Professional Documents
Culture Documents
AND CONSTRUCTION
By James L. Burati Jr., 1 Member, ASCE, Jodi J. Farrington, 2 Associate
Member, ASCE, and William B. Ledbetter, 3 Fellow, ASCE
Downloaded from ascelibrary.org by Universitas Indonesia on 09/11/19. Copyright ASCE. For personal use only; all rights reserved.
ABSTRACT: Quality deviation data are collected from nine fast-track industrial
construction projects. The data are collected after the construction phase of the
projects and identify the direct costs associated with rework (including redesign),
repair, and replacement. Analyses of the data indicate that deviations on the proj-
ects accounted for an average of 12.4% of the total project costs. Furthermore,
design deviations average 78% of the total number of deviations, 79% of the total
deviation costs, and 9.5% of the total project cost. Construction deviations average
16% of the total number of deviations, 17% of the total deviation costs, and 2.5%
of the total project cost. These values are conservative because they consider only
direct costs, but they are indications of the areas that cause the greatest impact on
total project costs. By applying the procedures presented in this paper to its his-
torical records, a company can identify not only its deviation costs, but also the
most likely areas on which to focus to reduce these costs on future projects.
BACKGROUND
In recent years, participants in the construction industry have become
increasingly aware of rising construction costs and perceptions of increased
quality problems. Business Week ("Quality" 1982) stated that manufacturers
agreed that 15-20% of their sales dollars were used to correct mistakes,
and that the way to increase profit was to reduce the cost of poor quality
rather than to increase sales. At a national conference on quality assurance
in the building community, it was suggested that the cost of poor quality
was at least 7.5% of the value of new nonresidential work, and the question
was raised as to why the construction industry did not follow the lead of
the manufacturing industry, and increase profit by reducing the costs of
quality problems (Shilstone 1983).
Research performed in conjunction with the Business Roundtable's con-
struction industry cost-effectiveness project revealed that on-site construc-
tion activities for industrial projects were perceived to be the most troubling
quality problems (Ledbetter 1983). The troublesome items were identified
as concrete, piping, welding, roofing, painting, and electrical work. In ad-
dition, investigation of the frequency and severity of claims on federally
funded and administered projects found that design errors were the single
most common cause for contract claims, accounting for 46% of the additive
claims that were reviewed (Diekmann and Nelson 1985).
These results appear to be in conflict, with one indicating that on-site
construction is the most important source of quality problems and the other
indicating that design errors are the major cause of increased costs. Ques-
tions regarding the causes, number, and costs of quality problems in design
and construction remained unanswered.
'Prof, of Civ. Engrg., Clemson Univ., Clemson, SC 29634-0911.
2
Asst. Mgr. Tech. Services, Nat. Industrial Constructors, Birmingham, A L 35243.
3
Quality Mgmt. Consultant, 1006 Challedon Way, Pendleton, SC 29670.
Note. Discussion open until August 1,1992. To extend the closing date one month,
a written request must be filed with the ASCE Manager of Journals. The manuscript
for this paper was submitted for review and possible publication on January 8, 1990.
This paper is part of the Journal of Construction Engineering and Management, Vol.
118, No. 1, March, 1992. © A S C E , ISSN 0733-9364/92/0001-0034/$1.00 + $.15 per
page. Paper No. 26562.
34
The research presented in this paper was conducted to identify the causes
and magnitude of quality problems in design and construction and to de-
termine the costs associated with the quality problems. The research was
conducted under the guidance of the quality management task force (QMTF)
of the Construction Industry Institute (CII).
Downloaded from ascelibrary.org by Universitas Indonesia on 09/11/19. Copyright ASCE. For personal use only; all rights reserved.
All CII member firms were surveyed to identify those willing to provide
projects on which quality deviation data could be collected. To allow for
meaningful comparisons, project selection was limited to industrial projects
of at least $5,000,000 in total installed costs that were completed in the
mid-1980s and that each had a different designer and constructor. Table 1
presents brief descriptions for the nine projects that were studied in detail.
Types of Construction
The projects were classified according to the following types:
e
Upgrade construction: the design and construction associated with the
modification of an existing facility, for example, technological advance-
ments and process improvements.
