 min
Filling Up(including Waiting
2.3 time) 45 min 60 min

Watering of Form/Refill
2.4 Water Tanks 45 min min
TOTAL 555 min 555

Date 09/06/2012 (11:30-17:30) Total Observation time = 300 min


1.0 Cycles / Filling cyc 1 cyc

2.1 Curing Insufficient DATA min 135 min


2.2 Backfill min 45 min
Filling Up(including Waiting
2.3 time) min 60 min
Watering of Form/Refill
2.4 Water Tanks min 60 min
TOTAL 0 min 300

Date 10/06/2012 (11:30-17:30) Total Observation time = 600 min


1.0 Cycles / Filling 3 cyc 3 cyc

2.1 Curing 210 min 225 min


2.2 Backfill 75 min 210 min
Filling Up(including Waiting
2.3 time) 150 min 120 min
Watering of Form/Refill
2.4 Water Tanks 165 min 45 min
TOTAL 600 min 600
Water Truck 2(6406)
e = 300 min
1 cyc

240 min
60 min

0 min

0 min
300 min

e = 555 min
2 cyc

390 min
30 min

135 min

0 min
555 min

me = 300 min
1 cyc

165 min
min

30 min

105 min
300 min

me = 600 min
2 cyc

420 min
0 min

135 min

45 min
600 min
WATER TRUCK UTILIZATION LOG
DATE:
Time Water Truck 1 (9722) Water Truck 2(4155)

Refill water tank @ B -08-10 Spray water on backfill @B-12-1


11:30
Finish refilling of water tank @
B-08-10
11:45

Break Break
12:00

Waiting @ B-08-9
13:00

Curing of foundation @ B08-9


13:15

Spray water on backfill @B-12-1


13:30

13:45

Curing of foundation @ B09-2


14:00

Curing of parapet @ B-5-3


14:15

14:30

Spray water on backfill @ B-09-3


14:45

Curing of grade beam @ B-09-1


15:00

15:15
Curing of footing @ B-11-8 /
Curing of column @ B-11-9
15:30

Spray water on backfill @B-07-1


15:45
Water truck empty proceed to
refilling station
16:00

Spray water on backfill @B-07-1


16:15
16:30

Refilling station Spray water on backfill @B-07-1


16:45

Curing of Column @ B-13-1


17:00

Curing of footing @ B-103-1


17:15
Finish spraying of water @ B- Finish watering of column @ B-
103-1 13-1
17:30
WATER TRUCK UTILIZATION LOG
6/6/2012
Water Truck 2(6406)

Curing of Grade Beam @ B-02-1

Break

Curing of Grade Beam @ B-02-1

Curing of Grade Beam @ B-02-1

Curing of Slab @ B-04-1

Spray water on grade beam


forms @ B-08-6

Curing of slab @ B-04-1


Curing of slab @ B-04-1

Spray water on backfill @ B-17-2

Sandby @ B-17-2
WATER TRUCK UTILIZATION LOG
DATE:
Time Water Truck 1 (9722) Water Truck 2(4155)

Curing of column @ B-11-10 Not on the site


7:15

7:30

Curing of foundation @ B-08-9


7:45

Curing of column @ B-38-1


8:00

8:15

Curing of column @ B-09-2


8:30

Curing of grade beam @ B-09-1


8:45

Curing of foundation @ B-103-1


9:00

Curing of grade beam @ B-09-1


9:15

Curing of column @ B-11-4


9:30

Curing of column @ B-13-1


9:45

Curing of column @ B-11-3


10:00

10:15

Spray water on backfill @ B-8-11


10:30

Curing of column @ B-13-1


10:45

Curing of footing @ B-11-8


11:00

11:15
Curing of column @ B-11-10
11:30

Curing of column @ B-13-1


11:45

- Stopby @ B-38-1
12:00

Stop @ refilling station Curing of column @ B-38-1


13:00

13:15

Curing of column @ B-38-1


13:30

Spray water on backfill @ B-09-3


13:45
Curing of roof slab & beam @ B-
05-5
14:00
Water truck empty proceed to
refilling station
14:15

Spray water on backfill @ B-09-3


14:30

14:45
Spray water on backfill @ B-08-
12
15:00

Curing of parapet @ B-05-4


15:15

15:30
Spray water on backfill @ B-08-
12
15:45

Curing of parapet @ B-05-3


16:00

16:15

Refilling of water tank @ B-04-3


16:30

Curing of grade beam @ B-09-1


16:45
17:00

Spray water on backfill @ B-02-3 Curing of grade beam @ B-09-1


17:15
Finish watering on backfill Finish watering @ grade beam @
@ B-02-3 B-09-1
17:30
WATER TRUCK UTILIZATION LOG
7/6/2012
Water Truck 2(6406)

