BOQ

EQUIPMENT MANPOWER
DESC ITEM QTY UNIT I.D PROD I.D PRO CALCULATION DUR

1 Excavation 10,000 m3 Excavator 450 m3 / day 10,000 m3 * day / (450m3 * 2 exca) 10

2 Lean Concrete 7

3 Foundation- Steel Fixing 40,000 kg Steel Fixer 800kg/day 40,000kg* day/(800kg * 3 fixer) 18

4 Foundation- Forming 18

5 Foundation- Pouring 7

6 Columnneck -Steel Fixing 10

7 Column neck- Forming 10

8 Columnneck- Pouring 4

9 Tiebeam- Steel Fixing 10

10 Tiebeam-Forming 10

11 Tiebeam-Pouring 4

12 Gradeslab- Steel Fixing 21

13 Gradeslab-Forming 21

14 Grade Slab-Pouring 10