COLLECTION OF DATA
Wherever possible, data were collected directly from field change orders,
requests for information, or design change orders that contained complete
information concerning (1) A description of the change; (2) why the change
was required; (3) who initiated the change; and (4) the cost of the change.
When this information was not available, other sources, including cost ac-
counting tabulations and computerized project summaries, were investi-
gated. When complete information was not available from the alternate data
sources, additional information was obtained through interviews with proj-
ect representatives in order to gain sufficient understanding for analysis of
the data.
The deviation data that were collected and analyzed were limited to the
design and construction (including fabrication) phases of the projects stud-
ied. The deviation data collected included only the direct costs associated
with rework (including repair and replacement) and therefore do not con-
stitute the total costs associated with the deviations. These direct costs of
correcting deviations are only the "tip of the iceberg." Impact costs, such
as the effects of the rework on the project schedule or on other project
activities, were not generally available and are not included in the deviation
costs presented herein. In addition, no data were available on the costs
associated with quality management activities.
36
The deviation data collected on the nine projects were classified to allow
a more descriptive analysis of the causes of the deviations and their asso-
ciated costs. The deviation cost data were divided into five major areas—
design, construction, fabrication, transportation, and operability. Each of
these areas were further subdivided by type of deviation, i.e., change, error,
Downloaded from ascelibrary.org by Universitas Indonesia on 09/11/19. Copyright ASCE. For personal use only; all rights reserved.
Design Deviations
Design deviations are related to the design of the project. Design errors
(DE) are the result of mistakes or errors made in the project design. Design
omissions (DO) result when a necessary item or component is omitted from
the design. Design changes occur when changes are made in the project
design or requirements, and are further classified as follows.
37
installation of equipment.
Construction Deviations
Construction deviations are related to the construction phase of the proj-
ect and consist of those activities and tasks that take place at the project
site. A construction change (CC) is defined as a change in the method of
construction, such as placing concrete by pump father than by bucket.
Construction changes are usually made to enhance the constructability of
the project. Deviations classified as construction errors (CE) are the result
of erroneous construction methods or procedures. Construction omissions
(CO) are those deviations that occur due to the omission of some construc-
tion activity or task.
Fabrication Deviations
Fabrication deviations are related to shop fabrication. Changes, errors,
and omissions that occur during field fabrication are included in the con-
38
Transportation Deviations
Transportation deviations are related to the transport of equipment, ma-
terials, or supplies. A transportation change (TC) indicates a change in the
method of shipment, e.g., shipping by air to expedite delivery rather than
shipping by truck. Transportation errors (TE) denote errors made in trans-
porting a product, e.g., shipping an article in separate pieces when the
specifications require the shipment of an assembled product. Transportation
omissions (TO) occur when a required part or item is not included in the
appropriate shipment.
Operability Deviations
A differentiation was made between changes, errors, and omissions made
to the operation or process portion of the facility and those changes made
to improve operability. An operations change might be the use of two pumps
instead of one, or the addition of check valves in a required line; while an
operability improvement might be relocating valve handles to improve op-
erator access. Changes in operability are denoted with the deviation code
(OC), while changes made in the operation or process portion of the facility
are included in a specific design-change category. There is no need for error
or omission categories for operability since errors and omissions in opera-
bility are the result of an error or omission made in design, fabrication, or
construction.
Decision Rules
If comparisons are to be made among different projects, it is essential
that a clear and consistent set of criteria or decision rules be established to
govern the way in which the deviation costs are assigned to the various
deviation categories. Appendix II presents the decision rules that were
developed to ensure consistent classification of each deviation. The devia-
tion categories are designed to be mutually exclusive and only one complete
category should be applied to each deviation (a single deviation report may
contain several different deviations) (see Fig. 1).
The primary descriptor designates the major area, i.e., design (D), con-
struction (C), fabrication (F), transportation (T), or operability (O). The
second descriptor designates whether the deviation was a change (C), error
(E), or omission (O). The tertiary descriptor is only used to further subdivide
the design changes category (Table 2).
In some cases it may not be possible to discern a single classification from
39
ANALYSIS OF DATA
The data were analyzed both in terms of numbers and costs of deviations.