Not on site

Curing of grade beam @ B-02-1

Spray water on backfill @ B-17-2

Curing of roof slab @ B-04-1

Curing of roof slab @ B-04-1

Curing of grade beam @ B-02-1

Curing of grade beam @ B-02-1

Curing of roof slab & beam @ B-


08-1
Curing of roof slab & beam @ B-
08-1

Stopby @ B-08-1

Curing of roof slab & beam @ B-


08-1

Curing of roof slab & beam @ B-


08-1

Curing of grade beam @ B-02-1

Water truck empty proceed to


refilling station

Not on site
Not on site
WATER TRUCK UTILIZATION LOG
DATE:
Time Water Truck 1 (9722) Water Truck 2(4155)

Refill watere tank @ B-11-7 Refill water tank @ B-05-2


11:30

11:45

Onsite @ B-17-1 Onsite @ B-05-2


12:00

13:00

13:15

Spray water on backfill @ B-12-1


13:30

13:45

14:00

Curing of parapet @ B-05-5


14:15

14:30

Curing of parapet @ B-05-3


14:45

15:00

Curing of parapet @ B-05-4


15:15

15:30

Curing of grade beam @ B-09-1


15:45

16:00

16:15
Water truck empty proceed to
refilling station
16:30

16:45

17:00

17:15

Stop @ refilling station


17:30
WATER TRUCK UTILIZATION LOG
9/6/2012
Water Truck 2(6406)

Curing of grade beam @ B-02-1

Onsite @ B-02-1

Curing of grade beam @ B-02-1

Refill water tank @ B-17-1

Curing of grade beam @ B-08-6

Refill water tank @ B-08-6

Refill water tank @ B-17-2


Water truck empty proceed to
refilling station

Stop @ refilling station


WATER TRUCK UTILIZATION LOG
DATE:
Time Water Truck 1 (9722) Water Truck 2(4155)

on site @ B-11-10 onsite @ B-07-1


6:30

6:45
Curing of neck column @ B-11- Spray water on backfill @ B-38-1
10
7:00

7:15

7:30

Curing of neck column @ B-11-7


7:45

Curing of grade beam @ B-09-1


8:00

Curing of neck column @ B-02-2


8:15

8:30

Curing of grade beam @ B-09-1


8:45

Spray water @ B-80


9:00
Curing of parapet @ B-05-3 & B-
05-4
9:15

9:30
Water truck empty proceed to
refilling station
9:45

Curing of parapet @ B-05-5


10:00
Water truck empty proceed to
refilling station
10:15

10:30
10:45

Refill water tank @ B-08-10 Refill water tank @ B-05-3


11:00

11:15

11:30

Spray water on backfill @ B-07-1


11:45

On site @ B-08-10 onsite @ B-07-1


12:00

Refilling of water tank @ B-08-9 Spray water on backfill @ B-07-1


13:00

13:15

13:30

Spray water on backfill @ B-13-2


13:45

Spray water on bakfill @B-05-2


14:00
Water truck empty proceed to
Refilling of water tank @ B-02-2 refilling station
14:15

14:30
Water truck empty proceed to
refilling station
14:45

Spray water on backfill @ B-05-2


15:00

15:15

Curing of foundation @ B-11-7


15:30

15:45

Curing of grade beam @ B-09-1


16:00
Curing of neck column @ 11-10
16:15

16:30

Curing of grade beam @ B-09-1


16:45

Refilling of water tank @ B-08-10


17:00
Curing of parapet @ B-05-3 & B-
05-4
17:15

Not on site Not on site


17:30
WATER TRUCK UTILIZATION LOG
10/6/2012
Water Truck 2(6406)

Not on site

Curing of column @ B-08-4

Curing of column @ B-08-6

Curing of column @ B-08-4

Refilling of water tank @ B-05-2

Water truck empty proceed to


refilling station
Curing of neck column @ B-11-3

onsite @ B-11-3

Curing of neck column @ B-11-4

Curing of neck column @ B-11-4

Curing of grade beam @ B-08-6

Curing of grade beam @ B-08-6

Curing of slab @ B-04-1


Curing of slab @ B-04-1

Curing of slab @ B-04-1

Finish watering of slab @ B-04-1

Not on site