Since the size of each of the projects (in total cost) varied, comparisons of
number of deviations and deviation costs were all performed on a percentage
basis to allow comparisons among the projects. The analyses consisted of
the number of deviations, deviation costs as a percentage of total project
deviation costs, and deviation costs as a percentage of total project cost.
Number of Deviations
Table 3 presents the number of deviations in the design, construction,
fabrication, transportation, and operability areas as a percentage of the total
number of deviations on the project. The greatest number of deviations
occurred in the design and construction areas. Design deviations accounted
for 67-90% of the total number of deviations on the projects, while con-
struction deviations ranged from 5-29% of the total number of deviations.
Table 4 shows the percentage of the total number of deviations for design
changes, errors, and omissions for each project. Design changes generally
resulted in the greatest number of design deviations. An exception is project
I, which reported no design changes. Discussions with project representa-
tives revealed that for this project, changes in design were not recorded
unless they were the result of an error or omission.
Design changes for improvement (DCI) caused, on the average, the great-
est number of deviations, 13.3%, followed by design changes in process
(DCP), 10.9%, and design changes initiated by the owner (DCO), 9.9%,
while 13.2% of the total number of deviations were classified as design
changes of unknown origin (DCU).
Cost of Deviations
Table 5 presents the deviation costs for each area as percentages of the
total deviation costs for each project. Fig. 2 presents the nine-project av-
erages for the same data. Since design deviations accounted for such a large
Project
Aver-
Area A B c D E F G H 1 age
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11)
Design 66.5 89.6 74.7 88.6 73.8 84.8 69.5 75.1 80.8 78.1
Construction 25.5 8.4 15.4 5.7 19.5 4.9 28.8 12.0 19.2 15.5
Fabrication 6.0 1.0 8.5 2.3 3.7 0.3 1.4 12.4 0.0 4.0
Transportation 0.7 1.0 1.1 1.1 0.6 0.0 0.0 0.0 0.0 0.5
Operability 1.3 0.0 0.3 2.3 2.4 10.0 0.3 0.5 0.0 1.9
40
Design change/ 10.4 7.3 9.5 26.1 26.4 24.1 8.3 7.3 0.0 13.3
improvement
Design change/ 1.0 0.0 2.8 2.3 3.3 0.5 1.4 6.8 0.0 2.0
construction
Design change/ 14.8 11.5 0.0 1.1 2.7 1.9 0.0 4.7 0.0 4.1
field
Design change/ 10.4 18.8 9.7 9.1 14.6 5.7 0.2 12.1 0.0 9.0
owner
Design change/ 2.0 0.0 3.6 27.3 20.1 37.0 0.7 7.4 0.0 10.9
process
Design change/ 0.0 0.0 0.0 0.0 0.3 0.0 0.0 0.0 0.0 0.0
fabrication
Design change/ 2.7 9.4 11.5 17.1 0.3 9.7 54.1 14.2 0.0 13.2
unknown
Design change 41.3 46.9 37.1 83.0 67.8 78.9 64.7 52.4 0.0 52.5
total
Design error 24.8 26.0 24.3 5.7 4.0 5.7 4.7 21.6 60.1 19.7
Design omission 0.3 16.7 13.3 0.0 2.1 0.3 0.1 1.2 20.7 6.1
Design total 66.4 89.6 74.7 88.7 73.9 84.9 69.5 75.2 80.8 78.3
Fabrication
3.3%
Design
79.1%
DCP
DCI
_ . --. DCU 14.3%
Design '"--..17.3%
Deviations
Design Changes
(54.2%)
42
Construction
2.5%
Design
Deviations
Design Changes
(7.9%)
sign and construction, therefore, were the primary causes of both the number
of deviations and increases in project costs.
• i Other
I I Construction
O 41 H H Design
CD 31
A
E 21
3
2
1(
for design (Table 8) are consistent with the average number of deviations
for design (Table 7). Upgrade projects had the highest percentage of total
deviation cost in the DCI and DCP categories. Similarly, the retrofit average
percentage of total deviation cost in the DCF category exceeds the upgrade
and new construction averages.
Analysis of the construction deviations for the three types of construction
reveals that the new construction projects had the greatest average number
of construction errors and omissions, but that construction errors and omis-
sions on the retrofit projects had the greatest average impact on total de-
viation costs. Construction changes for the upgrade projects were not as
numerous as for the new and retrofit projects, but they had a greater impact
on total project costs for the upgrade projects. Thus, a better understanding
44
Type of Construction
Deviation category New Retrofit Upgrade
0) (2) (3) (4)
Construction change 1.8 1.7 3.7
Downloaded from ascelibrary.org by Universitas Indonesia on 09/11/19. Copyright ASCE. For personal use only; all rights reserved.
Total
Design
Construction
Other
ANALYSIS OF RESULTS
For the projects studied, identified deviation costs averaged 12.4% of the
total installed project cost. This value is only the tip of the iceberg. Dis-
cussions with representatives of the projects studied indicated that not all
of the deviations on a project were recorded. Construction changes made
at the site were often not included in formal reports, and errors were often
repaired and/or accepted immediately rather than expending the time and
effort to file formal requests. The deviation data gathered included only the
45
CONCLUSIONS
The two major areas resulting in deviations were design and construction.
Design deviations averaged 78% of the total number of deviations, 79% of
the total deviation costs, and 9.5% of the total project cost for the nine
projects studied. Furthermore, design changes accounted for two-thirds of
the design deviations. Construction deviations accounted for 16% of the
total number of deviations, 17% of the total deviation costs, and 2.5% of
the total project cost. These results indicate that rework costs are a signif-
icant portion of total costs.
The analyses presented in this paper demonstrate that a methodology to
categorize historical data can be used to identify the type and number of
quality deviations and their associated rework costs. The methods presented
herein cannot only identify deviation costs, but can also identify the most
likely areas in which to reduce them on various types of future projects.
ACKNOWLEDGMENTS
s
Defect: a deviation of a severity sufficient to require corrective action.
e
Deviation: a departure from established requirements. A deviation may
be classified as an imperfection, nonconformance, or defect based on
its severity.
9
Deviation costs: the sum of those costs, including consequential costs
such as schedule impact, associated with the rejection or rework of a
product, process, or service due to a departure from established re-
quirements.
9
Error: any item or activity in a system that is performed incorrectly
resulting in a deviation, e.g., design error, fabrication error, construc-
tion error, etc. An error requires an evaluation to determine what
corrective action is necessary.
9
Imperfection: A deviation that does not affect the use or performance
of the product, process, or service. In practice, imperfections are de-
viations that are accepted as they are.
° Nonconformance: a deviation that occurs with a severity sufficient to
consider rejection of the product, process, or service. In some situations
the product, process, or service may be accepted as is; in other situations
it will require corrective action.
9
Omission: any part of a system, including design, construction, and
fabrication, that has been left out, resulting in a deviation. An omission
requires an appraisal to determine what corrective action is necessary.
9
Prevention: quality activities employed to avoid deviations, including
such activities as: quality systems development, quality program de-
velopment, feasibility studies, contractor/subcontractor evaluation, quality
orientation activities, and certification/qualification.
9
Project: all those elements associated with a facility from initial concept
to final disposition.
9
Project elements: the major phases of a project, which include: pre-
planning, design, procurement, construction, start-up, operation, and
final disposition.
9
Quality: conformance to established requirements (not a degree of
goodness).
9
Quality activities: those activities in a project directly associated with
prevention and appraisal.
9
Quality assurance: all those planned or systematic actions necessary to
provide adequate confidence that a product, process, or service will
conform to established requirements.
9
Quality control: inspection, test, evaluation, or other necessary action
to verify that a product, process, or service conforms to established
requirements.
9
Quality management: concerns the optimization of the quality activities
involved in producing a product, process, or service. As such, it includes
prevention and appraisal activities.
47
the description.
3. Does the description of the deviation give a significant indication of one
secondary descriptor with the others treated in passing?
Yes: Classify the deviation with the secondary descriptor indicated by
the detailed discussion.
No: Proceed to step 4.
4. Contact the project representative for help.
5. Based on the discussion with the project representative, is a descriptor
indicated?
Yes: Classify by the secondary descriptor indicated by the project rep-
resentative.
No: Classify as unknown.
49